Majestic GOLD Corp. – Shareholder’S Update

Corporate Updates

MAJESTIC GOLD CORP. – SHAREHOLDER’S UPDATE

Vancouver, British Columbia – June 14, 2019 - Majestic Gold Corp. (“Majestic” or the “Company”)

(TSX.V: MJS, FSE: A0BK1D) is pleased to provide a shareholder’s update on its operations at the

Songjiagou Gold property (“Songjiagou”) in conjunction with the Company’s Annual General Meeting held

on June 13, 2019.

Production at Majestic’s operation at Songjiagou continues to rely mainly on the open pit that has been in

commercial production since May 2011. During 2018, test mining from underground at Songjiagou North

contributed higher grade material from test stopes in the u pper two levels of what will ultimately be

developed into a six-level underground mine.

Songjiagou Gold Mine

The overall operation of the open pit at Songjiagou is still benefiting from amendments to the mining

agreement in early 2017 and by processing higher grade material. Continued optimization of the operation

has resulted in achieving even lower total cash costs and all-in sustaining costs that were down to $614 and

$712 per ounce respectively for the first six months of fiscal 2019. Gold production for fiscal year 2018 was

29,160 ounces, a 15% increase in production over the prior 2017 fiscal year . This increase was mostly due

to an increase in head grade from 0.55 g/t in 2017 to 0.64 g/t in 2018.

A significant portion of the past 15 months has been dedicated to work on reducing the angle of the

northwestern pit slope, which also included reclamation work on the upper levels of the pit. Extensive work

has also been done on road access in and out of the pit and improving the road from the pit to the mill facility

in anticipation of increased traffic once increases to mining in the pit are initiated . As a result , mining

production in the pit has experienced a decline during this period of work. The Company anticipates that

production will ramp up in early fiscal 2020.

Songjiagou North Underground

The focus of work at the underground operation at Songjiagou during the past year was on development of the

upper levels as the ramp advanced toward the deepest of the six levels at -160 metres above sea level. Test mining

from the +49 and +9 meter levels began during the first six months of fiscal 2019 at an average rate of 220 tonnes

per day with a grade of 2.53 g/t which provided the mill with higher grade material to mix with mill feed from

the open pit. Final government approvals are required before the underground can run at full capacity; it is

anticipated that these approvals will be granted in late fiscal 2019.

Songjiagou North Underground is expected to produce about 90,000 tonnes of ore annually or about 250-275

tonnes per day averaging about 2.4 g/t gold which should add almost 7,000 ounces of gold to yearly production.

The underground development has been designed to mine four discrete gold-rich veins that are a continuation of

mineralization that is being developed in the open pit.

Village Relocation

Construction of the main buildings that will house villagers who currently live in close proximity to

operations at Songjiagou has been completed and has been inspected and approved. Some minor work on

the exterior of the grounds is ongoing and will be complete d in the next 2 -3 months. Approximately 180

306 - 1688 152nd Street

Surrey, British Columbia

Canada, V4A 4N2

Telephone: 604-560-9060

Facsimile: 604-560-9062

Email: [email protected]

families will move into the complex by the end of fiscal 2019, while retaining their farmland and holding a

75-year condominium lease.

Corporate Development

The Company continues to monitor progress at Yantai Baiheng Gold Mining Co. Ltd.’s (“Baiheng”) Shuang

Shan Tun and Xia Yu Cun properties of which the Company holds an option (see August 12, 2015 News

Release). At Shuang Shan Tun, Baiheng is progressing with pre-production level development targeting the

M7 Vein which hosts almost 80% of the mineralized material discovered by deep drilling at Shuang Shan

Tun.

Annual General Meeting

The Company announces that all of the resolutions set out in the Company’s Notice of Meeting for its Annual

General Meeting of Shareholders held on June 13, 2019 were approved by the shareholders, including the

election of the six directors nominated by management as put forth in the Information Circular.

Stephen Kenwood, P. Geo., a Director of Majestic, is the Qualified Person within the context of National

Instrument 43-101 and has read and approved this news release.

About Majestic Gold

Currently focused solely in China, Majestic Gold Corp. is a British Columbia based company engaged in

commercial gold production at the Songjiagou Gold Mine in eastern Shandong Province, China. Additional

information on the Company and its projects is available at www.sedar.com and on the Company’s website

at www.majesticgold.com.

For further information, please contact:

Stephen Kenwood, P.Geo., President and CEO

Telephone: (604) 560-9060

Email: [email protected]

Website: www.majesticgold.com

Cautionary Notes

Certain statements contained herein may constitute forward‐looking statements and are made pursuant to the

"safe harbor" provisions of the United States Private Securities Litigation Reform Act of 1995 and Canadian

securities laws. Forward‐looking statements are statements which relate to future events. Such statements include

estimates, forecasts and statements as to management's expectations with respect to, among other things, business

and financial prospects, financial multiples and accretion estimates, future trends, plans, strategies, objectives and

expectations, including with respect to production, exploration drilling, reserves and resources, exploitation

activities and events or future operations. Information inferred from the interpretation of drilling results and

information concerning mineral resource estimates may also be deemed to be forward ‐looking statements, as it

constitutes a prediction of what might be found to be present when, and if, a project is actually developed.

In some cases, you can identify forward‐looking statements by terminol ogy such as "may", "should", "expects",

"plans, "anticipates", believes", "estimates", "predicts", "potential", or "continue" or the negative of these terms or

other comparable terminology. These statements are only predictions and involve known and unknow n risks,

uncertainties and other factors that may cause our or our industry's actual results, level of activity, performance

or achievements to be materially different from any future results, levels of activity, performance, or achievements

expressed or implied by these forward‐looking statements.

While these forward‐looking statements, and any assumptions upon which they are based, are made in good faith

and reflect our current judgment regarding the direction of our business, actual results will almost always vary,

sometimes materially, from any estimates, predictions, projections, assumptions or other future performance

suggestions herein. Except as required by applicable law, Majestic Gold does not intend to update any forward‐

looking statements to conform these statements to actual results.