Montage GOLD Achieves Key Construction Milestone at Its Koné Project as Process Plant Concrete Works Commenced

Mine Development & Operations Metallurgy & Processing

Press

Release

montagegold.com 1

MONTAGE GOLD ACHIEVES KEY CONSTRUCTION MILESTONE AT ITS KONÉ

PROJECT AS PROCESS PLANT CONCRETE WORKS COMMENCED

Abidjan, Côte d’Ivoire — March 24, 2025 — Montage Gold Corp. (“Montage” or the “Company”) (TSXV: MAU, OTCQX: MAUTF) is

pleased to announce that rapid construction progress is being achieved at its Koné project in Côte d’Ivoire, where process plant

concrete works, including the ahead -of-schedule pouring of Carbon -in-Leach tank foundations, have commenced, marking an

important milestone.

Since the mid-December 2024 groundbreaking ceremony, construction activities at the Koné project have significantly ramped up,

with the on-site workforce increasing from approximately 350 to 1,700 employees and contractors. Strong progress has been made

to take advantage of the dry season, with process plant earthworks and foundations preparation, water storage facility preparation,

camp construction and process plant engineering, all advancing at a rapid pace . The project remains on track to pour gold in Q2 -

2027 and on budget with a pproximately 25% of the US$835 million capital spend committed thus far , with prices in line with

expectations.

Martino De Ciccio, Chief Executive Officer of Montage, commented: “We are very pleased with the rapid construction progress being

made at our Koné project in Côte d’Ivoire which builds on the momentum generated over recent quarters to progress our strategy of

creating a premier African gold producer and delivering value for all our stakeholders.

We are equally pleased with our ongoing exploration success and look forward to publishing maiden resources in the coming weeks

as we deliver against our previously published target of discovering at least 1 million ounces of Measured and Indicated Resources

at a grade which is 50% higher compared to the current Koné deposit grade, to be achieved before the commencement of

production1.”

Peder Olsen, President and Chief Development Officer of Montage, commented: “We are extremely pleased with the ramp-up of

our construction activities as it positions us to take full advantage of the dry season. We are benefiting from last year’s rapid success

achieved in securing our mining permit and financing, while commencing training programmes, conducting land compensation, and

ordering long-lead items.

Given this planning, we now have more than 100 machines on-site and our construction team has grown from 350 to 1,700 people

over the last three months, resulting in 730,000 hours worked without a lost-time injury, reflecting our strong focus on health and

safety. We are equally pleased with the advancement of the fabrication of long lead time items and in particular the mill.

I would like to thank our team for their strong efforts and dedication thus far, which places us in a strong position as construction

progresses”.

1For further information on the discovery target please refer to the Company’s news release dated October 7, 2024, and for information regarding the Koné deposit

please refer to the Updated Feasibility Study press release dated January 16, 2024 available on Montage’s website and on SEDAR+.

TSX.V MAU OTCQX MAUTF

montagegold.com 2

KONÉ PROJECT CONSTRUCTION UPDATE

Construction is progressing on-budget and on-schedule for first gold pour in Q2-2027, with key highlights summarized below:

› On-site workforce now comprises approximately 1,200 Montage employees and 500 contractors, both of which comprise over

90% Ivorian nationals. Demonstrating its commitment to local content, Montage partnered with the government -accredited

Lycée Technique de Mankono to provide practical vocational training programs tailored to the Koné project. Training

encompasses steel fixing, building , electricity, masonry, carpentry, plumbing, firefighting, working at heights, environmental

management, and heavy equipment operation.

› Strong continued safety record with no Lost Time Injury (“LTI”) with more than 730,000 man-hours worked.

› Treatment plant earthworks are more than 30% com plete and progressing well as the concrete pouring for the ring beams of

the Carbon-in-Leach tanks commenced 3-weeks ahead of schedule, as shown in Figure 1 below.

Figure 1: Process plant area overview and CIL ring beams

TSX.V MAU OTCQX MAUTF

montagegold.com 3

› Long-lead items are all ordered and fabrication commenced , including the ball mill, gyratory crusher, cone crushers, HPGR,

thickeners, CIL bolted tanks, and reagent storage building.

Figure 2: Mill gear casting and shell being fabricated

› Engineering, design, and procurement is being conducted by Lycopodium Minerals Pty Ltd (“Lycopodium”), along with

Montage’s in-house construction team, following the award of the engineering, procurement and construction management

(“EPCM”) contract given their involvement in the project sinc e 2018 and their strong track record in West Africa. Infrastructure

detailed design is scheduled to be completed in Q2 -2025, and process plant engineering and procurement is 30% complete

compared to the 17% target within the baseline schedule. Key civil design areas such as that for the CIL ring beams, the mill raft,

and the reagent foundation have been issued for construction. Detailed design of the steel work for the CIL trains, main pipe

racks, thickeners and the elution building are nearing completion, while the steel and platework fabrication contracts have been

awarded.

TSX.V MAU OTCQX MAUTF

montagegold.com 4

› Earthworks equipment has been received, comprising 35 dump trucks, eight 20-tonne vibrating compactors, 10 excavators, 4

bulldozers, 3 graders, 8 concrete trucks, 5 telehandlers, 2 container loaders, and 4 90-tonne rough terrain cranes , as shown in

Figure 3 below.

Figure 3: Major earthworks and construction equipment on-site

› Water Storage Facility is more than 35% complete and ahead of schedule, with trench excavation and backfilling preparation for

final lining and dam wall construction underway, as shown in Figure 4 below.

Figure 4: Water Storage Facility preparation

› Access roads and laydown yard is more than 60% complete, with key drainage infrastructure installed.

› Tailings Storage Facility (“TSF”) key equipment is on schedule to be delivered in Q3 -2025, while the TSF haul road is more than

35% complete.

› Power will be drawn from the national grid operator, Compagnie Ivoirienne d’Electricite (“CIE”), via a new 225kV transmission

line connecting to existing power lines located approximately 20km from the processing plant area. The CIE has confirmed

capacity to mee t the demand requirements for the Koné project and Montage has conducted a power system study with CIE

which supports the delivery of high -quality power. A project management agreement has been executed with CIE and works

commenced on-site with clearing for the sub-station.

TSX.V MAU OTCQX MAUTF

montagegold.com 5

› Permanent camp construction is well advanced with 80 rooms now complete, with a further 160 prefabricated rooms under

assembly, as shown in Figure 5 below.

Figure 5: Permanant camp construction progress

› Gbongogo haul road construction is nearing completion with final grading and windrow installations underway to ensure

efficient access to mining zones.

Figure 6: Gbongogo haul road nearing completion

TSX.V MAU OTCQX MAUTF

montagegold.com 6

› Resettlement Action Plan is progressing well, with compensation agreements signed with landowners in priority construction

areas.

Figure 7: Resettlement area preparation and early works

› Livelihood Restoration Plan is underway with projects launched focusing on agricultural development and financial literacy

programs. A total of 130 individuals from affected villages were also trained in civil construction works at accredited institutions,

enhancing employability and aligning with our local employment policy. In addition, over 450 individuals from impacted

communities received free literacy training providing empowerment and employment opportunities.

TSX.V MAU OTCQX MAUTF

montagegold.com 7

Timeline to first gold pour

The Company remains on track for first gold pour in Q2-2027, based on a 27-month construction period for the process plant , with

key upcoming milestones presented in Table 1 belo w. As noted above, major construction works for the water storage dam , site

infrastructure, and earth and concrete works are well underway . Approximately 25% of the US$835 million capital has been

committed thus far, with prices in line with expectations.

Table 1: Koné project timeline to first gold pour

Work Stream Q1-2025 Q2-2025 Q3-2025 Q4-2025 Q1-2026 Q2-2026 Q3-2026 Q4-2026 Q1-2027 Q2-2027

Tailings Dam & Water Dams

Tailings Dam * * *

Water Storage & Dam * *

Construction

Power Supply * * * * *

Site Infrastructure * * * * * * *

Earth works & Concrete Works * * * * * *

Structural, Mechanical, Piping * * * * * *

Electrical * * * *

Process Plant Commissioning * *

First Gold *

Exploration activities

Montage remains on track to achieving its short-term exploration target, as published on October 7, 2024, of discovering more than

1Moz of Measured and Indicated Resources, at a grade 50% higher than the Koné deposit, to be achieved before the commencement

of production. Achieving the set exploration target would represent a significant return on the exploration investment and aligns

with the Company’s strategic objective of boosting production from the commencement of production while maintaining an annual

production of at least 300koz for more than 10 years1.

The 2024 drilling campaign comprised a total of over 81,000 meters across the Koné project for a total expenditure of approximately

US$13 million. Given the success of the drill programme, Montage expects to publish maiden resources in the coming weeks for

notably the new discoveries made.

The 2025 drilling campaign is well underway, comprising 90,000 meters of drilling at an approximate cost of US$14 million, focused

on both resource delineation of existing deposits and testing new targets.

Neither TSX Venture Exchange nor its Regulation Services Provider accepts responsibility for the adequacy or accuracy of this

release.

ABOUT MONTAGE

Montage Gold Corp. (TSXV: MAU) is a Canadian -listed company focused on becoming a premier multi -asset African gold producer,

with its flagship Koné project, located in Côte d’Ivoire, at the forefront. Based on the Updated Feasibility Study published in 2024

(the “UFS”), the Koné project has an estimated 16 -year mine life and sizeable annual production of +300koz of gold over the first 8

years and is expected to enter production in Q2-2027.

TSX.V MAU OTCQX MAUTF

montagegold.com 8

TECHNICAL DISCLOSURE

Mineral Resource and Reserve Estimates

The Koné and Gbongogo Main Mineral Resource Estimates were carried out by Mr. Jonathon Abbott of Matrix Resource Consultants

of Perth, Western Australia, who is considered to be independent of Montage. Mr. Abbott is a member in good standing of the

Australian Institute of Geoscientists and has sufficient experience which is relevant to the commodity, style of mineralisation under

consideration and activity which he is undertaking to qualify as a Qualified Person under NI 43 –101.

The Mineral Reserve Estimate was carried out by Ms. Joeline McGrath of Carci Mining Consultants Ltd., who is considered to be

independent of Montage. Ms. McGrath is a member in good standing of the Australian Institute of Mining and Metallurgy and has

sufficient experience which is relevant to the work which she is undertaking to qualify as a Qualified Person under NI 43 –101.

QUALIFIED PERSONS STATEMENT

The scientific and technical contents of this press release have been verified and approved by Mr. Peder Olsen, a Qualified Person

pursuant to NI 43 -101. Mr. Olsen, President and Chief Development Officer o f Montage, is a registered Fellow of the Australasian

Institute of Mining and Metallurgy (AusIMM).

CONTACT INFORMATION

For Investor Relations Inquiries:

Jake Cain

Strategy & Investor Relations Manager

[email protected]

+44-7788-687-567

For Media Inquiries:

John Vincic

Oakstrom Advisors

[email protected]

+1-647-402-6375

For Regulatory Inquiries:

Kathy Love

Corporate Secretary

[email protected]

+1-604-512-2959

FORWARD-LOOKING STATEMENTS

This press release contains certain forward -looking information and forward -looking statements within the meaning of Canadian

securities legislation (collectively, “Forward-looking Statements”). All statements, other than statements of historical fact, constitute

Forward-looking Statements. Words such as “will”, “intends”, “proposed” and “expects” or similar expressions are intended to

identify Forward-looking Statements. Forward-looking Statements in this press release include statements related to the Company’s

objectives of achieving first gold pour in the second quarter of 2027; timing for various parts of the construction at the Koné Project;

the Company’s mineral reserve and resource estimates; timing for various parts of the construction at the Koné Project; the timing

and amount of future production from the Koné Project; anticipated mining and processing methods of the Koné Project; anticipated

mine life of the Koné Project.

Forward-looking Statements involve various risks and uncertainties and are based on certain factors and assumptions. There is no

assurance that any economic satellite deposits will be discovered, and if discovered ever developed or mined. There can be no

assurance that any Forward-looking Statements will prove to be accurate, and actual results and future events could differ materially

from those anticipated in such statements. In particular, there is no assurance that any economic satellite deposits contai ning

additional resources will be discovered, and if discovered ever developed or mined. Important factors that could cause actual results

to differ materially from the Company's expectations include uncertainties inherent in the preparation of mineral reserve and

resource estimates and definitive feasibility studies such as the Mineral Reserv e Estimate and the UFS, and in delineating new

mineral reserve and resource estimates, including but not limited to, assumptions underlying the production estimates no t being

realized, incorrect cost assumptions, unexpected variations in quantity of mineralized material, grade or recovery rates being lower

than expected, unexpected adverse changes to geotechnical or hydrogeological considerations, or expectations in tha t regard not

being met, unexpected failures of plant, equipment or processes (including construction equipment), delays in or increased co sts

for the delivery of construction equipment and services, or supplies for operation of the mine, labour shortages o r disruptions,

unexpected changes to availability of power or the power rates, failure to maintain permits and licenses, higher than expecte d

interest or tax rates, adverse changes in project parameters, unanticipated delays and costs of consulting and accommodating rights

of local communities, environmental risks inherent in the Côte d’Ivoire, title risks, including failure to renew concessions,