Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MKO.V ·

Mako Mining Announces Q2 2025 Production Results Generating Record Gold Revenue of US$38.1 million and an Increase in Cash of US$18.2 million

Production Results Financials

595 Burrard Street, Suite 2833

Vancouver, BC V7X 1K8

Tel: (604) 646-1580

www.makominingcorp.com

TSX-V: MKO | OTCQX: MAKOF

Suite 700 - 838 West Hastings St.

Vancouver, BC - V6C 0A6

IR: (647) 203-8793

www.makominingcorp.com

TSX-V: MKO | OTCQX: MAKOF

July 14th, 2025

TSX-V: MKO; OTCQX: MAKOF

Mako Mining Announces Q2 2025 Production Results Generating Record Gold Revenue

of US$38.1 million and an Increase in Cash of US$18.2 million

Mako Mining Corp. (TSX-V: MKO; OTCQX: MAKOF) (“Mako” or the “Company”) is pleased to provide

second quarter 2025 (“Q2 2025”) production results for the Company’s San Albino gold mine (“San

Albino”) in northern Nicaragua, the Moss Mine in Arizona and an update on the Eagle Mountain gold

project in Guyana. Certain amounts shown in this news release may not total to exact amounts due to

rounding differences. All amounts expressed in U.S. dollars unless otherwise noted.

Q2 2025 San Albino Operational Highlights

• 54,354 tonnes mined, containing 10,911 ounces (“oz”) of gold (“Au”) at an average grade of

6.24 grams per tonne (“g/t”) Au and 12,491 oz of silver (“Ag”) at 7.15 g/t Ag

o 25,022 tonnes mined from diluted vein material containing 7,981 oz Au at 9.92 g/t Au and 8,829

oz Ag at 10.97 g/t Ag

o 29,332 tonnes mined from historical dump and other mineralized material above cutoff grade

(“historical dump + other”) containing 2,930 oz Au at 3.11 g/t Au and 3,662 oz Ag at 3.88 g/t

Ag

o 38.3:1 strip ratio (1)

• 52,705 tonnes milled containing 11,153 oz Au and 12,847 oz Ag grading 6.58 g/t Au and 7.58

g/t Ag

o 41% and 59% from diluted vein and historical dump and other, respectively

o 595 tonnes per day (“tpd”) milled at 97% availability

o Mill recovery of 80.3% for gold

• At quarter end, the stockpile was estimated at 127,897 tonnes at an average grade of 2. 52

g/t Au for contained Au of 10,352 oz

Q2 2025 Mako Financial Highlights

• Mako total gold sales of 11,476 oz Au for total revenue of $38.1 million in Q2 2025

o San Albino Mine sales of 10,104 oz Au at $3,323 per ounce

o Moss Mine sales of 1,372 oz Au from residual leaching activities at $3,321 per ounce

• Delivered final 13,500 oz silver payment to Sailfish Silver Loan for a total of $0.4 million in

Q2 2025

• $1.5 million release of collateral at Moss Mine from Trisura Guarantee Insurance Company

• Cash Balance of $28.6 million as of June 30th, 2025

LEGAL*57291589.1

2

Akiba Leisman, Chief Executive Officer of Mako states that “in Q2 2025 we generated US$38.1 million in

revenue, a record for the Company. Gold sales of 10,104 ounces were similar to the previous two quarters;

however, realized gold prices of $3,323 per ounce were substantially higher. This was the first full quarter

the Company owned the Moss Mine, with 1,372 gold ounces sold from the residual leach operations. After

reinvesting cash flow in exploration in Nicaragua, rapidly advancing the Eagle Mountain project in Guyana,

and preparing for the restart of mining operations at the Moss Mine in Arizona, the Company managed to

increase cash on the balance sheet by US$18.2 million to US$28.6 million, which gives an indication as to

how profitable our current min ing assets are. This cash will be used for the eventual construction of the

Eagle Mountain project next year.”

Table 1 – Operating Results for San Albino

Units Q3 2024 Q4 2024 Q1 2025 Q2 2025

Mined

Diluted Vein

Tonnes t 6,781 24,819 29,163 25,022

Gold Grade g/t 12.72 14.81 10.26 9.92

Silver Grade g/t 12.02 13.06 10.43 10.97

Contained Gold oz 2,774 11,818 9,620 7,981

Contained Silver oz 2,620 10,419 9,777 8,829

Historical Dump + Other*

Tonnes t 22,968 21,913 19,650 29,332

Gold Grade g/t 3.57 3.97 2.97 3.11

Silver Grade g/t 3.98 3.87 3.58 3.88

Contained Gold oz 2,640 2,799 1,875 2,930

Contained Silver oz 2,937 2,728 2,259 3,662

Waste

Tonnes t 758,401 1,287,997 2,272,474 2,081,322

Phase 2 - Capitalized Waste t 1,286,632 614,119 0 177,544

Strip Ratio (1) w:o 29.4 27.6 46.6 38.3

Milled

Diluted Vein % 14% 49% 52% 41%

Historical Dump + Other* % 86% 51% 48% 59%

Tonnes t 51,865 51,242 53,551 52,705

Gold Grade g/t 4.20 8.60 7.10 6.58

Silver Grade g/t 5.08 8.17 7.40 7.58

Contained Gold oz 7,002 14,175 12,228 11,153

Contained Silver oz 8,479 13,453 12,740 12,847

Mill Availability % 96% 97% 98% 97%

Average Tonnes per Day t/day 584 576 608 595

Recovered

Gold Recovery % 73.4% 85.0% 85.3% 80.3%

Gold Recovered oz 5,142 12,053 10,436 8,961

Gold Equiv. Recovered (2) oz 5,210 12,182 10,553 9,063

Gold Sold oz 6,532 10,803 9,881 10,104

Gold Equiv. Sold (2) oz 6,641 10,873 10,021 10,194

Avg. Realized Price Gold ** US$/oz 2,470 2,670 2,898 3,323

Avg. Realized Price Silver US$/oz 29 31 32 33

LEGAL*57291589.1

3

* Includes historical dump, hanging wall, footwall, historical muck and all other non-vein mineralized material above cutoff grade.

**For the purpose of calculating revenue, payments to Sailfish are deducted from the Average Realized Price Gold.

(1) Strip Ratio calculation does not include waste material that is capitalized

(2) Equivalent Gold ounces are calculated by: Silver recovered. or Silver sold (oz) / Avg. Realized Price Gold ($/oz) / Avg. Realized Price Silver

($/oz)

Table 2 – San Albino Quarter-End Stockpile Statistics

** Includes historical dump, hanging wall, footwall, historical muck and all other non-vein mineralized material above cutoff grade.

Mining at San Albino

In Q2 2025, the mine produced an average of 597 tonnes per day of diluted vein, historical dump and other

material. The average strip ratio (which excludes capitalized waste material) was 38.3:1. The Diluted vein

material was sourced from six different veins: Las Conchitas South ( Bayacun-Limon-Mango 35%, Las

Dolores 22%) and Las Conchitas Central (Intermediate 32% and Cruz Grande 11%).

Milling at San Albino

During Q2 2025, the plant throughput rate averaged 595 tpd, 19% above nameplate capacity. Mill

availability remained high at 97% which compares favorably with industry averages. The mill head grade

averaged 6.58 g/t Au, comprised of 41% diluted vein material and 59% historical dump + other material. A

total of 8,961 ounces of gold were recovered during the quarter at a mill recovery of 80.3%.

Moss Mine

In Q2 2025, r esidual leaching continue d at the Moss Mine, with gold sales of 1,372 oz. The Company

engaged a new mining contractor on June 10 th with the mine receiving an initial delivery of mining

equipment with the full fleet expected to arrive by early August. There are currently over 80,000 tonnes of

material already blasted that are waiting to be excavated, hauled and crushed through the fully refurbished

10,000 tonnes per day plant. The Company expects to restart mining operations in early Q3 2025, with

steady state production expected by the end of the year.

Eagle Mountain Gold Project

The H1 2025 work program included engineering and environmental activities to confirm mine design

parameters and to generate the baseline environmental data and other studies required to complete an

Environmental Impact Assessment (“EIA”) for submission to the Guyana Environmental Protection Agency

(“EPA”). The Company anticipates submission of the draft EIS to the EPA in H2 2025.

Phase 2 geotechnical activities, which commenced in Q1 2025, comprised drilling and testing of the

saprolite and underlying fresh rock to facilitate infrastructure siting studies and site hydrogeological drilling

and hydrology testing to generate data for both pit optimization and water resource management studies.

Units Q3 2024 Q4 2024 Q1 2025 Q2 2025

Historical Dump + Other**

Tonnes t 135,496 130,987 126,248 127,897

Gold Grade g/t 2.49 2.69 2.61 2.52

Contained Gold oz 10,849 11,327 10,587 10,352

LEGAL*57291589.1

4

H1 2025 activities also included environmental geochemical testing of water, soils, and rock and

metallurgical tests to produce representative tailings samples for environmental modelling.

In March, the Company advanced permitting efforts for the Eagle Mountain Project with the submission of

comprehensive Environmental Application and Project Summary documents to the Guyana EPA, marking

a critical step in the regulatory approval process. Subsequently, in May, Mako hosted EPA officials at the

Eagle Mountain site.

On behalf of the Board,

Akiba Leisman

Chief Executive Officer

Qualified Person

John Rust, a metallurgical engineer and qualified person (as defined under NI 43 -101) has read and

approved the technical information contained in this press release. Mr. Rust is a senior metallurgist and a

consultant to the Company.

About Mako

Mako Mining Corp. is a publicly listed gold mining, development and exploration company. The Company

operates the high-grade San Albino gold mine in Nueva Segovia, Nicaragua, which ranks as one of the

highest-grade open pit gold mines globally and offers district-scale exploration potential. Mako also owns

the Moss Mine in Arizona, an open pit gold mine in northwestern Arizona. Mako also holds a 100% interest

in the PEA -stage Eagle Mountain Project in Guyana, South America. Eagle Mountain is the subject of

engineering, environmental and mine permitting activity.

For further information: Mako Mining Corp., Akiba Leisman, Chief Executive Officer, Telephone: 917-558-

5289, E -mail: [email protected] or visit our website at www.makominingcorp.com and

SEDAR www.sedarplus.ca.

Forward-Looking Information: Statements contained herein, other than historical fact, may be considered “forward -looking

information” within the meaning of applicable securities laws. The forward -looking information contained herein is based on the

Company’s plans and expectations and assumptions as of the date such statements forward looking statements include that :

expectations stated regarding Q2 and Q3 2025 production at San Albino, expected timing for the submission of the EIS to the

Guyana EPA. Such forward-looking information is subject to a variety of risks and uncertainties which could cause actual events

or results to differ materially from those reflected in the forward -looking information, including, without limitation; that production

results in Q2 and Q3 2025 will not meet expectations; that the EIS will not be submitted on the timeline expected; uncertainty

related to mining exploration properties; political risks and uncertainties involving the Company’s mineral properties; the inherent

uncertainty of cost estimates and the potential for unexpected costs and expense; commodity price fluctuations and other risk s

and uncertainties as disclosed in the Company’s public disclosure filings on SEDAR + at www.sedarplus.ca. Such information

contained herein represents management’s best judgment as of the date hereof, based on information currently available and is

included for the purposes of providing investors with the Company’s expectations regarding the Company’s Q2 2025 production

and operating results at San Albino gold project, financial highlights for Q2 2025 and current corporate updates, and may not be

appropriate for other purposes. Mako does not undertake to update any forward -looking information, except in accordance with

applicable securities laws.

LEGAL*57291589.1

5

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.