Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MKA.V ·

Mkango Announces Results of Updated Feasibility Study FOR the Songwe Hill Rare Earths Project IN Malawi and Pre-Feasibility Results FOR the Proposed Puławy Rare Earth Separation Plant IN Poland

Economic Studies

THIS NEWS RELEASE IS INTENDED FOR DISTRIBUTION IN CANADA AND THE UNITED

KINGDOM ONLY AND IS NOT FOR DISTRIBUTION, DIRECTLY OR INDIRECTLY, IN OR INTO

THE UNITED STATES (INCLUDING ITS TERRITORIES AND POSSESSIONS, ANY STATE OF

THE UNITED STATES OR THE DISTRICT OF COLUMBIA), OR ANY JURISDICTION WHERE TO

DO SO WOULD CONSTITUTE A VIOLATION OF THE RELEVANT LAWS OF SUCH

JURISDICTION.

MKANGO RESOURCES LTD.

550 Burrard Street

Suite 2900

Vancouver

BC V6C 0A3

Canada

MKANGO ANNOUNCES RESULTS OF UPDATED FEASIBILITY STUDY FOR THE SONGWE

HILL RARE EARTHS PROJECT IN MALAWI AND PRE-FEASIBILITY RESULTS FOR THE

PROPOSED PUŁAWY RARE EARTH SEPARATION PLANT IN POLAND

London / Vancouver: March 19 , 2026 – Mkango Resources Ltd. (AIM/TSX -V: MKA) (the

“Company” or “Mkango”) is pleased to announce the results of the updated definitive feasibility study

(“DFS”) for the Songwe Hill Rare Earths Project (“Songwe” or the “Project”) in Malawi, and results of

a pre-feasibility study (“PFS”) for the proposed Puławy Rare Earths Separation Plant (“Puławy”) in

Poland.

Alexander Lemon, President of Mkango commented: "We are delighted to announce the results of

our updated NI 43-101 DFS for the Songwe Hill Rare Earths project and the PFS results for the Puławy

Rare Earth Separation Plant. Incorporating revised rare earth pricing, capital and operating cost

assumptions, these studies reflect our commitment to moving these high -quality projects forward. As

one of the few companies in the sector to update feasibility studies with current market pricing, Mkango

is uniquely pos itioned as a future supplier of both mined and recycled rare earths — a critical

differentiator as global demand for green transition materials accelerates. Songwe in Malawi and

Puławy in Poland are landmark projects for the communities and economies they are expected to

transform and our mission to deliver sustainable, long-term value for our shareholders."

Based on updated feasibility -study inputs and assumptions regarding rare earth pricing, production

volumes, recoveries, capital and operating costs, discount rates, tax regimes, project schedules, and

market demand forecasts, as well as the technical, envi ronmental and regulatory parameters set out in

the DFS and PFS and as summarised in this release (the “Study-level Assumptions”), selected study-

level outputs from the DFS and PFS include:

● Songwe is among the very few rare earths projects globally to have achieved the DFS stage,

with a Mining Development Agreement, a full Environmental, Social, Health Impact Assessment

(“ESHIA”) completed in compliance with IFC Performance Standards. The Global Industry

Standard on Tailings Management (2020) (“GISTM”) has been adopted for design and

management of the tailings storage facility, as well as Songwe being selected as a strategic project

under the European Union Critical Raw Materials Act (“CRMA”).

• Songwe will produce a value -add purified mixed rare earth carbonate (“MREC”)

product, which can be sold into international markets and is suitable for the proposed

Puławy separation plant in Poland.

• Neodymium, praseodymium, dysprosium and terbium are critical for the green

transition, used in permanent magnets for electric vehicles, wind turbines and many

electronic devices.

● Operating life of 18 years for Songwe, with production averaging 5,954 tonnes per year

total rare earth oxides (“TREO”) for the first full five years of production, including 1,953

tonnes per year of neodymium and praseodymium oxides, and 56 tonnes per year of

dysprosium and terbium oxides, in a MREC grading 55% TREO (dry basis).

● Songwe i nitial capital expenditure (“capex”) of approximately US$325.5 million

(including a US$27.8 million contingency) for development of mine, mill, flotation and

hydrometallurgy plants, tailings storage facility, and related project infrastructure in

Malawi.

● Puławy initial plant capex of approximately US$212 million (including a US$35.4 million

contingency) for development of a Rare Earth Separation plant and related project

infrastructure in Poland.

● Songwe post-tax net present value (“NPV”) of approximately US$339 million, using a

10% nominal discount rate, with an internal rate of return (“IRR”) of 24%, payback

period of 3.4 years from start of full production and post -tax life-of-operations nominal

cash flow of US$1.55 billion.

● Puławy post-tax NPV of approximately US$779 million, using a 10% nominal discount

rate, with an IRR of 40%, payback period of 2.12 years from start of full production and

post-tax life-of-operations nominal cash flow of US$4.95 billion.

● Applying Adamas Intelligence upside forecasts 1, Songwe's post -tax NPV increases to

approximately US$489 million with a nominal IRR of 29%, payback period of 2.9 years

from start of full production and post -tax life-of-operations nominal cash flow of $2.04

billion while Puławy's expanded 100% neodymium/praseodymium (“NdPr”) separation

case rises to a post-tax NPV of approximately US$892 million and nominal IRR of 43%,

payback period of 1.89 years from start of full production and post-tax life-of-operations

nominal cash flow of $5.58 billion.

Summary of Selected Financial DFS-level outputs for Songwe Hill – Post-Tax Basis

Item Unit Value

Life of operations post-tax nominal cash flow US$ million 1,554.0

Payback period from project start1 Years 5.9

Payback period from start of full production Years 3.4

Post-tax NPV at 10% (nominal) discount rate US$ million 339.5

Post-tax IRR (nominal) % 24.3

1 Recent REO price movements have driven Nd & Pr oxide prices to levels broadly aligned with Adamas

Intelligence's Q4 2025 base case pricing report for 2028 and upside case for 2030– 2031, providing support for

the forecast scenario.

1 Assumes project start i.e. start of capital expenditure in July 2027.

2 Figures based on Mkango owning all of the shares of Mkango Rare Earths Limited (“ MKAR”). Mkango’s

interest in MKAR will be diluted following the proposed business combination with Crown Proptech Acquisitions

and related proposed listing on Nasdaq of the MKAR shares to a significant majority interest, subject to the final

transaction structure. It is expected that MKAR will be a “controlled company” for Nasdaq listing purposes.

Songwe - Project Overview

Mkango appointed SENET, a DRA Global company, as the principal consultant to complete the original

and the updated DFS. SENET is a leading engineering, procurement and construction management

(EPCM) minerals processing and project delivery firm located in Africa. Other primary consultants for

the updated DFS included the following:

Geology, Mineral Resource, and Geotechnical Investigation: The MSA Group (Pty) Ltd (“MSA”)

Mining: Bara Consulting (Pty) Ltd (“Bara”)

Comminution: Grinding Solutions Limited (“Grinding Solutions”), Keramos

Process Plant including On- Site and Off -Site Infrastructure: SENET, a DRA Global Company

(“SENET”)

Hydrometallurgy: Australian Nuclear Science and Technology Organisation (“ANSTO”)

Flotation: KYSPY Investments (Pty) Ltd (“ KYSPYmet”), ALS Metallurgy (Pty) Ltd (“ ALS

Metallurgy”)

Tailings Storage Facility (TSF): Epoch Resources (Pty) Ltd (“Epoch”)

Environmental, Social and Health Impact Assessment (ESHIA): Digby Wells and Associates (Pty)

Ltd (“Digby Wells Environmental”), Kongiwe Environmental (Pty) Ltd

Geochemistry: SGS Australia (Pty) Ltd

Geotechnical testwork: Western Geotechnical and Laboratory Services

Logistics: C. Steinweg Bridge (Pty) Ltd

Market Intelligence: Adamas Intelligence Inc (“Adamas”)

The DFS is based on a conventional open pit contract mining operation, feeding mills, flotation and

hydrometallurgy plants on site in Malawi to produce a MREC, with an operating life (mining and

processing) of 18 years. The Company believes there is potent ial to increase the mine life given the

additional Inferred Resource, and the potential to expand the Mineral Resource. The DFS supports the

declaration of a Proven and Probable Mineral Reserve Estimate of 18.1 million tonnes grading 1.16%

TREO.

Songwe features broad zones of outcropping rare earth mineralisation on the northern slopes of a steep

sided hill. The annual processing capacity is assumed to be approximately 1.0 million tonnes per year

of ore producing an average of 5, 954 tonnes of TREO in MREC per year for the first five years and 4,

081 tonnes of TREO in MREC per year in years 6 to 18. The MREC will be cerium depleted. Because

cerium is currently considered to have challenging market fundamentals, there is a strong economic

rationale to remove as much cerium as possible and, as a result, a large proportion of the cerium will be

removed from the MREC during the hydrometallurgical process. Confirmation of the flotation and

hydrometallurgical processing flow sheets was underpinned by seven piloting campaigns at ALS

Metallurgy and ANSTO.

The final stage of hydrometallurgical piloting at ANSTO produced MREC grading 55% TREO

equivalent, enriched in Nd/Pr oxides, which together made up 31% of the rare earth oxide content in

the carbonate product (i.e. Nd/Pr oxides / TREO = 31%).

Energy supply of 25 megawatts (“MW”) is expected to be obtained from the Malawi grid network for

the Project, which in Malawi is from hydroelectric and solar sources. A 25 MW back up solar farm with

battery storage and diesel generators is also expected to be installed.

The MREC is expected to be exported via largely existing infrastructure. The Project is located

approximately 95 km by road from Blantyre, the largest commercial centre in Malawi, which is served

by a rail head and international airport.

There have been significant improvements to local infrastructure in recent years. The Malawi Roads

Authority has upgraded an existing government road from nearby Migowi to the Songwe Hill project

site. This 15 -km government road has been upgraded and widened to an all-weather gravel road with

reinforced concrete culverts, embankments and bridges installed.

The MREC is expected to be sold to the proposed Puławy project in Poland for separation. The DFS is

based on the sale of MREC. The Puławy PFS, completed by PRODEO Consulting (Pty) Ltd and dated

19 March, 2026, indicates a separation cost of approximately US$2.142 per kilogram of TREO in

MREC to produce the designated product suite at Puławy. The PFS forecasts a separation plant CAPEX

for the proposed separation plant (expanded capacity, 100% separation plant option) targeted at

approximately US$212 million3.

Based on the Study- level Assumptions, the following summary of the key inputs and results of the

updated Songwe DFS is presented in the tables below:

Summary of Mining and Processing Inputs and Results – Average over First Full Five Years

Item Unit Value

Mining

Average yearly ore mined kt 2,186

Average TREO grade mined % 1.19

Average yearly waste mined kt 3,667

Average strip ratio (waste:ore) 1.68

Processing

Average yearly flotation plant feed kt 1,000.8

Average plant feed TREO grade % 1.50

Flotation TREO concentrate grade % 15.05

Average TREO recovery to concentrate % 74.10

2 The OPEX estimate was developed to the level of accuracy required for an AACE Class 4 estimate (an overall

weighted accuracy of ±25%). The OPEX estimate has a base date of 25 February 2026, with no provision for

escalation.

3 The CAPEX estimate was developed to the level of accuracy required for an AACE Class 4 estimate (an overall

weighted accuracy of ±25%). The CAPEX estimate has a base date of 25 February 2026, with no provision for

escalation.

Average yearly flotation concentrate feed to hydrometallurgical plant kt 74.06

Average NdPr oxide hydrometallurgical recovery to carbonate % 85.3

Average Ce oxide hydrometallurgical recovery to carbonate % 20.9

Average yearly TREOs in carbonate product t 5,954

Average carbonate TREO grade % 55

Average yearly carbonate production (dry basis) t 10,826

Summary of Mining and Processing Inputs and Results – Life of Operations (averages)

Item Unit Value

Life of operations (mining and processing) Years 18

Mining

Average yearly ore mined kt 1,481

Average TREO grade mined % 1.16

Average yearly waste mined kt 3,311

Average strip ratio (waste:ore) 2.2

Processing

Average yearly flotation plant feed kt 1,000.8

Average plant feed TREO grade % 1.16

Flotation TREO concentrate grade % 11.64

Average TREO recovery to concentrate % 74.10

Average yearly flotation concentrate feed to

hydrometallurgical plant

kt 74.06

Average NdPr oxide hydrometallurgical recovery to carbonate % 85.3

Average Ce oxide hydrometallurgical recovery to carbonate % 20.9

Average yearly TREOs in carbonate product t 4,634

Average carbonate TREO grade % 55.00

Average yearly carbonate production (dry basis) t 8,425

Summary of Mining and Processing Inputs and Results – Life of Operations (totals)

Item Unit Value

Mining

Total ore mined kt 18,147.8

Total waste mined kt 40,553.9

Strip ratio (waste: ore) 2.2

Processing

Total flotation concentrate feed to hydrometallurgical plant kt 1,341.4

Total contained TREO in carbonate product kt 83.4

Total carbonate production (dry basis) t 151,644

Market and Financial Analysis

A detailed financial model was constructed based on input parameters and the Study-level Assumptions

set out in the DFS. Free cash flows were modelled in both real and nominal terms for a range of discount

rates and on a debt free basis.

MREC price forecasts and underlying rare earth oxide (“REO”) price forecasts were based on the

following current market analysis by Adamas Intelligence from their Q4 2025 dated report entitled Rare

Earth Market Outlook: Independent Analysis for Inclusion in Mkango Resources’ Songwe Hill

Feasibility Study (the “Adamas Analysis”). Adamas Intelligence highlights that from 2024 through

2040:

• Global demand for NdFeB magnets is expected to increase at a compound annual growth rate

(“CAGR”) of 8.5%, bolstered by double-digit growth from the electric vehicle and wind power

sectors, translating into comparable demand growth for the rare earth elements (“REEs”) (i.e.,

neodymium, praseodymium, dysprosium and terbium) that these magnets contain.

• Global production of neodymium, praseodymium, dysprosium and terbium are forecast to

collectively increase at a slower CAGR of 7.4 % as the supply side of the market increasingly

struggles to keep up with rapidly growing demand.

Based on the Adamas Analysis, from 2024 through 2040, the global rare earth industry is expected to

consistently underproduce neodymium, praseodymium, dysprosium and terbium oxides (or oxide

equivalents), resulting in the depletion of historically accumulated inventories and, ultimately, shortages

of these critical magnet materials if supply is not increased beyond the levels currently anticipated.

Songwe offers strong economic exposure to the rare earth permanent magnet sector, which is the fastest-

growing end-use category for rare earths and the one most in need of additional rare earth supplies.

Based on the DFS metallurgical recoveries, MREC composition, and the Adamas Analysis, the DFS

indicates that the high proportion of valuable magnet -related REEs in the Songwe Hill project’s

prospective TREO production means that a future mine (with separation) could generate approximately

95% of its rare earth revenues from just 34% of its production volume.

Adamas Intelligence forecasts the following for the basket value (real 2025 US dollars) of Songwe

Hill’s TREO production:

• Base case: US$28.40/kg in 2025 increasing to US$69.60/kg in 2034

• Upside scenario: US$28.91/kg in 2025 increasing to US$79.39/kg in 2034

The key revenue drivers for Songwe are neodymium and praseodymium. The base case basket value

and MREC price forecasts reflect underlying neodymium oxide (Nd oxide) and praseodymium oxide

(Pr oxide) price forecasts.

Based on the preceding assumptions and the other Study-level Assumptions, the discounted cash flow

valuation analysis for the base case in the DFS provided the following results:

• NPV at 10% (nominal) (7.3% real) of US$339 million as at 30 June 2025

• IRR of 24.3% (nominal) (21.3% real)

These are project-level economic assessment outputs used to evaluate potential economic viability and

do not constitute corporate -level forecasts or guidance. Actual results may differ materially if Study -

level Assumptions change.

NPVs of Songwe Hill Project1

Financial

Evaluation

Nominal

Discount

Rate

(%)

Real

Discount

Rate

(%)

Adamas Intelligence

Base Case

Post-Tax NPV

(US$m)

Adamas Intelligence

Upside Case

Post-Tax NPV

(US$m)

8.0 5.37 461.2 644.8

Base Case 10.0 7.32 339.5 488.5

12.0 9.27 247.3 369.8

Nominal Internal Rate of Return 24.3% 29.3%

Real Internal Rate of Return 21.3% 26.1%

1 As at 30 June 2025

Operating Costs

Cash operating costs include the costs of contract mining, milling, flotation, leaching, purification and

precipitation to produce a MREC in addition to other costs associated with the operation. The operating

costs do not include the cost of separation, which is reflected in the 15% discount applied to the basket

value of the REOs in MREC. The estimate of operating expenditure (“ OPEX”), and the associated

general and administration (“G&A”) costs, were calculated to an accuracy of ±10% and were utilised

in the economic analysis of the Project.

Reagents and consumables account for 49% of estimated OPEX , with power accounting for an

additional 13%. The Company and SENET, together with the Company’s other consultants, have

identified opportunities to reduce reagent consumption and optimise the flowsheet. This will be

investigated further in parallel with front end engineering and design (“FEED”) work for Songwe.

Operating Costs – Average over First Full Five Years

Item Value (US$/kg TREO)

Mining 5.4

Beneficiation – Milling and Flotation 9.1

Hydrometallurgical Plant 5.2

G&A and Other 2.5

Total Operating Costs 22.3

Operating Costs – Average over Life of Operations

Item Value (US$/kg TREO)

Mining 4.4

Beneficiation – Milling and Flotation 11.6

Hydrometallurgical Plant 6.8

G&A and Other 3.2

Total Operating Costs 26.1

Capital Expenditure

The estimate of initial capital expenditure costs was calculated to an accuracy of ±10% and was utilised

in the economic analysis of the Project. The largest capex component is an integrated processing plant

comprising a mill, flotation plant, hydrometallurgical plant, and a sulphuric acid plant with co-generated

power capacity. The capex estimate for the integrated processing plant was completed by SENET and

covers the design, engineering, procurement, supply/manufacture, construction and pre-commissioning

of the proposed new processing facility and associated plant complex infrastructure including a 24.4

MW solar facility. Other major capex items include the cost of a lined tailings storage facility with

design provided by Epoch.

Based on the Study-level Assumptions in the DFS, total initial capital expenditure is US$297.8 million,

not including a contingency of US$27.8 million.

Capital Cost Summary

Item Value (US$ million)

Total Development Capital 297.8

Contingency 27.8

Total Development Capital Including Contingency 325.5

Sustaining capital and reclamation 91.5

Total Capital Expenditure 417.0

Capital Cost Breakdown

Description CAPEX (US$) Contingency (US$) Total CAPEX (US$)

Earthworks 8,151,015 776,287 8,927,303

Civil Works – Plant 19,480,113 2,060,397 21,540,510

Civil Works – Infrastructure 2,068,686 197,018 2,265,704

Infrastructure 2,918,556 138,979 3,057,535

Structural Steel 6,345,323 423,022 6,768,345

Plate Work 2,658,354 177,224 2,835,578

Tankage 4,332,050 322,047 4,654,097

Machinery and Equipment 52,477,378 2,894,436 55,371,814