Minera Alamos Receives Positive Notice Regarding Permit Applications for La Fortuna Gold Project in Durango, Mexico

Permits & Approvals

Minera Alamos Receives Positive Notice Regarding

Permit Applications for La Fortuna Gold Project in

Durango, Mexico

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - November 21, 2018) - Minera Alamos Inc. (TSXV: MAI)

("Minera" or the "Company") is pleased to announce that it has received a positive notification from the Mexican environmental

authorities (Secretaria de Medio Ambiente y Recursos Naturales - "SEMARNAT") regarding the Company's permit application

(MIA/ETJ) for the development of the La Fortuna Gold Project ("Fortuna").

The notification confirms the successful completion of

the technical review phase of the Company's application (Estudio Tecnico Justificativo - "ETJ") for the change of land use to

construct mining and processing facilities at the Fortuna project area.

Following the completion of the change of land use

payments, SEMARNAT will be in a position to issue the formal approval documentation for the project.

"The receipt of this notification represents a major milestone for the Company.

Despite some procedural changes in the

MIA/ETJ application process that caused early delays, the notice was received a little over a year following the completion of our

strategic partnership with Osisko Gold Royalties and starts the transformation of the Company from a junior explorer to a

growing gold producer," stated Darren Koningen, CEO of Minera Alamos.

"Our highly experienced Mexican technical team

continues to demonstrate the ability to advance concurrently our full portfolio of late-stage gold development projects.

Mexico

remains one of the world's premier mine development locations with respect to the timeframes required for permitting of new

operations.

We now eagerly await similar notifications regarding the Company's Santana gold project which remains our first

priority for construction consideration in 2019 according to the Company's current development schedule."

The receipt of a MIA-ETJ permits for the Fortuna project will allow the Company to initiate applications for other state/local

permits that will be required in advance of any commercial mine production.

These cover activities such as water use and

explosives.

In addition, the Company can advance discussions with potential contractors related to mining, crushing,

construction, etc.

The Fortuna MIA-ETJ applications were structured to provide the Company with significant flexibility to further

optimize the development approach for the project and the ability to expand the project operations organically once resources

are increased.

In advance of a final construction decision, the Company has also initiated discussions with a number of project finance groups

that can provide debt facilities complementary to the Fortuna royalty structure arranged with strategic partner Osisko Gold

Royalties.

The recently completed PEA (

see news release dated August 16

th

2018

) for the project demonstrated an after-tax

internal rate-of-return in excess of 90%, a rapid payback of capital of approximately one year and low production costs for an

initial 50,000 oz (AuEq) per annum operation (

see La Fortuna Gold Project below

).

As planning activities are refined in the coming year (2019) the Company will provide regular updates regarding ongoing

advancements at the Fortuna project.

The PEA identified several opportunities to further enhance the overall project economics

and these are currently under review.

Included in this list are the following:

Additional metallurgical studies to further optimize the gold extraction process and improve overall metal recoveries.

A staged plant construction plan (possibly involving earlier use of ore sorting technology) to reduce the initial start-up

CAPEX and then expand the facilities once production is underway.

Mine planning studies to evaluate opportunities to delay portions of early waste removal until later in the mine life

Consideration of more aggressive use of ore sorting to offer additional economic benefits for the project (i.e. plant CAPEX

reductions, increased mineable gold ounces, etc.)

Trade-off studies aimed at optimizing cut-off grades (with or without ore sorting) and the incorporation of additional milling

capacity - the project is permitted for a 2,000 tpd operation with the PEA based on a starting rate of 1,100 tpd.

In addition to the engineering activities, the Company is also preparing for some new exploration at the Fortuna project.

The

footprint of the currently drilled deposit is small compared to the overall land position (6,200 Ha) and a number of other areas of

historical mining activity have been identified with most having never been evaluated using modern exploration methods.

La Fortuna Gold Project

Details of potential development plans for the Fortuna Gold project were prepared in an independent Preliminary Economic

Assessment ("PEA") completed by CSA Global Geosciences Canada Ltd (CSA Global) of Toronto, Canada.

For a detailed

summary of the PEA contents refer to a previous news release issued by the Company dated August 16

th

2018.

(

Note to reader: Unless stated all

currency

references are in US dollars).

Table 1 -

PEA Summary

US$

CDN$

Pre-Tax NPV (7.5%)

$103,800,000

$134,800,000

Pre-Tax IRR

122%

122%

After-Tax NPV (7.5%)

$69,800,000

$90,600,000

After-Tax IRR

93%

93%

Pre-Tax Payback Period

9 months

After-Tax Payback Period

11 months

Average Annual Production

43,000 oz Gold, 220,000 oz Silver, 1,000 t Copper (50koz GEO

1

)

Preproduction Capital

$26,900,000

$34,900,000

LOM Average AISC

2

$440/oz

$571/oz

Mine Life

5 years

Mill Throughput (avg. tpd)

1,100

Mill Grade & Recovery

3.68 g/t Au (90% recovery)

Gold Price

$1,250/oz

Silver Price

$16/oz

Copper Price

$5,725/tonne

FX Rate (CDN$/US$)

0.77

Notes:

1

.

GEO - Gold Equivalent Ounces

2

.

"AISC per ounce" is a non-GAAP financial performance measures with no standardized definition under IFRS; additional

reference info at bottom of release

3

.

Base case prices for gold, silver and copper were assessed at values approximately 2%-7% below the three-year trailing

average prices for each of the metals and below the majority of the publicly available forward looking estimates available

as of July 2018

PEA Cautionary Note:

Readers are cautioned that the PEA is preliminary in nature and there is no certainty that the PEA results will be realized.

Mineral resources are not mineral reserves and do not have demonstrated economic viability. Additional work is needed to

upgrade these mineral resources to mineral reserves.

Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the technical content of this press

release under National Instrument 43-101. Mr. Koningen has supervised the preparation of, and has approved the scientific and

technical disclosures in this news release.

About

Minera Alamos

:

Minera Alamos is an advanced-stage exploration and development company with a growing portfolio of high-quality Mexican

assets, including the La Fortuna open-pit gold project in Durango with positive PEA completed, the Santana open-pit heap-

leach development project in Sonora with test mining and processing completed and the Guadalupe de Los Reyes open-pit

gold-silver project in Sinaloa with mine planning in progress.

The Company is awaiting the pending approval of permit

applications related to the commercial production of gold at both the Santana and Fortuna projects.

The Company's strategy is to develop low capex assets while expanding the project resources and pursue complementary

strategic acquisitions.

For Further Information Please Contact:

Minera Alamos Inc.

Doug Ramshaw, President

Tel: 604-600-4423

Email:

[email protected]

Website:

www.mineraalamos.com

NON-GAAP

Financial Performance Measures

The Company has included certain non-GAAP performance measures (All-in Sustaining Cost - "AISC") in this document.

The

Company believes that, in addition to conventional measures prepared in accordance with GAAP, certain investors and other

stakeholders also use this information to evaluate the Company's economic performance estimates; however, these non-GAAP

performance measures do not have any standardized meaning. Accordingly, these performance measures are intended to

provide additional information and should not be considered in isolation or as a substitute for measures of performance

prepared in accordance with GAAP. The Company's primary business is gold asset development and maximizing returns from

future gold production, with other metal production being incidental to the gold production process. As a result, where applicable,

the Company's non-GAAP performance measures are disclosed on a per gold ounce basis.

The Company has followed the

guidance note released by the World Gold Council, which became effective January 1, 2014. The World Gold Council is a non-

regulatory market development organization for the gold industry whose members comprise global senior gold mining

companies.

Caution Regarding Forward-Looking Statements:

This news release may contain forward-looking information and Minera Alamos cautions readers that forward-looking

information is based on certain assumptions and risk factors that could cause actual results to differ materially from the

expectations of Minera Alamos included in this news release. This news release includes certain "forward-looking statements",

which often, but not always, can be identified by the use of words such as "believes", "anticipates", "expects", "estimates",

"may", "could", "would", "will", or "plan". These statements are based on information currently available to Minera Alamos and

Minera Alamos provides no assurance that actual results will meet management's expectations. Forward-looking statements

include estimates and statements with respect to Minera Alamos' future plans with respect to the Projects, objectives or goals, to

the effect that Minera Alamos or management expects a stated condition or result to occur and the expected timing for release

of a resource and reserve estimate on the Projects. Since forward-looking statements are based on assumptions and address

future events and conditions, by their very nature they involve inherent risks and uncertainties. Actual results relating to, among

other things, results of exploration, the economics of processing methods, project development, reclamation and capital costs of

Minera Alamos' mineral properties, the ability to complete a preliminary economic assessment which supports the technical and

economic viability of mineral production could differ materially from those currently anticipated in such statements for many

reasons. Minera Alamos' financial condition and prospects could differ materially from those currently anticipated in such

statements for many reasons such as: an inability to finance and/or complete an updated resource and reserve estimate and a

preliminary economic assessment which supports the technical and economic viability of mineral production; changes in general

economic conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation, legislative,

environmental and other judicial, regulatory, political and competitive developments; technological and operational difficulties

encountered in connection with Minera Alamos' activities; and other matters discussed in this news release and in filings made

with securities regulators. This list is not exhaustive of the factors that may affect any of Minera Alamos' forward-looking

statements. These and other factors should be considered carefully and readers should not place undue reliance on Minera

Alamos' forward-looking statements. Minera Alamos does not undertake to update any forward-looking statement that may be

made from time to time by Minera Alamos or on its behalf, except in accordance with applicable securities laws.

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN

THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY

OF THIS RELEASE.