MONTAGE GOLD REPORTS ON ITS Q4-2025 ACTIVITIES Koné project construction on-budget and ahead of schedule • Strong continued exploration focus • Robust liquidity sources CONSTRUCTION ACTIVITIES › Rapid progress achieved with +9.0 million hours worked to date, with more than 3,000 employees and contra
MONTAGE GOLD REPORTS ON ITS Q4-2025 ACTIVITIES
Koné project construction on-budget and ahead of schedule • Strong continued exploration focus • Robust liquidity sources
CONSTRUCTION ACTIVITIES
› Rapid progress achieved with +9.0 million hours worked to date, with more than 3,000 employees and contractors on-site
› Well on track for first gold pour in late Q4-2026 through the oxide circuit and on budget with $572.8 million of capital
committed as at today, representing approximately 65% of the total upfront capital expenditure
› Key process plant achievements include completion of all CIL tanks and ball mill shell installation, oxide sizer completion,
foundation concrete pours for pre-leach and tailings thickeners, and advancement of the hard-rock comminution circuit
› Other key infrastructure is well advanced including the full operation of the river abstraction and water storage facilities,
TSF lining tracking ahead of schedule, relocation completed, and plant buildings already fully operational
EXPLORATION ACTIVITIES
› 114,699 meters drilled at the Koné project in 2025 focused on delineating higher grade satellite resources, whilst an initial
90,000-meter drill programme for 2026 is well underway
› Resource updates are expected to be published in the coming weeks for the Koné and Gbongogo Main deposits, as well as
for other deposits along with maiden resource estimates for new discoveries
› 9,000 meter drilling programme is underway at the Wendé advanced greenfield property focusing on initial step out and
downdip drilling of areas that have been historically drilled, as well as testing new prospective targets
FINANCIAL POSITION
› Robust liquidity and Koné project funding sources totalling $559.4 million compared to remaining capital disbursements
of $518.0 million
Vancouver, Canada — March 25, 2026 — Montage Gold Corp. (“Montage” or the “Company”) (TSX: MAU, OTCQX: MAUTF) is
pleased to report on its construction and exploration activities for Q4-2025, with highlights provided in Table 1 below.
Table 1: Business and financial highlights
THREE MONTHS ENDED YEAR ENDED
vs.
Q2-2025
All amounts in millions of USD unless otherwise specified
Dec 31,
2025
Sep 30,
2025
Dec 31,
2024
Dec 31,
2025
Dec 31,
2024
Δ Q4-2025
vs.
Q3-2025
CONSTRUCTION ACTIVITIES
Cumulative hours worked, million hrs 7.0 4.8 0.3 7.0 0.3 +2.2
Lost-Time Injuries Frequency Rate 0.20 0.20 - 0.20 - -
Total cumulative capital committed, inclusive of amount disbursed 540.6 428.0 109.2 540.6 109.2 +112.6
- Cumulative capital disbursed1 367.0 262.3 27.4 367.0 27.4 +104.7
- Cumulative capital committed and to be disbursed1 173.6 165.7 81.8 173.6 81.8 +7.9
EXPLORATION ACTIVITIES
Meters drilled, meters 28,915 2,504 46,709 114,699 81,815 +26,411
Exploration expenditure1 5.8 2.4 9.3 21.6 18.7 +3.4
CASH FLOW AND LIQUIDITY POSITION1
Cash flows used in investing activities (113.9) (92.1) (78.1) (237.2) (83.6) (21.8)
Cash flows generated from financing activities 157.3 156.8 77.5 307.7 232.0 +0.5
Cash and cash equivalents, end of period 191.8 159.0 115.3 159.0 115.3 +32.8
Total liquidity and Koné project funding sources 559.4 712.8 918.5 559.4 918.5 (153.4)
1As referenced in the Company’s Financial Statements and Management’s Discussion and Analysis for the year ended December 31, 2025, available on SEDAR+ and on the
Company’s website.
The Company’s Consolidated Financial Statements and associated Management’s Discussion and Analysis for the year ended
December 31, 2025, and 2024, have been filed under the Company’s profile on SEDAR+ (www.sedarplus.ca) and are available
for download on the Company’s website.
montagegold.com 1
Rapid construction progress continues to be made at the Company’s flagship Koné project, in Côte d’Ivoire, with first gold pour
targeted ahead of schedule in late Q4-2026, through the oxide circuit, and on-budget. A total of 2.2 million construction hours
were worked in Q4-2025, with total hours worked now totalling +9.0 million hours from the commencement of the project
until today, with a Lost Time Injury Frequency Rate (“LTIFR”) of 0.20.
Significant progress is being made on the key processing infrastructure, notably with the completion and hydro-testing of all
the tanks on the carbon in leach ("CIL") trains and the completion of the oxide sizer. The ball mill shell has been installed ahead
of schedule and foundations preparation for the primary crusher, secondary crusher and high-pressure grinding rollers
(“HPGR”) within the hard-rock comminution circuit are well advanced. Process plant water services and reagents areas are also
progressing ahead of schedule. Construction of the tailings storage facility (“TSF”) is nearing completion with the laydown of
high-density polyethylene (“HDPE”) liners over 50% complete. Other key infrastructure including the construction of the 225kV
electrical substation, preparation for grid connection, permanent camp and airstrip preparation also continue to advance
ahead of schedule. Moreover, in light of Montage’s funding headroom as a result of an earlier oxide start-up, the Company has
recently approved the procurement of back-up diesel-powered generator-sets which would enable the process plant to
operate at full nameplate capacity on back-up power, thereby providing greater operating flexibility, for a cost of $25.0 million.
A total of $540.6 million of capital had been committed as at quarter-end (inclusive of $367.0 million disbursed), which has
further increased to approximately $572.8 million as at today, representing approximately 65% of the total $885.0 million
capital expenditure, with prices in line with expectations.
In parallel, the Company continues to be focused on unlocking value through its exploration programmes. A total of 114,699
meters were drilled at the Koné project in 2025, exceeding the 81,815 meters completed in 2024. Exploration efforts continue
to focus on three parallel tracks: infill and extension drilling of previously delineated starter deposits, advancing pre-resource
targets toward maiden resource definition, and testing new targets through regional scout drilling. During the year, the
Company published an updated Mineral Resource Estimate ("MRE") for select deposits along the Sissedougou and Gbongogo
trends, whilst additional discoveries such as Petit Yao continue to demonstrate the project’s significant exploration potential.
Further resource updates are expected to be published in the coming weeks for the Koné and Gbongogo Main deposits as well
as for other satellite deposits, while maiden resources are anticipated on new targets throughout 2026. Results from the
Company's pre-production drilling programme at the Koné and Gbongogo Main deposits have confirmed both the grade and
continuity of the mineralized envelopes and identified high-grade zones, with full results expected to be released soon. In
addition, the Company was awarded the Wendé advanced greenfield exploration property in late 2025, for which a 9,000
meter drilling programme has already commenced.
In late Q4-2025, the Company announced the acquisition of African Gold Limited (ASX:A1G)(“African Gold”), which adds the
high-quality resource-stage Didievi project in Côte d’Ivoire. The transaction is expected to close in Q2-2026.
Martino De Ciccio, Chief Executive Officer of Montage, commented: “We are very pleased with the momentum generated thus
far to advance our strategy of creating a premier multi-asset African gold producer and delivering value for all our
stakeholders.
Construction at our flagship Koné project, in Côte d’Ivoire, continues to progress at a rapid pace with a number of key
milestones achieved including completion of the oxide sizer and installation of the ball mill shell ahead of schedule, which
positions us to target a first gold pour through an oxide circuit start-up in late Q4-2026. Moreover, we are continuing to enjoy
significant exploration success at our Koné project as we have executed on our goal of delineating higher grade satellites to
supplement production from the onset. We look forward to integrating the new discoveries into our mine plan with the goal of
publishing an updated life-of-mine plan later this year.
Looking ahead, we are also pleased to be consolidating a project pipeline in Côte d’Ivoire through the acquisition of African
Gold, where recently published drill results continue to confirm the prospectivity of the Didievi project. In parallel, we have
commenced drilling at our newly awarded Wendé advanced greenfield property in Côte d’Ivoire with the goal of organically
sourcing the Company’s next project through our ability to stake prospective grounds and explore.
I’d like to take this opportunity to thank our employees, contractors, financiers, local stakeholders, and wider partners for their
strong dedication and support as we continue to deliver on our collective goals.”
TSX MAU OTCQX MAUTF
montagegold.com 2
KONÉ PROJECT UPDATE
Construction continues to progress on-budget with rapid progress made across a number of key workstreams as summarized
below:
› On-site workforce now exceeds 3,000 employees and contractors, with over +9.0 million hours worked to date, and with
over 90% local employment, demonstrating the Company’s commitment to local content.
› Process plant construction continues to rapidly advance:
– CIL tank construction has progressed rapidly where all tanks have been erected and hydro-tested. Structural steel,
piperacks and grid mesh are well advanced on CIL trains 1 and 2.
– Oxide sizer construction has been completed, approximately 4 months ahead of schedule, with electrical
commissioning complete. Ongoing work includes structural fill placement and concrete pours on the oxide sizer
retaining wall, both of which are advancing ahead of schedule.
– The ball mill shell arrived on-site in early-January 2026 and all three shells and trunnions have already been installed,
marking a critical milestone. The installation of structural steel, piperacks and grid mesh is ongoing.
– Water services are well advanced with all four tanks completed and hydro-tested.
– Pre-leach and tailings thickener concrete pours are complete, and deliveries of the thickeners have begun arriving on-
site ahead of schedule. The installation of the thickeners are expected to commence imminently.
– Hard-rock comminution circuit earthworks are progressing rapidly, with rebar installation on the primary crusher
chamber and tunnel section ongoing and formwork commencing. Earthworks are well advanced on the secondary
crusher where rebar steel installation has begun, and earthworks are ongoing on the HPGR area.
– Reagent foundations and all other civil work have been completed and erection of reagents tanks are well advanced,
whilst hydro-testing of completed tanks is ongoing.
– Gold room concrete vault walls were poured and the gold safe was installed. Suspended concrete slab roof works is
ongoing.
– Foundations have been completed for ancillary buildings in the process plant and all buildings are being utilized or
fitted out.
Figure 1: Process plant area overview
TSX MAU OTCQX MAUTF
montagegold.com 3
Figure 2: Process plant key infrastructure
› Fabrication of other long-lead items following the delivery of the ball mill shell and thickeners to site is progressing on-
schedule, including the hard-rock comminution circuit equipment, HPGR and associated fabricated steel.
› The Koné and Gbongogo mine services areas continue to progress on schedule ahead of first deliveries of the mining fleet in
mid-2026.
Figure 3: Koné and Gbongogo mine services areas
TSX MAU OTCQX MAUTF
montagegold.com 4
› Water storage infrastructure was completed in Q3-2025 alongside the river abstraction, booster stations and water
treatment plants, which were all successfully commissioned and operational last year.
Figure 4: Water storage facility
› Grid connection is progressing rapidly with power line construction of the 33kV overhead line to the camp, river abstraction
and processing plant main area nearing completion. The 225kV substation construction is progressing on-schedule with cable
trench excavation nearing completion and internal fit-out of the substation buildings largely completed. Earthworks and
foundations for the 225kV overhead powerline tower settings have been completed, and tower assembly is now complete.
All 225kV powerline towers have been erected and installation of high-voltage cables is underway. The Ivorian national
power company, La Compagnie Ivoirienne d’Électricité, has confirmed power availability for the Koné project which is
expected to benefit from the powerline’s favourable location along the major 225kV national ring main which currently has
amongst the highest availability in the country. In order to provide greater operating flexibility, and in light of Montage’s
funding headroom as a result of an earlier oxide start-up, the Company has approved the procurement of an additional
32MW of back-up diesel-powered generator-set capacity (“Gensets”), supplementing the existing 10MW of back-up power
already on site, which would enable the process plant to operate at full nameplate capacity on back-up power. The upfront
capital to procure and install the Gensets is expected to amount to $25.0 million. Delivery of the Gensets is expected to
commence in Q2-2026 and the Gensets are expected to be operational in Q4-2026.
Figure 5: Electrical substation and high-voltage grid connection preparation
TSX MAU OTCQX MAUTF
montagegold.com 5
› Gbongogo haul road construction is well advanced between the Marahoué river and Gbongogo. Earthworks and concrete
structural fill on the Marahoué river bridge foundations were completed ahead of schedule. Installation of structural steel is
ongoing and is expected to be complete in Q2-2026.
Figure 6: Marahoué river bridge construction
› Tailings Storage Facility (“TSF”) embankment wall construction was completed 3 months ahead of schedule. TSF HDPE lining
laydown is already more than 50% complete.
Figure 7: TSF development and HDPE liner laydown
TSX MAU OTCQX MAUTF
montagegold.com 6
› The airstrip has been completed and is now fully operational. Aircraft hanger installation is due to commence imminently.
Figure 8: Airstrip
› The permanent camp construction is complete, with all permanent rooms fully fitted and available for use. Remaining
workstreams include landscape gardening, which will advance during the rainy season.
Figure 9: Permanent camp
› The resettlement village was completed in November 2025 and subsequently officially inaugurated with more than 1,000
people attending the opening ceremony. The village includes new houses, a school, a pharmacy, a maternity hospital, a
market, a community centre and religious buildings. The construction of the village enabled 18 local businesses to create
more than 490 jobs in the community, empowering local entrepreneurs and providing numerous skills development
opportunities. All households have successfully been resettled and formal handover of the village to the community is
complete.
› Operational readiness is well underway with key hires for operational role having commenced. Training programmes for
construction employees who have been selected to transition into mining and processing roles, has also commenced.
TSX MAU OTCQX MAUTF
montagegold.com 7
Timeline to first gold pour
Given the strong advancement in construction activities, the Company remains on-budget and is targeting first gold pour in
late Q4-2026 through the oxide circuit start-up , whilst the hard-rock c omminution circuit remains well on-schedule for
completion in Q2-2027, with key upcoming milestones presented in Table 2 below.
Table 2: Koné project timeline to first gold pour
Work Stream Q1-2025 Q2-2025 Q3-2025 Q4-2025 Q1-2026 Q2-2026 Q3-2026 Q4-2026 Q1-2027 Q2-2027
Tailings Dam & Water Dams
Tailings Dam * * * *
Water Storage & Dam * *
Construction
Power Supply * * * * *
Site Infrastructure * * * * * * *
Earth works & Concrete Works * * * * * *
Structural, Mechanical, Piping * * * * * *
Electrical * * * *
Process Plant Commissioning * * *
First Gold - Oxide Circuit *
First Gold - Hard-Rock Circuit *
As detailed in the above section, in light of Montage’s funding headroom as a result of an earlier oxide start-up, the Company
has approved the procurement of back-up diesel-powered generator-sets which would enable the process plant to operate at
full nameplate capacity on back-up power, thereby providing greater operating flexibility, for an estimated cost of $25.0
million. As such, the revised total upfront capital expenditure for the project now stands at $885.0 million, up from $860.0
million.
The Company expects to publish an updated life of mine plan (“LOM”) later this year to incorporate the initiatives currently
underway to further unlock value at the Koné project, aimed at enhancing the production profile from the onset. The updated
LOM is expected to be based on the updated resource of the Koné and Gbongogo Main deposits, along with the addition of
several higher grade satellites deposits. In addition, the LOM will reflect the addition of the oxide circuit, along with other
process plant design enhancements made, and the shift to an owner-operated mining model.
CASH FLOW, LIQUIDITY SOURCES AND CAPITAL REQUIREMENTS
Cash flows generated from financing activities increased by $0.5 million from $156.8 million in Q3-2025 to $157.3 million in
Q4-2025, as equal portions of the Wheaton Stream were drawn down in both Q4-2025 and Q3-2025, whereas cash receipts
related to stock options exercise has increased. Cash flows used in investing activities increased by $21.7 million, from $92.1
million in Q3-2025 to $113.9 million in Q4-2025. This increase reflects the ongoing construction activities for the Koné project.
As at December 31, 2025 , the Company had a consolidated cash balance of $191.8 million, compared to $159.0 million as at
September 30, 2025, a s t h e C o m p a n y d r e w $ 1 5 6 . 2 5 m i l l i o n o f t h e W h e a t o n S t r e a m i n Q 4 - 2 0 2 5 , p a r t i a l l y o f f s e t b y t h e
investments in mineral property, plant and equipment (Koné project construction), as well as operating cash outflows for
general and administrative expenses and exploration activities.
As at December 31, 2025 , the Company had total liquidity and Koné project funding sources of $559.4 million, comprised of
$331.3 million of undrawn funding sources (composed of the $156.3 million Wheaton Stream, $50.0 million Zijin Loan Facility,
$75.0 million Wheaton Loan Facility, and $50.0 million local Working Capital Facility), $191.8 million of cash on hand and $36.4
million of other liquid assets. In addition, the Company has $75.0 million of undrawn CAT Equipment Financing.
A total of $540.6 million of capital had been committed for the Koné project construction as at December 31, 2025 (inclusive
of amounts disbursed), which further increased to $572.8 million as of the date of this press release, representing 65% of the
total $885.0 million capital expenditure estimate, with costs in line with expectations. As at December 31, 2025, a total of
$367.0 million has been disbursed for the Koné project construction, of which $104.7 million in Q4-2025, with approximately
$418.0 million remaining to be disbursed until first gold pour through the oxide circuit in late Q4-2026, and a total of
approximately $518.0 million remaining to be disbursed to completion of the hard-rock comminution circuit (inclusive of
contingencies).