Metal Energy Updates on Flagship High-Grade Nickel Manibridge Project Phase 1's 3,000 metre drill program is expected to begin in early March Advance team on site next week to prepare drill pads A property wide magnetotellurics survey scheduled for May, with Phase 2's 10,000 metre drill

Exploration Programs

Metal Energy Updates on Flagship High-Grade

Nickel Manibridge Project

Phase 1's 3,000 metre drill program is expected to begin in early March

Advance team on site next week to prepare drill pads

A property wide magnetotellurics survey scheduled for May, with Phase 2's 10,000 metre drill

program thereafter

Metal Energy will accelerate project operatorship after March's Phase 1 drill program

TORONTO

,

Feb. 8, 2022

/CNW/ - Metal Energy Corp. ("the "

Company

" or "

Metal Energy

") (TSXV:

MERG) is pleased to provide an update on the upcoming drill program planned for the high-grade

nickel Manibridge project (the "

Project

" or "

Manibridge

") in the Thompson Nickel Belt,

Manitoba

.

The Project incorporates a past-producing mine that produced 1.3 million tonnes at 2.55% nickel and

0.27% copper between 1971 and 1977.

"Drilling at Manibridge remains our top priority as our internal projections for the Project suggest it

has the potential to yield a bulk mineable resource. Our first drill program for Manibridge is

scheduled to start within the next 3 to 4 weeks. Drill targets have been planned to assess historic

high-grade nickel drill intercepts beneath the old mine workings and along strike of the past-

producing mine, as well as targeting areas within the mine's shadow that remain untested. Nickel

demand is forecast to grow by 2x to 4x within the next 10 to 20 years spurred on by the

electrification revolution and battery storage systems to complement a global effort to replace fossil

fuels with renewable energy sources," said

James Sykes

, CEO of Metal Energy.

Manibridge's drill program is planned for 3,000 metres with 7 drill holes all within a kilometre strike of

the past-producing mine. A crew is scheduled to start field preparations early next week to clear the

trails and pack snow for the proposed drill collar locations. This program is fully permitted.

A heli-borne mobile magnetotellurics ("

Mobile

MT

") geophysical survey is planned to cover the entire

Project in May. Mobile MT is a cutting-edge technology that accurately identifies electromagnetic

and magnetic signatures to depths exceeding 1 km from the surface. Metal Energy plans to use the

results from the Mobile MT survey to identify exploration targets for future drill programs proximal to

the mine and on greenfields Project holdings to the east and north.

The Company plans to follow up this news release with a video presentation to highlight the geology

of Manibridge and how Metal Energy views its development potential.

About the Manibridge Project

Manibridge encompasses 4,368 hectares and is within the world-class Thompson Nickel Belt. The

Project is 20 kilometers southwest of

Wabowden

, which has significant infrastructure and capacity

that has supported previous exploration programs, including year-round highway access via Highway

6.

CanAlaska Uranium Ltd. are the operators of the Manibridge project. Metal Energy is earning into

the Project and can become the operators after March's Phase 1 drill program.

About Metal Energy Corp.

Metal Energy is a well-funded nickel and battery metal exploration company with two projects,

Manibridge and Strange, in the politically-stable jurisdictions of

Manitoba

and

Ontario, Canada

,

respectively. Both projects are subject to earn-in agreements where the Company can acquire 100%

exploration rights to approximately 16,200 hectares.

QP Statement

The technical information contained in this news release has been reviewed and approved by

Mike

Sweeny

, P.Geo., Vice-President, Exploration & Development for Metal Energy, and a Qualified

Person as defined in "National Instrument 43-101, Standards of Disclosure for Mineral Projects."

Reader Advisory

Certain information set forth in this news release contains forward-looking statements or

information ("

forward-looking ​statements

"), including details about the business of the Company.

By their nature, forward-looking statements are subject to numerous risks ​and uncertainties, some

of which are beyond the Company's control, including the impact of general economic conditions,

​industry conditions, volatility of commodity prices, currency fluctuations, environmental risks,

operational risks, competition from ​other industry participants, stock market volatility. Although the

​Company believes that the expectations in its forward-looking statements are reasonable, its

forward-looking statements have ​been based on factors and assumptions concerning future events

which may prove to be inaccurate. Those factors and ​assumptions are based upon currently

available information. Such statements are subject to known and unknown risks, ​uncertainties and

other factors that could influence actual results or events and cause actual results or events to

differ materially ​from those stated, anticipated or implied in the forward-looking statements.

Accordingly, readers are cautioned not to place undue ​reliance on the forward-looking statements,

as no assurance can be provided as to future results, levels of activity or achievements. ​Risks,

uncertainties, material assumptions and other factors that could affect actual results are discussed

in our public disclosure ​documents available at

www.sedar.com

including the Filing Statement

dated

November 15, 2021

. Furthermore, the forward-looking statements contained in this

document are made as of ​the date of this document and, except as required by applicable law, the

Company does not undertake any obligation to publicly ​update or to revise any of the included

forward-looking statements, whether as a result of new information, future events or ​otherwise. The

forward-looking statements contained in this document are expressly qualified by this cautionary

statement.​

Neither the TSX Venture Exchange Inc. nor its Regulation Services Provider (as that term is

defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or

accuracy of this release.

SOURCE

Metal Energy

View original content:

http://www.newswire.ca/en/releases/archive/February2022/08/c9735.html

%SEDAR: 00051725E