Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MKO.V ·

Mako Mining Provides Q1 2022 Production Results

Production Results

LEGAL*55828338.1

1

595 Burrard Street, Suite 2833

Vancouver, BC V7X 1K8

Tel: (604) 646-1580

www.makominingcorp.com

TSX-V: MKO | OTCQX: MAKOF

Suite 700 - 838 West Hastings St.

Vancouver, BC - V6C 0A6

IR: (647) 203-8793

www.makominingcorp.com

TSX-V: MKO | OTCQX: MAKOF

April 27, 2022

TSX-V: MKO; OTCQX: MAKOF

Mako Mining Provides Q1 2022 Production Results

Mako Mining Corp. (TSX-V: MKO; OTCQX: MAKOF) (“Mako” or the “ Company”) is pleased to provide

first quarter 2022 (“Q1 2022”) production results from its San Albino gold mine (“San Albino”) in northern

Nicaragua, which is the third full quarter of production results since declaring commercial production on

July 1, 2021. Financial results for Q1 2022, including detailed reporting of our operating costs, are expected

along with our Q1 2022 Financial results in May.

Q1 2022 Production Highlights

• 49,780 tonnes mined containing 11,577 ounces of gold (“oz Au”) at a blended grade of 7.23

grams per tonne gold (“g/t Au”)

o 17,400 tonnes mined containing 8,723 oz Au from diluted vein material at 15.59 g/t Au

o 32,380 tonnes mined contain ing 2,854 oz Au from historical dump and other mineralized

material above cutoff grade (“historical dump + other”) at 2.74 g/t Au

o 17.9:1 strip ratio for Phase 1

o 30.5:1 strip ratio overall (including Phase 2 accelerated waste development)

• 46,869 tonnes milled containing 10,843 oz Au at a blended grade of 7.20 g/t Au

o 48% and 52% from diluted vein and HW/FW, respectively

o 596 tonnes per day (“tpd”) milled at 87% availability

o 85.6% gold recoveries (majority of material processed was fresh material)

• 148,050 tonnes in stockpile containing 11,269 oz Au at a blended grade of 2.37 g/t Au

• 9,280 oz Au recovered and 9,580 oz Au sold at an average realized price of US$ 1,870 per

ounce

Akiba Leisman, Chief Executive Officer of Mako states that, “ this quarter was the third full quarter of

commercial production at San Albino . The mine is performing well, where the diluted vein material

continues to positively reconcile to the resource model in grade and ounces, and mill throughput has been

running at above nameplate capacity of 500 tonnes per day, including all availability factors . The mi ll

averaged 596 tonnes per day for the quarter at 87% availability , which is a 22% improvement over the

previous quarter including mill availability (46,869 tonnes milled in Q1 2022 vs. 38,313 tonnes milled in Q4

2021). Replenishment of spare parts and minor adjustments to the plant improve d mill availability and

throughput for the first quarter of 2022 , and we expect to be running at or above nameplate capacity for

the foreseeable future. Now that the mill is processing mainly fresh material instead of the oxide material

from last year, recoveries were running at 85.6% , which is i nline with the 86% metallurgical recoveries

predicted in our December 2019 metallurgical update (see press release dated December 13, 2019). The

plant is going through a series of optimizations, expected to be completed in Q2 2022, and we are optimistic

that minor improvements in recoveries can be made thereafter. 9,580 ounces were sold and operating

LEGAL*55828338.1

2

cash flow fro m the mine remains robust, with exploration expenditures increasing, waste development

accelerating ahead of the rainy season, payables fully normalized from elevated levels during ramp -up,

and over US$4 million of principal being repaid since the end of Q4 2021 (over US$7 million of principal

since the end of Q3 2021).”

Table 1 – Production Results

* Includes historical dump, hanging wall, foot wall, historical muck and all other non-vein mineralized material above cutoff grade

**For the purpose of calculating revenue, payments to Sailfish are deducted from the Average Realized Price

Units Q3 2021 Q4 2021 Q1 2022

Mined

Diluted Vein

Tonnes t 14,329 17,500 17,400

Gold Grade g/t 15.80 16.94 15.59

Contained Gold oz 7,278 9,530 8,723

Historical Dump + Other*

Tonnes t 36,881 26,660 32,380

Gold Grade g/t 2.72 3.17 2.74

Contained Gold oz 3,220 2,720 2,854

Waste

Tonnes t 794,791 776,539 1,516,510

Strip Ratio Phase 1 15.5 17.6 17.9

Strip Ratio Total N.A N.A 30.5

Milled

Diluted Vein % 56% 51% 48%

Historical Dump + Other* % 44% 49% 52%

Tonnes t 33,441 38,313 46,869

Gold Grade g/t 8.25 9.01 7.20

Contained Gold oz 8,873 11,102 10,843

Mill Availability % 85% 82% 87%

Average Tonnes per Day t/day 429 507 596

Recovered

Recoveries % 92.9% 92.7% 85.6%

Gold Recovered oz 8,239 10,291 9,280

Gold Sold oz 8,280 9,588 9,580

Average Realized Price** US$/oz 1,783 1,797 1,870

w:o

LEGAL*55828338.1

3

Table 2 – Mining by phases Q1 2022

Table 3 – Quarter End Stockpile Statistics

* Includes stockpiles of mineralized material at the crusher.

** Includes historical dump, hanging wall, foot wall, historical muck and all other non-vein mineralized material above cutoff grade.

Mining

The mine averaged 553 tpd of diluted vein material and historical dump + other in Q1 2021 with a strip

ratio of 17.9 from the main West Pit, and 30.5x inclusive of the Central Pit (Arras Zone) and West Pit Phase

2 waste development (see Table 1). The stockpile is now 148,050 tonnes and is comprised of 2,959 tonnes

of diluted vein material at 7.95 g/t Au and 145,091 tonnes of historical dump + other at 2.25 g/t Au for a

total of 11,269 oz Au (see Table 3).

Since the end of March, most of the diluted vein material has been coming from 79% Porcelana Zone and

21% Arras Zone, which is being blended with historical dump + other at the mill. The Porcelana Zone,

which has the highest grade -thickness profile encountered at San Albino, is expected to make up the

majority of the diluted vein tonnes for the foreseeable future.

At the beginning of Q1, the pre -strip for phase 2 West Pit development commenced, and the mining

contractor was instructed to accelerate waste development prior to the start of rainy season in May. The

strip ratio just for the Phase 1 Pit was 17.9x and including the accelerated waste development it was 30.5x.

Units West Pit

Phase 1

West Pit

Phase 2

Arras

Zone Total

Ore Tonnes t 39,180 0 10,600 49,780

Au Grade g/t 7.82 N.A 5.07 7.23

Au Ounces oz 9,851 0 1,726 11,577

Waste Tonnes t 699,646 498,925 317,939 1,516,510

Strip Ratio w:t 17.9x N.A 30.0x 30.5x

Units Q3 2021 Q4 2021 Q1 2022

Diluted Vein*

Tonnes t 3,545 6,510 2,959

Gold Grade g/t 11.86 13.62 7.95

Contained Gold oz 1,352 2,850 756

Historical Dump + Other**

Tonnes t 125,486 132,092 145,091

Gold Grade g/t 2.38 2.35 2.25

Contained Gold oz 9,608 9,982 10,513

Total

Tonnes t 129,031 138,602 148,050

Gold Grade g/t 2.64 2.88 2.37

Contained Gold oz 10,960 12,832 11,269

LEGAL*55828338.1

4

Milling

All components of the 500 tpd gravity and carbon -in-leach processing plant have been fully operational

since the beginning of May 2021. During Q1, 2022, the plant has been averaging 596 tpd at 87% availability

(see Table 1). In the first quarter of 2022 the plant processed 47% diluted vein material and 53% historical

dump + other to achieve an average blended grade of 7.20 g/t Au and recovering an average of 85.6%

(see Table 1).

The first quarter of 2022 saw the mill operate at a throughput rate significantly higher than previous

quarters. This was due primarily to improved operational performance. The recovery was lower than

previous quarters due to the much higher amount of fresh feed which contains a higher amount of organic

carbon. Further mill optimization efforts , which include optimizing grind size and lowering cyanide

concentrations from the recycled plant water , are planned in the months ahead to more effectively treat

the increased quantity of fresh ore feeding the mill.

An additional carbon stripping vessel is being fabricated to increase stripping capacity in the elution circuit,

which is expected to be operational in Q3 2022. Wood and other debris from historical mining has impacted

the operating time of the existing carbon stripping circuit. Procedures implemented in the mine have been

effective in addressing some of the problems from debris from historic mining but an additional stripping

vessel is expected to fully debottleneck this part of the plant.

All of the above mentioned improvements to the processing plant have helped the plant achieve processing

rates of an average of 596 tpd in Q1 2022, with over 9,500 ounces of gold sold for the second consecutive

quarter (see Table 1).

Qualified Person

John Rust, a metallurgical engineer and qualified person (as defined under NI 43 -101) has read and

approved the technical information contained in this press release. Mr. Rust is a senior metallurgist and a

consultant to the Company.

On behalf of the Board,

Akiba Leisman

Chief Executive Officer

About Mako

Mako Mining Corp. is a publicly listed gold mining, development and exploration company. The Company

operates the high -grade San Albino gold mine in Nueva Segovia, Nicaragua, which ranks as one of the

highest-grade open pit gold mines globally. Mako’s primary objective is to operate San Albino profitably

and fund exploration of prospective targets on its district-scale land package.

LEGAL*55828338.1

5

For further information: Mako Mining Corp., Akiba Leisman, Chief Executive Officer, Telephone: 203-862-

7059, E -mail: [email protected] or visit our website at www.makominingcorp.com and

SEDAR www.sedar.com.

Forward-Looking Information: Statements contained herein, other than historical fact, may be considered “forward-

looking information” within the meaning of applicable securities laws. The forward -looking information contained

herein is based on the Company’s plans and certain expectations and assumptions, including that Q1, 2022 detailed

operating costs and financial results will be available in May 2022; that the replenishment of spare parts and minor

adjustments to the plant are expected to further improve mill availability for the first quarter of 2022 and beyond; that

we expect to be running at or above nameplate capacity for the foreseeable future; that p lant optimizations are

expected to be completed in Q2 2022, and that we are optimistic that minor improvements in recoveries can be made

thereafter; the Porcelana Zone is expected to make up the majority of the diluted vein tonnes for the foreseeable

future; now that the gravity circuit is operating continuously it is expected to improve recoveries and reduce

processing costs of the high -grade mineralization coming from the Porcelana Zone; the additional carbon stripping

vessel is expected to increase strip ping capacity in the elution circuit and be operational in Q2 2022; ;and that the

Company can operate San Albino profitably in order to fund exploration of prospective targets on its district -scale

land package. Such forward-looking information is subject to a variety of risks and uncertainties which could cause

actual events or results to differ materially from those reflected in the forward -looking information, including, without

limitation, the risk that the expected improvements noted will not be completed in the timeframes expected and/or will

lead to the improvements expected;that theCompany’s not successful in operating San Albino profitably and/or fund

its exploration of prospectus targets on its district -scale land package; political risks and uncertainties involving the

Company’s exploration properties; the inherent uncertainty of cost estimates and the potential for unexpected costs

and expense; commodity price fluctuations and other risks and uncertainties as disclosed in the Company’s publi c

disclosure filings on SEDAR at www.sedar.com. Such information contained herein represents management’s best

judgment as of the date hereof, based on information currently available and is included for the purposes of providing

investors with the Company’s expectations regarding the Company’s production results at San Albino gold project,

and may not be appropriate for other purposes. Mako does not undertake to update any forward-looking information,

except in accordance with applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the

TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.