Visible Gold in Quartz Vein Discovered in Biggest Step-Out Drill Hole in History of PL Mine and Phase 1 Restart Initiatives Update

Drill Results

Minnova Corp. Office: +1 647 985 2785

MCI:TSXV 217 Queen Street W., Suite 401

www.minnovacorp.ca Toronto, Ontario M5V 0R2

Minnova Corp.

Visible Gold in Quartz Vein Discovered in Biggest Step-Out Drill Hole in History of

PL Mine and Phase 1 Restart Initiatives Update

NOT FOR DISSEMINATION INTO THE UNITED STATES

April 20, 2021, Toronto, Ontario – Minnova Corp. (TSXV: MCI, OTC Pink: AGRDF, "Minnova”

or the “ Company”), a discovery -stage exploration and advanced development -stage gold

company focused on the expansion and restart of our 100% owned PL Gold Mine in central

Manitoba is pleased to announce recent exploration developments, current and planned on site

activities.

Visible Gold Intersected in Step-Out Drilling

Targeted deep drilling on the down dip/on strike extension to earlier positive drill results from the

Company’s Spring 2021 drill campaign have intersected visible gold in hole M-21-048x at a depth

of 208 m. Visible gold mineralization is described as coarse, 1mm to 3mm grains at the margins

of a 30.0 cm wide quartz vein (see Photo 1). The success of this intercept is a result of a detailed

re-interpretation of historic drilling along with more recent shallow drilling on the PL North

mineralized structures. From this work it was determined that a previous Minnova wildcat hole

testing a shallow airborne EM conductor may have been shut down short of the projected down

dip extension of the PL North mineralized structures. The successful re -entry of M -21-048x

affirms a predictable model for gold mineralization based on continued structural a nalysis of the

deposit. Iterations of this model are being used for deposit development and regional scale

exploration.

Photo 1: Visible Gold in Quartz Vein

Visible Gold was logged along the margins the quartz vein is located within a broader high-strain

structure measuring 1.0 meters at the target depth. This structure is interpreted to be the down

dip extension of the PL North Upper Zone. M -21-048x is located approximately 350 meters

Minnova Corp. Office: +1 647 985 2785

MCI:TSXV 217 Queen Street W., Suite 401

www.minnovacorp.ca Toronto, Ontario M5V 0R2

northwest of the PL mill and over 500 meters beyond the limits of the 2017 PL Deposit resource

model. This mineralized intercept demonstrates that the deposit is open for expansion along

strike and down-dip beneath the permitted 1,000 tpd PL mill (see Figure 1 Location Map).

Figure 1: Location Map of DDH M-21-048x

Gorden Glenn President & CEO commented: “We are very excited to announce this intercept of

visible gold. It confirms our structural model that the mineralized PL North structures extend to

significant depth along strike to the northwest. This intercept is the result of thorough structural

analysis by our exploration team. This discovery is also significant as it is located well outside

the currently defined PL Deposit reserves and resources (see Note 1) an d demonstrates the

significant potential for resource expansion and brown-fields exploration of the PL Project.

In fact, it is the most significant and farthest step -out drill hole in the history of the property. It

gives credence to the potential for additional gold deposits in the greater PL Project region . We

intend to aggressively follow up these results with further diamond drilling at depth and along

strike.”

Minnova Corp. Office: +1 647 985 2785

MCI:TSXV 217 Queen Street W., Suite 401

www.minnovacorp.ca Toronto, Ontario M5V 0R2

PL Mine Phase-1 Restart Update

In addition to exploration upside evidenced by above noted discovery of visible gold in step-out

drilling the Company is confident that the current development options being studied will also

deliver significant shareholder value.

The Company is actively planning for an optimized Phase-1 Restart of the PL Mine to capitalize

on current high gold price and positive gold price outlook. Our efforts are focused on development

strategies that minimize; both risk, and initial capital costs to optimize near term and long term

mine developments and operational plans to maximize metallurgical recoveries.

A key variance to the initial development strategy from the 2017 Feasibility Study is the

development of a new northern portal and decline to access the PL deposit. Benefits to this

development approach include:

• much earlier access to high grade reserves and resources potentially shorting time to

first production

• reduced initial underground development requirements

• increased development options for initial test mining techniques that focus on selective

mining to minimizing dilution without compromising overall resource extraction

• optimal location for new underground access as resource appears to extend to the

northwest

• underground mine access closer to the mill to reduce ore haul travel distance on

surface

Included in our revised mine development plan is the opportunity to initiate an on-site bulk sample

of mined material provided by the t est mining program. On-site testing is envisioned to include

basic crushing, milling, and processing via modern gravity recovery equipment. This testing will

contribute to updated metallurgical recoveries using modern gravity concentration technology and

potentially allow free gold to be recovered during the early test mining phase . Tailings from the

gravity process test work will be a) stockpiled for future on-site flotation processing following the

restart of PL mill and b) sent offsite for additional floatation circuit recovery testing . Previous

metallurgical studies estimated over 50% of gold recovery by gravity concentration using spirals,

jigs and a shaker table, technology prevalent at that time.

The company is optimistic the revised mine development plan and onsite bulk sample test work

will result in streamlined processes that lead to significant cost savings and improve overall gold

recovery.

The PL Mine is located in a mining friendly jurisdiction with access to a highly skilled local

workforce. The Company believes the PL Mine can make a significant contribution to regional

economic development and future investment in the historic Flin Flon, MB mining district.

Minnova Corp. Office: +1 647 985 2785

MCI:TSXV 217 Queen Street W., Suite 401

www.minnovacorp.ca Toronto, Ontario M5V 0R2

Minnova will provide further progress updates as internal studies and site work advances during

the summer of 2021 and over the remainder of the year.

Notes 1: Nokomis NI 43-101 mineral resource estimate was prepared by Leon McGarry, B.Sc., P.Geo., of CSA Global

Pty Ltd., and is contained in the Technical Report entitled Feasibility Study, PL Gold Project, Manitoba, Canada filed

on SEDAR on May 4, 2018.

About Minnova Corp.

Minnova Corp. is an emerging Canadian gold producer focused on restarting the PL Gold Mine

and expanding gold resources on its PL and Nokomis gold deposits. The Company has completed

a Positive Feasibility Study in support of restarting the PL Mine at an average annual production

rate of 46,493 ounces over a minimum 5 year mine life. The resource remains open to expansion

and future surface exploration work programs will target resource expansion. The PL Gold Mine

has a relatively short pre -production timeline for ecast at 15 months, benefits from a valid

underground mining permit (Environment Act 1207E), an existing processing plant, over 7,000

meters of developed underground ramp to -135 metres depth, is fully road accessible and close

to existing mining infrastructure in the prolific Flin Flon – Snow Lake Greenstone Belt of Central

Manitoba.

Qualified Person

Mr. Chris Buchanan, M. Sc., P. Geo., a consultant of the Company and a “Qualified Person” under

National Instrument 43-101, has reviewed and approved the scientific and technical information

in this press release.

For more information please contact:

Minnova Corp.

Gorden Glenn

President & Chief Executive Officer

For further information, please contact Investor Relations at 647-985-2785 or

[email protected]

Visit our website at www.minnovacorp.ca

Forward Looking Statements

This news release contains "forward -looking information" within the meaning of applicable Canadian securities legislation.

Forward-looking information includes, but is not limited to, information regarding the Company including management’s

assessment of future plans and operations, that may involve risks associated with mining exploration and development, volatility

of prices, currency fluctuations, imprecision of resource estimates, environmental and permitting risks, access to labour and

services, competition from other companies and ability to access sufficient capital. As a consequence, actual results may differ

materially from those anticipated in the forward looking statements. A feasibility study has not been completed and there is no

certainty the disclosed targets will be achieved nor that the proposed operations will be economically viable. Although Minnova

has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-

looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be

no assurance that such information will prove to be accurate, as actual results and future events could differ materially from those

Minnova Corp. Office: +1 647 985 2785

MCI:TSXV 217 Queen Street W., Suite 401

www.minnovacorp.ca Toronto, Ontario M5V 0R2

anticipated in such information. Accordingly, readers should not place undue reliance on forward-looking information. Minnova

does not undertake to update any forward-looking information, except in accordance with applicable securities laws.