Minera Alamos Provides Santana Mine Construction Update

Mine Development & Operations

Minera Alamos Provides Santana Mine

Construction Update

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - January 27, 2021) -

Minera

Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos")

is pleased to provide a construction

update detailing progress at the Santana gold project, Sonora, Mexico, as the Company advances

towards the commencement of mining.

Leach solution ponds (barren and pregnant) are now fully lined and ready for operations (see

Photo 1 below).

The plant foundations have been completed and all previously fabricated plant structures (including

carbon columns for gold recovery) have been delivered to site in preparation for final installation

that is now underway.

The majority of the civil works for the heap leach pad area have been completed and the

installation of the pad liner has commenced this week.

Foundations for additional site infrastructure items including the warehouse and fuel storage areas

are also complete.

The crushing system previously acquired for potential future expansions at Santana or at the

Company's Cerro de Oro project is in transit from the U.S. to the Company's staging facilities in

Obregon, Sonora

The Company is well funded to complete construction of Santana while advancing development

activities across its pipeline of projects.

"We have made tremendous progress towards the completion of construction at the Santana gold

project since activities were allowed to restart around the middle of last year following the widespread

Covid-19 shutdowns.

Major civil works are now drawing to an end and the focus has shifted towards the

final placement of field connections required for fluid handling systems involved in the leach process.

The

overall project site is quickly taking shape with the plant, remaining buildings and storage facilities all

beginning their final construction and installation phases over the coming month.

In parallel, our mining

group continues to finalize start-up optimization plans for the Nicho and Nicho Norte open pits." stated

Darren Koningen, CEO of Minera Alamos. "We would like to take this opportunity to thank our

contractors and team in Mexico for the excellent progress in building the Santana operation at a time

where so many logistical challenges presented themselves. As construction activities draw to a close at

Santana the project's development is a testament to their hard work and commitment."

Photo 1- Lined Solution Ponds with Plant location in background

To view an enhanced version of Photo 1, please visit:

https://orders.newsfilecorp.com/files/4183/72948_32db0b2a54e3e8a5_002full.jpg

With the vast amount of construction activity in 2020 revolving around earthworks for the plant, ponds and

pad the final installation of liners and plant process equipment is moving forward quite rapidly as can be

seen in the transition from unlined to fully lined ponds in just a few weeks (Photo 1).

The main pad liner is

expected to be installed over the coming weeks in parallel with the final installation and connection of

equipment related to the gold recovery plant.

Photo 2 - Panoramic Site showing Plant foundations adjacent to Solution Ponds (December

2020)

To view an enhanced version of Photo 2, please visit:

https://orders.newsfilecorp.com/files/4183/72948_32db0b2a54e3e8a5_003full.jpg

Crushing System

In 2020 the Company was able to acquire a complete crushing, screen and agglomeration system

suitable for gold heap leach operations including the associated material handling systems and power

generation infrastructure.

The system is currently being transported from the U.S. where it had been

stored to the Company's existing storage facilities in Obregon, Sonora.

Internal planning studies are

underway to finalize decisions as to which items will be designated for future use at the Santana

operation versus the Company's recently acquired Cerro De Oro gold project in Zacatecas.

Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the

technical content of this press release under National Instrument 43-101.

For Further Information Please Contact:

Minera Alamos Inc.

Doug Ramshaw, President

Tel: 604-600-4423

Email:

[email protected]

Website:

www.mineraalamos.com

Victoria Vargas de Szarzynski, VP Investor Relations

Tel: 289-242-3599

Email:

[email protected]

About Minera Alamos Inc.

Minera Alamos is a gold development company poised to join the ranks of gold producers in 2021. The

Company has a portfolio of high-quality Mexican assets, including the 100%-owned Santana open-pit,

heap-leach development project in Sonora that is currently under construction, and which is expected to

have its first gold production in early 2021.

The newly acquired 100%-owned Cerro de Oro oxide gold

project in northern Zacatecas that has considerable past drilling and metallurgical work completed and

could enter the permitting process rapidly. The La Fortuna open pit gold project in Durango (100%-

owned) has an extremely robust and positive preliminary economic assessment (PEA) completed and

the main Federal permits in hand. Minera Alamos is built around its operating team that together brought

3 mines into production in Mexico over the last 13 years.

The Company's strategy is to develop very low capex assets while expanding the projects' resources

and continuing to pursue complementary strategic acquisitions.

Caution Regarding Forward-Looking Statements:

This news release may contain forward-looking information and Minera Alamos cautions readers that

forward-looking information is based on certain assumptions and risk factors that could cause actual

results to differ materially from the expectations of Minera Alamos included in this news release. This

news release includes certain "forward-looking statements", which often, but not always, can be

identified by the use of words such as "believes", "anticipates", "expects", "estimates", "may", "could",

"would", "will", or "plan". These statements are based on information currently available to Minera

Alamos and Minera Alamos provides no assurance that actual results will meet management's

expectations. Forward-looking statements include estimates and statements with respect to Minera

Alamos' future plans with respect to the Projects, objectives or goals, to the effect that Minera Alamos or

management expects a stated condition or result to occur and the expected timing for release of a

resource and reserve estimate on the Projects. Since forward-looking statements are based on

assumptions and address future events and conditions, by their very nature they involve inherent risks

and uncertainties. Actual results relating to, among other things, results of exploration, the economics of

processing methods, project development, reclamation and capital costs of Minera Alamos' mineral

properties, the ability to complete a preliminary economic assessment which supports the technical and

economic viability of mineral production could differ materially from those currently anticipated in such

statements for many reasons. Minera Alamos' financial condition and prospects could differ materially

from those currently anticipated in such statements for many reasons such as: an inability to finance

and/or complete an updated resource and reserve estimate and a preliminary economic assessment

which supports the technical and economic viability of mineral production; changes in general economic

conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation,

legislative, environmental and other judicial, regulatory, political and competitive developments;

technological and operational difficulties encountered in connection with Minera Alamos' activities; and

other matters discussed in this news release and in filings made with securities regulators. This list is not

exhaustive of the factors that may affect any of Minera Alamos' forward-looking statements. These and

other factors should be considered carefully and readers should not place undue reliance on Minera

Alamos' forward-looking statements. Minera Alamos does not undertake to update any forward-looking

statement that may be made from time to time by Minera Alamos or on its behalf, except in accordance

with applicable securities laws.

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT

TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS

RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/72948