Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MAU.TO ·

Montage GOLD Launches the Construction of Its Koné Project with First GOLD Pour Expected IN Q2-2027

Production Results Mine Development & Operations

Press

Release

montagegold.com 1

MONTAGE GOLD LAUNCHES THE CONSTRUCTION OF ITS KONÉ PROJECT

WITH FIRST GOLD POUR EXPECTED IN Q2-2027

HIGHLIGHTS:

› A groundbreaking ceremony was held at Koné today with a strong presence from government officials and local

communities, demonstrating their support for the project given its significant social and economic benefits

› First gold production is expected in Q2-2027 as early works are well underway and major construction works are set to

commence in the coming weeks

› EPCM contract was awarded to Lycopodium Minerals Pty Ltd with a number of tasks to be self-performed by

Montage’s experienced in-house construction team

› Key design parameters were optimized to enhance the crushing and milling circuit and improve the efficiency of the

overall operation

› Project is fully funded with significant headroom given that the upfront capex is expected to be US$835m while

Montage has in excess of US$900m in liquidity sources

› Long-lead items have been ordered, including the HPGR, crushers, ball mill, thickeners, CIL tanks and key earthworks

mobile equipment, amounting to more than US$150m in pricing secured

› The ongoing 90,000m drill programme is expected to be completed in the coming weeks which is expected to result in

the publication of a maiden mineral resource in Q1-2025

› Exploration to remain a focus throughout the construction, to achieve prior to commencing production the published

target of discovering more than 1Moz of M&I resources at a grade 50% higher than the Koné deposit

Abidjan, Côte d’Ivoire — December 18, 2024 — Montage Gold Corp. (“Montage” or the “Company”) (TSXV: MAU, OTCQX:

MAUTF) is pleased to announce that it has launched the construction of its Koné project in Côte d’Ivoire (“Koné” or the “Project”)

with first gold production scheduled for Q2-2027. To mark this significant milestone, a groundbreaking ceremony was held at

Koné today with a strong presence from government officials and local communities, demonstrating their support for the project

given its significant social and economic benefits.

Significant progress is being made to rapidly advance and derisk the project as early works are well underway and major

construction works are set to commence in the coming weeks , once further construction equipment arrives to site . The

engineering, procurement and construction management (“EPCM”) contract has been awarded to Lycopodium Minerals Pty Ltd

(“Lycopodium”), with a number of tasks to be s elf-performed by Montage’s experienced in -house construction team which

already totals approximately 350 peopl e. Montage, together with Lycopodium, have completed a comprehensive engineering

review of Montage’s Updated Feasibility Study (“UFS”) published in January 2024 which has resulted in the optimization of

several key design parameters to enhance the crushing and milling circuit and improve the efficiency of the overall operation .

The project is fully funded with significant headroom with upfront capex expected to be US$835 million while Montage has in

excess of US$900 million in liquidity sources.

Martino De Ciccio, CEO of Montage, commented: “We are very pleased to announce the commencement of construction at the

Koné project in Côte d'Ivoire, marking a significant milestone in our journey to becoming a premier African gold producer and

the culmination of this year’s efforts.

Our ability to rapidly advance the project is driven by the strong partnerships we have built, based on a win -win approach, with

local stakeholders, strategic investors, financiers, suppliers, and contractors. We are also grateful for the dedication of o ur

experienced management team, and we thank everyone involved for their commitment.

TSX.V MAU OTCQX MAUTF

montagegold.com 2

Looking ahead, we are excited to continue unlocking value for all our stakeholders by advancing our construction efforts, whi le

also creating value through exploration and by expanding our focus on social, health, education, and economic programmes for

our local communities.”

Peder Olsen, President and Chief Development Officer of Montage, commented: "We are excited to launch the construction of

the Koné project, which marks the culmination of our efforts to optimize key design parameters aimed at enhancing the crushing

and milling circuit and improving the efficiency of the overall operation . Additionally, to mitigate construction risks, we have

strategically placed orders for long-lead items, securing both price stability and timely delivery.

Given the high quality of our project and our intention to create a leading African gold producer, we are proud to have assembled

a highly experienced and skilled construction team. Many of these team members have worked with me to successfully deliver

four projects over the last decade in West Africa, including two in Côte d’Ivoire.

I would like to take this opportunity to thank everyone who has contributed to getting us to this point. As the ideal time to begin

construction is after the rainy season, we are excited to have commenced early works at the optimal time. We now look forward

to delivering on our construction schedule and unlocking significant value for all stakeholders."

GROUNDBREAKING CEREMONY

Earlier today, a groundbreaking ceremony was held at Koné with over 2,000 people present including a strong presence from

government officials and local communities, demonstrating their support for the project , as shown in Figure 1 below . At the

ceremony, Mamadou Sangafowa -Coulibaly, Côte d’Ivoire’s Mines, Petroleum and Energy Minister reiterated the country’s

support for the mining sector and the Koné project in particular, outlining the significant social and economic benefits to all

stakeholders.

Figure 1: Groundbreaking ceremony

TSX.V MAU OTCQX MAUTF

montagegold.com 3

PROJECT CONSTRUCTION UPDATE

EPCM award

The Company has awarded the engineering, procurement and construction management (“EPCM”) contract to Lycopodium

Minerals Pty Ltd (“Lycopodium”). Lycopodium ’s involvement in the project commence d in 2018 and were the engineers for

Montage’s Definitive Feasibility Study (“DFS”) and Updated Feasibility Study (“UFS”). In addition, Lycopodium has a strong track

record in West Africa and in particular in Côte d’Ivoire, having recently completed construction of Fortuna Mining Corp’s Séguéla

project in 2023 and Endeavour Mining Plc’s Lafigue mine in 2024, both on time and on budget . Other projects in C ôte d’Ivoire

completed by Lycopodium include the Yaouré project for Perseus Mining Ltd, and Endeavour Mining Plc’s Ity CIL and Agbaou

projects. Integrating fully into the owner’s team, Lycopodium is responsible for providing Montage with support on the

engineering, design, procurement, construction management and commissioning of the processing plant and process related

infrastructure.

Order of long-lead items

A significant number of long lead item orders have been committed to by Montage, securing pricing for equipment and services

on initial capital of over US$150 million, with key orders placed including:

› Ball mill, high-pressure grinding rolls (“HPGR”) and crushers (primary and secondary)

› Thickeners and CIL tanks

› Key earthworks mobile equipment leases

› Early camp facilities are complete while construction of the permanent camp is underway which will also accommodate

construction personnel

Early works

Early works were launched in Q4-2024 and are progressing well with the following key highlights:

› No lost time incidents (“LTIs”), with over 138,890 workhours completed since the commencement of early works

› In line with its commitment to local content, Montage has partnered with the government -accredited Lycée Technique de

Mankono to deliver practical vocational training programs tailored to the needs of the Koné project for an initial 80 individuals.

The first group of participants, drawn from impacted local commun ities, has successfully completed its training and is now

commencing employment with Montage. This first group includes steel fixers, building electricians, masons, carpenters and

plumbers. The second group of trainees began its practical training on October 21, 2024

› In addition, Montage is pleased to be using local contractors for buildings, earthworks and camp electricals

› Montage has initiated a literacy and numeracy program for individuals in nearby affected villages. Currently over 500

participants are attending the programme which aims to empower local communities with essential skills to pursue

employment and improve access to economic opportunities and enhance long -term socio-economic resilience

› Land compensation and resettlement activities have begun with access secured to all major early works areas including the

plant, camp, water storage facility and the tailings storage facility (“TSF”)

› The resettlement site for the relocation of the Village of Dolourougokaha has been agreed between affected and host

communities with housing construction set to commence in late Q1-2025

› With Koné located in a low water stress area, project water will be sourced from the nearby Marahoué river into a water

storage facility (“WSF”) and from pit dewatering with a supplementary borefield. The Ministry of Water and Forests granted

the required water abstraction authorizations in Q3-2024 and compensation for access clearing for the pipeline is commencing

› Earthworks are underway for the access road construction, clearing of major work areas, and stockpiling of topsoil is ongoing

› Permanent camp construction has begun with the construction of the first 40 -man blocks well advanced

TSX.V MAU OTCQX MAUTF

montagegold.com 4

› Montage is also focusing on developing an Ivorian supply chain utilising local supply for project and camp consumables, and i s

advancing major contracts to procure fuel, cement, aggregates and explosive supplies, as well as sustainable food sources

› Power will be drawn from the national grid operator, Compagnie Ivoirienne d’Electricite (“CIE”), via a new 225kV transmission

line connecting to existing power lines located approximately 20km from the processing plant area. Natural gas and hydro-

electric generation account for approximately 70% and 20% of Côte d’Ivoire’s electricity generation 1 with expansions projects

underway to install an additional 1,448MW of natural gas and 297MW of hydro -electric generation capacity . The CIE has

confirmed capacity to meet the demand requirements for the Koné project and Montage has conducted a power system study

with CIE which supports the delivery of high quality power, without additional support measures.

Figure 2: Early works underway

Engineering optimizations

Further to Montage’s Updated Feasibility Study (“UFS”) published on January 16, 2024 , Lycopodium and Montage have

undertaken a comprehensive Front-End Engineering and Design process which has resulted in the optimization of several key

design parameters to enhance the crushing and milling circuit and improve the efficiency of the overall operation.

The plant nominal throughput as per the UFS is 11.0 Mtpa, based on a primary crushing, secondary crushing and HPGR, milling

and carbon-in-leach (“ CIL”) availability of 75%, 88% and 91% respectively. The following engineering improvements have

subsequently been made:

› The primary crusher has been upgraded with 33% extra power capacity (from 450kW to 600kW) and the eccentric speed has

been increased, which generates the potential to increase the throughput.

1Source: International Energy Agency at www.iea.org/countries/cote-divoire/electricity

TSX.V MAU OTCQX MAUTF

montagegold.com 5

› The secondary crushers have been upsized by 50% from (from 600kW to 930kW) to ensure that the secondary crushing circuit,

which typically has an availability of 75%, can match the full availability of the HPGR.

› The two HPGR's have been replaced with a single larger unit for ease of maintenance, as well as the ability to accept a coarser

feed size.

› The HPGR circuit includes a stockpile in lieu of a surge bin which is expected to provide significantly greater operating flexibility.

› Ball mill installed power has increased by 10% with a single ball mill of 22MW which compared to the two 10MW ball mills

previously considered. This single larger mill will be simpler to operate given that the addition of low-speed synchronous

motors has eliminated the need for gearboxes in the drive train, reducing components that need auxiliary cooling systems,

maintenance and spares.

› The twin seven tank CIL trains provide a combined slurry residence time of 36 hours for the 10% oxide / 90% fresh ore blend.

Should Montage decide to further increase the mill throughput, provisions have been made to add an extra tank to each train

to either improve residence time or maintain it with the potential to increase throughput.

› Montage continues to engineer the potential addition of an oxide circuit consisting of a sizer and conveyor to directly feed the

mill with oxide and transitional material , bypassing the hard rock comminution and HPGR. The current design limits oxide

material to 10% of total feed, and requires 18.8Mt of pre-stripping, stockpiling, and gradual reintroduction of oxide material

into the feed over the first eight years of production. An oxide circuit would enable an earlier first gold pour while the hard

rock comminution is being commissioned, reduce rehandling costs for oxide ore mined in pre -production, provide significant

operational flexibility to continue production during maintenance of the crushing circuit and would improve blending

optionality. While oxide feed is limited within the Koné deposit, Montage’s ability to discovery more oxide material across new

and existing targets will be a determining factor in forming an investment decision for the oxide circuit.

Based on the se optimization modifications, the treatment plant design now incorporates crushing, screening, HPGR, grinding

and classification, pre -leach and tailings thickening, CIL circuit, carbon recovery and acid wash, carbon elution, electrowinning

trains and smelting, as further detailed below:

› Primary crushing using a gyratory crusher Metso 54/75 and 600kW drive

› Coarse ore stockpile with 24 hours live capacity (34,200 tonnes) complete with three 50% capacity reclaim apron feeders

› Closed-circuit secondary crushing and screening with nominally duty stand -by cone crushers , Metso MP1250 and 930kW

drives, and double deck multi-slope screens, Schenck 4397, to produce a crushed product size P80 of approximately 32mm

› HPGR, Metso HRC2400e with dual 3.0MW drives to produce a nominal P80 of 6mm

› Covered HPGR product stockpile with a live capacity of 4 hours (4,800 tonnes) complete with two reclaim belt feeders

› HPGR product wet sizing/re-pulping screens, Schenck 4397, with undersize slurry reporting to the milling circuit via the cyclone

feed hopper

› HPGR screen oversize stockpile complete with three 50% capacity vibrating reclaim feeders

› Primary ball mill, Metso Φ8.53 metre diameter 14 metre long 22MW dual pinion, in closed circuit with 2 clusters of 14 each

500mm diameter hydrocyclones to produce a grind size with a P80 of 75µm

› Pre-leach thickening (44 metre diameter high rate) to increas e the slurry density feeding the carbon in leach, CIL, circuit to

minimise tankage and reduce overall reagent consumption

› Leach circuit incorporating 14 leach tanks, arranged in two parallel trains of seven each in series, to provide 36 hours leach

residence time, and equipped with external oxygen contactors , while provisions have been made to add an extra tank in the

future if required

› Twin 17 tonne split AARL elution circuits, electrowinning and gold smelting to recover gold from the loaded carbon to produce

a gold/silver doré

TSX.V MAU OTCQX MAUTF

montagegold.com 6

› Tailings thickening (44 metre diameter high rate) to recover cyanide and recycle process water from the CIL tailings

› Tailings pumping to the TSF complete with a supernatant reclaim and return system

› River water abstraction system from the Marahoué river and 32km pipeline

Based on the above-described optimization modifications, the total process plant capital cost has increased by US$33 million, or

approximately 10%. Based upon a comprehensive review o f total project costs accounting for scope changes, realized tender

prices, more conservative working capital assumptions (to account for greater volumes of spares and reagents), inclusion of a

livelihood restoration programme, and a higher contingency. Consequently, the total capital cost estimate has increased by

approximately 12%, from US$742 million to US$835 million, compared to the UFS, as shown in Table 1 below. The UFS assumed

US$30 million of vendor financing, mainly related to the mining contractor mobilization, which reduced the upfront capital to

US$712 million, whereas given the strong liquidity sources secured by Montage, vendor financing is currently no longer being

contemplated for contract mining.

Table 1 – Koné project capital expenditure, in US$m

Main Area

Previous UFS CAPEX Updated CAPEX Variance

($M) ($M) ($M) %

Process Plant 338 371 +33 +10%

Mining and contractor mobilization1 87 78 (9) (10%)

EPCM & Owners Costs 69 67 (2) (3%)

Camp & Other Infrastructure 64 60 (4) (6%)

Tailings and Water Storage 55 60 +5 +8%

Grid Connection 26 31 +5 +18%

Compensation, Resettlement & Livelihood Restoration 9 22 +13 +135%

Pre-Production, Start-up & Commissioning 13 19 +6 +49%

Taxes 5 8 +3 +63%

Working Capital 11 35 +24 +231%

Contingency 65 83 +18 +27%

Total CAPEX 742 835 +93 +12%

Vendor Finance (Mining Mobilisation and Camp) (30) - +30 +100%

Total upfront capital 712 835 +123 +17%

1UFS assumed vendor financing for the mining contractor mobilization while the updated estimate does not consider vendor financing given Montage’s available liquidity sources

Foreign exchange rates of 1.08 for USD:EUR, 0.053 for USD:ZAR, 1.56 for USD:AUD and 1.26 for USD:GBP have been used to

determine capital cost estimates.

TSX.V MAU OTCQX MAUTF

montagegold.com 7

Timetable to First Gold Pour

As shown in Figure 3 below, first gold pour is targeted for Q2-2027, based on a 27 -month construction period for the process

plant. As noted, early works are well underway and major construction works , as well as water storage and dam construction ,

are due to commence in early Q1-2025.

Figure 3 – Koné project timeline to first gold pour

Work Stream Q4-2024 Q1-2025 Q2-2025 Q3-2025 Q4-2025 Q1-2026 Q2-2026 Q3-2026 Q4-2026 Q1-2027 Q2-2027

Early Works

FID & EPCM Award *

Detailed Design & Engineering * * *

Order & Procure Long Lead Items * *

Tailings Dam & Water Dams

Tailings Dam * * *

Water Storage & Dam * *

Construction

Power Supply * * * * *

Site Infrastructure * * * * * * *

Earth works & Concrete Works * * * * * *

Structural, Mechanical, Piping * * * * * *

Electrical * * * *

Process Plant Commissioning * *

First Gold *

Exploration Update

Montage remains on track to achieve its previously published target of discovering more than 1 million ounces of Measured and

Indicated resources, at a grade 50% higher than the Koné deposit, to be achieved before the commencement of production .

2024’s first drill campaign was completed at the end of July, totalling 30,170 metres, with the goal of prioritizing key targ ets for

the next drill prog ramme. This first programme successfully confirmed mineralisation at all 14 targets tested. A second 2024

drilling campaign, totalling 60,000 metres, commenced in mid-September and to date has achieved 45,000 meters. Montage

remains on track to incorporate the 2024 drilling data into its year -end resource statement, with a maiden mineral resource

expected to be published in Q1-2025.

In line with Montage’s goal of unlocking exploration value, the Company expects to conduct similar exploration efforts in 2025,

while construction activities are ongoing.

Grant of stock incentives

Given the recent hires , t he Company has granted a total of 347,124 Restricted Share Units (“RSUs”) to non-executive team

members. The RSUs are granted in accordance with the Company’s 2024 Omnibus Equity Incentive Plan . The RSUs are subject

to vesting provisions.

Neither TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this

release.

TSX.V MAU OTCQX MAUTF

montagegold.com 8

ABOUT MONTAGE GOLD

Montage Gold Corp. (TSXV: MAU) is a Canadian -listed company focused on becoming a premier multi -asset African gold

producer, with its flagship Koné project, located in Côte d’Ivoire, at the forefront. Based on the Updated Feasibility Study

published in 2024, the Koné project has an estimated 16 -year mine life and sizeable annual production of +300koz of gold over

the first 8 years and is expected to enter production in Q2-2027.

TECHNICAL DISCLOSURE

Mineral Resource and Reserve Estimates

The Koné and Gbongogo Main Mineral Resource Estimates were carried out by Mr. Jonathon Abbott of Matrix Resource

Consultants of Perth, Western Australia, who is considered to be independent of Montage Gold. Mr. Abbott is a member in good

standing of the Au stralian Institute of Geoscientists and has sufficient experience which is relevant to the commodity, style of

mineralisation under consideration and activity which he is undertaking to qualify as a Qualified Person under NI 43 –101.

The Mineral Reserve Estimate was carried out by Ms. Joeline McGrath of Carci Mining Consultants Ltd., who is considered to be

independent of Montage Gold. Ms. McGrath is a member in good standing of the Australian Institute of Mining and Metallurgy

and has sufficient experience which is relevant to the work which she is undertaking to qualify as a Qualified Person under NI

43–101.

2024 Exploration

All exploration work on Kone project is designed and carried out under the supervision of Montage Gold Corp, Executive Vice

President, Exploration, Silvia Bottero, a registered Professional Natural Scientist with the South African Council for Natura l

Scientific Professions (SACNASP) and Qualified Person as defined in National Instrument 43 -101 developed by the Canadian

Securities Administrators.

Samples used for the results described above come from Diamond Drilling Holes and are based on 1 metre composite sample.

Core samples have been cut in two by core blade at the camp facilities then shipped by road to Bureau Veritas facility in Abidjan,

Côte d’Ivoire.

For RC drilling, samples were collected over 1 metre downhole intervals from the base of the cyclone and split with a three -tier

riffle split. Three kilograms samples were collected then shipped by road to Bureau Veritas facility in Abidjan, Côte d’Ivoir e. All

samples have been crushed to 2mm (80% passing) with 1 kilogram split out for pulverization to 75μm (85% passing) then analysed

by fire assay using a 50-gram charge.

Field duplicate samples are taken, and blanks and standards are inserted by Montage geologists into the sample sequence at a

rate of one of each sample type per 25 samples. This ensures that there is a minimum 4% QA/QC sample insertion rate applied

to each fire assay batch. The sampling and assaying are monitored and audited through analysis of these QA/QC samples by a

consultant independent of Montage. QA/QC has been designed to be in line with industry best standards and to follow NI 43 -

101 standards and the interpretation reviewed by the Qualified Person. Individual batches are monitored for Standard and Blank

failure during import to the database, whilst longer term QAQC trends are monitored on a periodic basis by Jonathan Hunt,

independent consultant of Montage and Chartered Geologist of the Geological Society of London.

Results for exploration drillholes used the following parameters: 0.3 g/t Au cut off for samples, 0.5 g/t Au minimum value

composite and 2.0 metre maximum interval dilution length. Composite intervals represent (apparent) downhole thickness.

“Including” represents >10 g/t Au.

For further details of the assumptions, parameters and methods used to develop the Mineral Resource Estimates and the Mineral

Reserve Estimate for the Koné Gold Project, please see the UFS, entitled "Koné Gold Project, Côte d'Ivoire Updated Feasibilit y

Study National Instrument 43-101 Technical Report" and filed on SEDAR+ at www.sedarplus.ca. Readers are encouraged to read

the UFS in its entirety, including all qualifications, assumptions and exclusions that relate to the details summarized in this news

release. The UFS is intended to be read as a whole, and sections should not be read or relied upon out of context.

Processing plant review

Stephan Buys, who is an Extractive Metallurgist with Lycopodium, independent to Montage, and fellow of AusIMM, is a Qualified

Person under NI 43-101 and has reviewed and approved the scientific and technical information contained in this news release

concerning the process plant. Mr. Buys has 30 years of experience in plant design, operations, and research in Africa, Australia,

Southeast Asia and South America's metals and minerals processing industry.