Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MARI.TO ·

Exceptional PEA Results for the Marimaca Project including US$524 million post-tax real NPV8 and 33.5% IRR

Economic Studies

News Release

Exceptional PEA Results for the Marimaca Project including

US$524 million post-tax real NPV8 and 33.5% IRR

Vancouver, British Columbia, August 4, 2020 – Marimaca Copper Corp. (“Marimaca Copper” or the “Company”)

(TSX: MARI) is pleased to announce the results of the Preliminary Economic Assessment (“PEA”) for the Company’s

flagship Marimaca Copper Project (“Marimaca” or “the Project”), located in northern Chile . The study confirmed that

the Project has the potential to be a very low capital and operating cost copper producer. The Company will host a

webinar to present the results of the study on Wednesday the 9th of September 2020.

Highlights

• US$524 million post-tax NPV8 (real) assuming a US$3.15/lb flat long-term copper price

o Payback of 2.6 years

o Post-tax IRR of 33.5%

• US$640 million post-tax NPV8 (real) assuming a US$3.45/lb flat long-term copper price

o Payback of 2.4 years

o Post-tax IRR of 38.0%

• Average annual steady state EBITDA of US$169 million

• Pre-production capital cost of US$285 million

o Capital intensity of US$7,125/tonne of copper production capacity

o Assumes mining fleet is purchased via lease to own to minimize upfront capital costs

• Profitability Index (NPV/Capex) of 1.8x

• Life of mine average all-in-sustaining cash costs of US$1.29/lb of copper1

o Life of mine average C1 Cash Costs of US$1.22/lb of copper2

• Conventional open pit mining focused exclusively on oxide mineralization

o Life of mine stripping ratio of 0.84:1

o Highest grade feed materials available in first five years of production resulting in improved payback and

overall economics

• Conventional heap leach, SX-EW, processing circuit

o Projected average life of mine metallurgical recoveries in heap leach of approximately 76% of total copper

supported by data from several metallurgical testing programs

o Process makes use of readily available sea water

• Average annual steady state copper production over first 6 yrs of close to 40,000 tonnes of cathode

o Total mine life of 12 years

o Total recovered copper of approximately 430,000 tonnes over the life of mine

• Significant ongoing exploration potential for both oxide and sulphide mineralization which could substantially

extend the mine life of the Project

The Preliminary Economic Assessment is considered preliminary in nature and includes Inferred Mineral Resources that

are considered too speculative, geologically, to have the econ omic considerations applied that would enable

classification as Mineral Reserves. There is no certainty that the conclusions within the PEA will be realized. The PEA is

1 All in sustaining costs is defined as cash cost (C1) plus general and administrative expenses, sustaining capital expenditure,

deferred stripping, royalties and lease payments and is used by management to evaluate performance inclusive of sustaining

expenditure required to maintain current production levels.

2 C1 cash cost includes all mining and processing costs less any profits from by-products and is used by management to arrive

at an approximated cost of finished metal.

based on the material assumptions outlined in this document. These include assumption s about the availability of

funding. While the Company considers all of the material assumptions to be based on reasonable grounds, there is no

certainty that they will prove to be correct or that the range of outcomes indicated by the PEA can be achieved.

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have

demonstrated economic viability.

Luis Tondo, CEO of Marimaca Copper commented:

“The exceptional results of the PEA have confirmed our belief that Marimaca is a development stage copper project of

the highest quality. Its pre -production capital costs place s it in the very lowest tranche of projects in the copper

development space, whi le its low operating costs, which place s it in the bottom quartile of operating copper mines

globally, means that the project will be profitable even in lower copper price environments.

“The Marimaca Project is substantially more de-risked than a typical PEA level project due, primarily, to the significant

amount of technical work we have already completed, which includes four phases of metallurgical testing, geotechnical

studies, nearly 100,000 metres of drilling over the Project and engagement with various input providers for the Project.

“In a commodity which is dominated by large, technically challenging projects in difficult jurisdictions, that carry with

them a level of development and operating risk commensurate with their size and complexity, Marimaca represents a

copper development p roject at the other end of the spectrum. Marimaca is a project, located in a tier 1 mining

jurisdiction, that can be both financed and built with lower levels of execution risk, and which provides a platform for

Marimaca Copper to become a mid-tier copper producer in the future.”

Figure 1: 2026 Projected All-in-Sustaining Cash Cost Curve

Executive Summary of Preliminary Economic Assessment

The Preliminary Economic Assessment (“PEA”) for Marimaca was completed by Ausenco Engineering in conjunction

with several Qualified Persons in various technical fields including NCL Ingeniería y Construcción SpA (“NCL”) for mining

and mine design and mineral resource estimation, and Jo Loyola Consultores de Procesos SpA (“JLCP”) on metallurgy

and process design.

The PEA was prepared in accordance with the requirements of the National Instrument 43-101, Standards of Disclosure

for Mineral Projects, (“NI43-101”) and is based on a Mineral Resource Estimate (“MRE”) completed by NCL, which

comprised 70 million tonnes, with an average grade of 0.60% total copper within the Measured & Indicated Categories

of mineral resources (approximately 420Kt of contained copper), and 40 million tonnes with an average grade of 0.52%

total copper within the Inferred Category of mineral resources (approximately 224kt of contained copper) (refer release

on 2 December 2019). The Preliminary Economic Assessment is considered preliminary in nature and includes Inferred

Mineral Resources that are considered too speculative, geologically, to have the economic considerations applied that

would enable classification as Mineral Reserves. There is no certainty that the conclusions within the PE A will be

realized. The PEA is based on the material assumptions outlined in this document. These include assumptions about

the availability of funding. While the Company considers all of the material assumptions to be based on reasonable

grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the PEA can

be achieved.

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have

demonstrated economic viability.

Marimaca is amenable to bulk, open pit, mining methods and this study contemplates an owner operated fleet utilising

a leasing option to minimise upfront capital c osts associated with fleet purchase. The deposit ’s favourable geometry

provides the Project with a low life of mine strip ratio of 0.84:1 as well as higher average grade in the first five years of

mine life. This shortens the capital payback period and improves overall economics for the Project.

Due to the oxide resource, processing is via a standard heap leach and Run-of-Mine (“ROM”) leach using sulphuric acid

and seawater followed by conventional solvent extraction and electrowinning to produce an average of nearly 40,000

tonnes per annum of high grade copper cathode during steady state production. Heap leach pads are designed as

dynamic leach pads where leach residue, known as ripios, are removed after the leaching cycle and stored in a

dedicated waste facility. ROM leach pads are designed as static leach pads, with stack height increasing over the life of

the mine.

Average recovery over the life of mine for the heap leach is estimated to be approximately 76% of total copper, and

ranges from a high of approximately 82% in the pure oxide zones (brochantite / atacamite), which make up the majority

of the project, down to approximately 49% in the enriched mineral subzone, which comprises a much smaller

proportion of the overall mineable resource. Recovery over the life of mine for the ROM leach is estimated to be

approximately 40% of total copper, comprising 9% of the estimated total copper cathode produced during the life of

mine.

Summary of Economic Assumptions and Results

Copper Price Assumption US$3.15/lb flat real

Pre-Tax NPV8 & IRR US$757 million / 39.9%

Post-Tax NPV8 & IRR US$524 million / 33.5%

Payback Period from First Production 2.6 years

Pre-Production Capital Costs US$285 million3

Life of Mine Sustaining Capital US$66 million

Ave. Annual Steady State EBITDA US$169 million

Life of Mine C1 Operating Costs US$1.22/lb of copper4

Life of Mine All-in-Sustaining Cash Costs US$1.29/lb of copper5

Mine Life 12 years

Ave. Annual Metal Production (first 6 years) Approximately 40,000 tonnes

Ave. Annual Metal Production Life of Mine (incl. ramp up) 35,600 tonnes

Steady State Average Process Recovery (Heap and ROM) 76% / 40%

Table 1: Summary of Economic Assumptions and Results

Economics and Sensitivity Analysis

Copper Price

US$/lb

Post-Tax NPV8

Base Case

US$ millions

Post-Tax NPV8

Capex (-10%)

US$ millions

Post-Tax NPV8

Capex (+10%)

US$ millions

Post-Tax NPV8

Opex (-10%)

US$ millions

Post-Tax NPV8

Opex (+10%)

US$ millions

Base Case

IRR

(%)

2.85 408 434 381 455 360 28.6%

3.00 466 492 439 514 418 31.1%

3.15 524 550 498 572 476 33.5%

3.30 582 608 556 630 535 35.7%

3.45 640 666 614 688 592 38.0%

Table 2: Sensitivity Analysis to Copper Price, Life of Mine Capital and Operating Costs

3 Assumes mining fleet is financed through a lease to own contract structure to m inimize upfront capital cost.

4 All in sustaining costs is defined as cash cost (C1) plus general and administrative expenses, sustaining capital expenditure ,

deferred stripping, royalties and lease payments and is used by management to evaluate performance inclusive of sustaining

expenditure required to maintain current production levels.

5 C1 cash cost includes all mining and processing costs less any profits from by-products and is used by management to arrive

at an approximated cost of finished metal.

PRELIMINARY ECONOMIC ASSESSMENT OF THE MARIMACA COPPER PROJECT

Geology and Mineral Resource Estimate

The Marimaca Project comprises a dominant structural feature of broad zones of sheeted dykes and fracture zones,

oriented north-north-east and dipping 45-60o to the east, which host copper mineralisation at surface. The location of

the Marimaca deposit is interpreted to be controlled by a dilational structural jog and the Company believes that this

control applies both to the MOD and to its downwards continuation into the sulphide zone. There is strong evidence

that the oxide zones encountered at surface we re generated as a result of the in -situ oxidation of primary sulphide

minerals, mostly chalcopyrite.

The PEA is based on the MRE, which was released to the market in January 2020 (refer to release on 2 December 2019).

The PEA includes Inferred Mineral Resources that are considered too speculative, geologically, to have the economic

considerations applied that would enable classification as Mineral Reserves. There is no certainty that the conclusions

within the PEA will be realized. The PEA is based on the material assumptions outlined in this document. These include

assumptions about the availability of funding. While the Company considers all of the material assumptions to be

based on reasonable grounds, there is no certaint y that they will prove to be correct or that the range of outcomes

indicated by the PEA can be achieved.

No mineral reserves have been estimated for the project. Mineral Resources are not Mineral Reserves and do not have

demonstrated economic viability.

The MRE was based on 346 reverse circulation holes (“RC”) and 39 diamond holes (“DD”) for a total of 91,210m drilled

between 2016 and 2019 and was completed at a range of Cut-Off grades by independent consultants NCL Ingeniería y

Construcción SpA (“NCL”). To demonstrate reasonable prospects for eventual economic extraction, a series of Lerchs-

Grossmann pit shell optimizations was completed by NCL, utilizing appropriate operating costs, recoveries obtained

from metallurgical test work, and a long term US$3 .00/lb copper price. The resources were estimated only for oxide,

mixed, wad and enriched copper mineralization which can be processed by heap leaching (HL) and run of mine (ROM)

dump leaching followed by solvent -extraction and electrowinning to produce co pper cathode. Primary sulphide

mineralization occurring in deeper parts of the deposit, which are within the constraining pit shell, is not included in

the MRE or for the purposes of this PEA.

Cut-off

grade

(% CuT)

Measured Indicated Measured + Indicated Inferred

Mineral

kt

CuT

(%)

CuS

(%)

Mineral

kt

CuT

(%)

CuS

(%)

Mineral

kt

CuT

(%)

CuS

(%)

Mineral

kt

CuT

(%)

CuS

(%)

0.40 14,403 0.81 0.55 30,600 0.74 0.48 45,003 0.76 0.50 23,607 0.70 0.40

0.30 17,865 0.72 0.49 40,253 0.64 0.42 58,118 0.67 0.44 33,410 0.60 0.35

0.22 20,721 0.66 0.44 49,666 0.57 0.37 70,387 0.60 0.39 43,015 0.52 0.31

0.18 22,072 0.63 0.42 54,109 0.54 0.35 76,181 0.57 0.37 47,164 0.49 0.29

0.10 23,087 0.61 0.41 57,619 0.52 0.33 80,706 0.54 0.35 50,641 0.47 0.27

Table 3: NI43-101 Mineral Resource Estimate at Various Cut-off Grades

* CuT means total copper and CuS means acid soluble copper. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral

resource technical and economic parameters included: copper price US$3.00/lb; mining cost US$2.00/t; HL processing cost including G&A US$9.00/t; ROM processing

cost including G&A US$2.50/t; selling cost US$0.07/lb Cu; heap leach recovery 76% of CuT; ROM recovery 40% of CuT and a 44°-46°pit slope angle

The deposit has a significant higher-grade zone which occurs from surface in its southern extent and provides a logical

target for the early years of mine life at Marimaca. The average grade expected during the first five years of mine life

is 0.78% total copper and is dominantly comprised of the main oxide mineral sub-zones of brochantite, atacamite and

chrysocolla.

Significant potential exists to increase oxide resources within proximity to Marimaca, but also in the broader claims

packages that surround this exciting project. Furthermore, the Company has recently released the results of a high -

resolution, drone mounted, magnetic survey, which indicates substantial potential for sulphide mineralization below

the Marimaca Oxide Deposit (refer to announcement on 14 July 2020).

Figure 2: Plan View and Long Section of Mineral Resource Estimate Highlighting

High Grade Zones from Surface

Mining

The Marimaca Oxide Deposit commences at surface and its geometry means that it is amenable to bulk, open pit,

mining methods, which have been contemplated for the purposes of this study. The study considers an owner operated

mining fleet based on lease to own contracts with reputable heavy equipment providers.

The mine will utilise convention drilling, blasting and shovel loading into trucks on bench heights of 10-20 m depending

on location within the open pit. The mine plan was designed to deliver a consistent production profile of approximately

40,000 tonnes per annum of copper cathode during steady state operations.

The open pit was designed based on eight phases of development targeting the higher grade, dominantly oxide,

mineralisation in the central portion of the deposit area in the early years of the mine life and gradually expanding, and

deepening the pit, over the mine life.

Due to the higher grade of the early years of mine life, the heap leach production tonnes in years 1 to 5 are designed

to average approximately 5.4Mtpa before increasing from year 6 onwards to approximately 9.0Mtpa of material. The

ROM leach production was designed to be variable to minimize the use of stockpiles, which can add complexity to the

mine planning and management, and ranges f rom a low side of 588ktpa up to a maximum of 6Mtpa of ROM leach

material.

Figure 3: Open Pit Development Phases

The open pit has a low life of mine strip ratio (including pre-stripping) of 0.84:1. The strip ratio has decreased from the

mineral resource estimate (at a cut-off of 0.22% total copper) because, in mine planning, it was noted that numerous

areas of mineralized waste (less than 0.22% total copper) are mined in the proposed PEA mine plan. Although they

may be considere d as marginal on the heap leach, these tonnes are considered to be economic on the ROM leach,

where the additional costs of crushing and agglomeration are removed. As a result, these tonnes, which would have

previously been classified as waste, have now be en classified as mineable resource for the purposes of copper

production.