Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

MAI.V ·

Minera Alamos Announces Positive Preliminary Economic Assessment for The Cerro de Oro Gold Project After-Tax IRR of 111% and sub-$30 million CAPEX

Economic Studies

Minera Alamos Announces Positive

Preliminary Economic Assessment for The

Cerro de Oro Gold Project

After-Tax IRR of 111% and sub-$30 million CAPEX

Toronto, Ontario--(Newsfile Corp. - October 3, 2022) - Minera Alamos Inc. (TSXV: MAI) ("Minera" or the

"Company") is pleased to announce the positive results of an independent Preliminary Economic

Assessment ("PEA") for its Cerro de Oro Project (the "Project") in Zacatecas, Mexico. The PEA was

prepared in accordance with National Instrument 43-101

Standards of Disclosure for Mineral Projects

("NI 43-101") by Scott Zelligan, P.Geo., Lawrence Segerstrom, M.Sc.,CPG, Peimeng Ling, P.Eng., Alex

Duggan, P.Eng. and Toren Olsen, PG. A Technical Report with the details of the PEA will be filed on

SEDAR under the Company's profile within 45 days of the date of this news release. (

Note to reader:

Unless stated all currency references are in US dollars).

Highlights of PEA

Production highlights

Average annual gold production approaching 60,000oz (~60,000oz to 70,000oz in Years 1

through 4).

8.2 year mine life based on initial mineable total of 59 Mt of mineralization (0.37 g/t Au) heap

leached at an average rate of approximately 20,000 tpd -- +0.40 g/t Au in Years 1 through 4.

477koz of gold produced in loaded carbon/doré.

LOM strip ratio of 0.3:1 (waste: mineralization)

Robust economics using metals prices of $1,600/oz Au

LOM All-In Sustaining Cost (AISC) of $873/oz -- averaging $763/oz in Years 1 through 4.

After-Tax NPV at 5% of $150.5M and IRR of 111%.

Low capital intensity project with rapid payback:

Pre-production capital costs of $28.1M (includes 30% contingency).

Payback period of

11 months.

Used crushing plant already purchased reduces up-front capital requirements.

Significant Upside

Mineralization appears open in multiple directions as well as to depth.

Additional metallurgical testing to examine amenability of gold recovery from deeper

sulphide zones of mineralization not accounted for in current resource calculations and mine

plans (some early indications that material may prove to be leachable).

Updated Inferred Mineral Resource estimate containing 67 million tonnes of 0.37 g/t Au (790 koz

of contained gold) based on an upward revision of the base case resource metal price to

$1,700/oz.

"Leaning on our team's collective experience in mine building in Mexico with capital and operating costs

informed by the recent construction and ramp up of the Santana gold mine, the Cerro de Oro PEA is a

game changer for Minera as we strive to reach our initial target of a +100,000 oz/y gold producer,"

commented Doug Ramshaw, President. "Given the rampant inflationary pressures across the industry, it

is a testament to Minera's smart and nimble business model that a new mine could be developed at

Cerro de Oro for the low capital intensity presented in the PEA."

Table 1 - PEA Economic Parameters Summary

Cerro de Oro PEA Study

Life-of-Mine

Gold Price

1

$1,600/oz

Mine Life

8.2 years

Total Mineralization Processed

59.3M

Total Waste Mined

17.9M

Strip Ratio (Waste/Mineral)

0.30

Average Annual Tonnes Processed

2

7,300,000

Average Daily Tonnes Processed

2

20 ktpd

Heap Leach Gold Grade

3

0.37 g/t

Gold Recovery

68%

Average Annual gold production (oz)

2

58,400

Total Gold Recovered

476,610

Pre-production Capital

$28,080,000

Sustaining Capital

$14,700,000

Average AISC

4

$873/oz

After-Tax NPV (5%)

$150,500,000

After-Tax IRR

111%

After-Tax Payback Period

11 months

Exchange Rate (MXP/USD)

20

After-Tax NPV (10%)

$115,500,000

Net Cash Flows (undiscounted)

$200,000,000

Notes:

1

.

Base case price for gold was assessed using long term consensus pricing factoring in a modest discount against the average of available

bank and brokerage firm estimates.

2

.

Life-of-Mine Averages exclude partial production in year 9

3

.

LOM average combined grade of run-of-mine ("ROM") and crushed material sent to leach pads

4

.

"AISC per ounce" is a non-GAAP financial performance measures with no standardized definition under IFRS; additional reference info at

bottom of release

PEA Cautionary Note:

Readers are cautioned that the PEA is preliminary in nature and includes inferred resources that are

considered too speculative to have the economic considerations applied to them that would enable them

to be categorized as mineral reserves.

There is no certainty that the PEA results will be realized.

Mineral

resources are not mineral reserves and do not have demonstrated economic viability.

Additional work is

needed to upgrade these mineral resources to mineral reserves.

Capital Cost Estimates

Total pre-production capital costs at the Cerro de Oro Project are estimated at $28.1 million.

Sustaining

capital costs over the LOM are estimated at $14.7 million for a total Project capital cost of $42.8 million.

The pre-production capital cost estimate includes the construction of a stand-alone gold recovery (to

carbon) facility, Phase 1 of the heap leach pad construction and all necessary site infrastructure to bring

the mine into production.

Preliminary site layouts for the project were completed and included suitable areas for life of mine leach

pad areas, required pond volumes and other infrastructure items in addition to the process plant and

crushing operations.

Cost estimates are primarily based on cost factors/data obtained from the

company's recent project construction experience in Mexico including the Santana gold project

completed in 2021.

To reduce initial capital requirements all open pit mining operations and associated

capital costs are the responsibility of an independent mining contractor.

In addition, the company plans

to utilize (with some modifications) an existing crushing plant purchased previously and personnel will

stay in the local municipality eliminating the requirement for any significant mine site camp facilities.

Table 2 - Initial and Sustaining Capital Costs (CAPEX)

Area

Initial ($US)

Sustaining

($US)

Total ($US)

Preproduction technical work and engineering (geo tech

drilling, etc.)

1,500,000

1,500,000

Infrastructure and Misc. Construction

(excl. crushing)

3,000,000

Process Plant

3,400,000

Pad construction

7,000,000

13,200,000

21,200,000

Pond construction

2,700,000

Crushing and Stacking Refurbishment

2,000,000

Substation, Misc. Power

2,000,000

Contingency (30%)

6,480,000

Total Project

28,080,000

14,700,000

42,780,000

Operating Cost Estimates

The total unit operating cost for the Project is estimated at US$ 6.66/t of mineralised material (including

general and administrative costs - "G&A").

Operating costs were developed based on first principles

where possible including estimated staffing levels, reagent consumptions and power requirements.

Unit

costs and allowances for G&A, maintenance supplies, etc. are based on data from current Minera

Alamos facilities (Santana gold project) and other similar heap leach operations in Mexico.

Power

requirements for the process operation (excluding crushing) were estimated based on operating

equipment motor sizes and plant availability, and costs assume diesel generation with a delivered diesel

fuel cost of US$1.10/litre (approx. US$ 0.30/kWh).

Power for the crushing system is assumed to be

taken from the nearby power grid at a price of US$ 0.13/kWh.

An overall contingency of 20% was

applied to the operating cost totals to account for additional cost items such as outside contractors,

laboratory consumables, vehicle fuel requirements, etc.

All mine operating activities are assumed to be the responsibility of a third party mining contractor.

Contractor rates include drilling, blasting and transportation of the waste/ore. Costs for the Company

mine services group were prepared separately and included.

LOM operating costs are summarized in

Table 3 below. Actual annual costs in the economic models for the project will vary based on the

proposed annual mine schedule and utilize the unit costs detailed below.

Table 3 - Operating Costs (OPEX)

Area

US$/t mineralized

material

1

US$/t mined

2

Open pit mining

3

2.90

2.23

Crushing

4

0.52

0.40

Processing

2.29

1.76

G&A

0.32

0.25

Contingency (20%)

5

0.63

0.48

All-in OPEX

6.66

5.13

Notes:

1

.

"Mineralized Material" represents mined material estimated to generate positive cash flows

2

.

"Mined" means total tonnes mined (mineralized + waste)

3

.

Open pit mining cost is $2.00/t for waste and $2.30/t for mineralization.

A cost of $0.30/t mineralization has been included in the base case

mining cost for mineralization to account for a longer haulage route to the leach pads than to the waste dumps.

4

.

Crushing costs are calculated per tonne of mineralized material to leach pad (or mined) assuming 30% of mineralized material is crushed

(crushing unit cost is estimated at $1.74/t of crusher feed material)

5

.

Contingency is applied to OPEX excluding mine contractor rates which are current

Mineral Resources

As part of the PEA an updated Cerro de Oro project Mineral Resource Estimate was completed to

reflect a higher gold price of US$1,700/oz which is more reflective of the three-year trailing average

price.

This reflects a change in the "reasonable prospects for eventual economic extraction" due to the

current market conditions. Other than the change to the gold price assumption, the remainder of the

estimate methodology remain identical to that utilized in the previous NI 43-101 report "Mineral

Resource Estimate for the Cerro de Oro Project" by Scott Zelligan, P.Geo dated November 16th, 2020

that is currently available on SEDAR. The block model was constrained using an economic pit shell at

the updated gold price resulting in the new and current Mineral Resource estimate as presented in Table

4.

Table 4 - Cerro de Oro Project, Estimate of Mineral Resources

Resource

Category

Material Type

Tonnes

(t)

Au

(g/t)

Au

(oz)

Inferred

Oxide

67,000,000

0.37

790,000

Notes:

The independent and QP for the mineral resource estimates, as defined by NI 43-101, is Scott Zelligan, P.Geo. The effective date of the 2022

mineral resource estimate is September 28, 2022.

A gold price of $1,700/oz was used in calculating the Mineral Resources.

The estimate is reported for a potential open pit/heap leach scenario.

The limits of the Resource-constraining pit shell assumed a mining cut-off based on a total operating cost (mining, milling, and general and

administrative [G&A]) of $8.80/t stacked, a metallurgical recovery of 70%, and a constant open pit slope angle of 45°. Inferred resources are

too speculative geologically to have economic considerations applied to them.

The gold cut-off grade applied to oxide mineralized material is 0.15 g/t Au

These Mineral Resources are not Mineral Reserves as they do not have demonstrated economic viability.

The Mineral Resource estimate follows CIM Definition Standards.

Results are presented in-situ. Ounce (troy) = metric tonnes x grade / 31.103. Calculations used metric units (metres, tonnes, g/t). Rounding

followed the recommendations as per NI 43-101.

The number of tonnes has been rounded to the nearest million.

The QPs of this Report are not aware of any known environmental, permitting, legal, title-related, taxation, socio-political, marketing, or other

relevant issues that could materially affect the Mineral Resource estimate other than those disclosed in this NI 43-101 compliant Technical

Report.

The Mineral Resource estimate has been wholly classified as Inferred.

The estimate represents the

oxidized portion of the Cerro de Oro deposit. Although drill spacing is locally sufficient for Indicated

classification, there remain necessary revisions and updates to the geological logs; better definition of

the limit between the oxides and fresh rock; understanding of mineralization controls; and bulk density

measurements. The reported inferred resources are estimated with an average drilling grid of

approximately 85m by 85m.

Table 5 shows the open pit constrained Mineral Resource sensitivity to the gold price.

The reader should

be cautioned that the figures provided in Table 5 should not be interpreted as a Mineral Resource

statement. The reported quantities and grade estimates at different gold prices are presented for the

sole purpose of demonstrating the sensitivity of the resource model to the selection of a reporting gold

price. The gold price of $1,700/oz that was used to report the Mineral Resources (the base case) for

Cerro de Oro is highlighted in bold. Mineral Resources that are not Mineral Reserves do not have

demonstrated economic viability.

Table 5 - Sensitivity of Mineral Resource to Gold Price

Gold Price

($/oz)

Category

Tonnes

(Mt)

Gold Grade

(g/t)

Contained

Ounces

('000s)

1,500

Inferred

54

0.40

690

1,600

Inferred

60

0.38

740

1,700

Inferred

67

0.37

790

1,800

Inferred

73

0.36

833

1,900

Inferred

78

0.35

865

Note:

Mineral Resource is shown in bold.

Mining

The Cerro de Oro Project is planned as a conventional open pit operation that will utilize 100-t haul

trucks and front-end loaders.

Material will be drilled and blasted, before being loaded and hauled to a

waste dump, crusher, or direct to the heap leach pad.

Mining activities will be completed by a contractor

who will supply all of the required mine equipment and personnel working under the supervision of the

Company's technical staff.

Using a nested pit shell that is based on a gold price of $1,500/oz and the economic parameters applied

to the resource estimate as a guide, a full open pit mine plan was completed.

Upon completion of the

ultimate pit designs a check was completed that considered both revisions to the Company's gold price

forecast and its operating cost estimates for the Project.

A LOM gold price of $1600/oz was selected for

use in the final mine planning economics.

Based on available metallurgical data for the project and an

evaluation of the host rock lithologies it was assumed that the majority of mineralization mined will be

placed directly on the heap leach as run-of-mine ("ROM") with approximately 30% of the mineralization

reporting to the crusher for size reduction (equivalent to crushing cut-off grade of approximately 0.40-

0.45 g/t Au).

The mine production schedule anticipates that mining starts at the beginning of year 1 following the

completion of all required earthworks activities such as road, dump and starter leach pad construction.

Due to the low LOM strip ratio (0.30:1) and the size of the mineralization the PEA did not adjust the

planned mining physicals to account for mining losses or dilution (magnitude of losses likely similar to

dilution).

Mine planning efforts going forward will be aimed at cut-off grades and the smoothing of the

mining activities later in the mine life that may provide additional economic upside for the project.

Over

the life of mine of 8.2 years a total of 59Mt of mineralization grading 0.37 g/t gold (~700koz of contained

gold) are anticipated to be mined.

Table 6 - Cerro de Oro Mine Production Schedule

Year

Total

Processed

(tonnes)

Processed

Head

Grade

Au (g/t)

Contained

Gold

(ounces)

Total Mined

Material

(tonnes)

Strip Ratio

(Waste t: Mineral

t)

1

6,540,000

0.44

93,400

7,230,000

0.11

2

6,650,000

0.41

87,300

8,500,000

0.28

3

7,500,000

0.41

99,000

10,000,000

0.33

4

7,510,000

0.42

100,800

10,730,000

0.43

5

7,200,000

0.32

73,800

10,500,000

0.46

6

7,740,000

0.37

91,300

10,520,000

0.36

7

7,500,000

0.32

76,900

10,740,000

0.43

8

7,500,000

0.27

65,000

7,800,000

0.04

9

1,160,000

0.36

13,400

1,160,000

-

59,300,000

0.37

700,900

77,180,000

0.30

Notes:

1

.

Processed totals include mineralization sent direct to the leach pad (41.5 million tonnes) and material sent to the crusher before stacking on

the heap leach pad (17.8 million tonnes).

2

.

Total mined material values include all production from the open pit mine (mineralization + waste) for noted intervals.

Pit bench heights were selected at 5m intervals in order to provide good ore/waste selectivity although

use of larger bench heights in zones of primarily waste and on final open pit walls should be considered

as part of future optimization studies.

Overall average pit slopes with the benches/ramps in place range

between approximately 30-43 degrees in the north pit and 34 - 38 degrees in the south pit.

It is assumed that all drilling/blasting/loading/hauling operations at the Project are planned to be

completed via an open pit mining contractor.

Mining costs were developed for the project utilizing recent

Mexican cost information for similar heap leach operations and as part of the Company's recent work at

its Santana mine.

Contractor availability in northern Mexico is currently high and rates are competitive.

An additional cost was applied to the mineralized material to account on average for longer hauls to the

heap leach pads over the mine life.

Mine planning and supervision activities will be performed by

Company personnel and these costs are excluded from contractor rates.

Processing

The process flowsheet for the Cerro de Oro project is similar to that utilized by the Company at their

recently constructed Santana gold heap leach project.

Metallurgical testwork completed to date on

samples from the Cerro de Oro deposit indicate that the gold mineralization is well disseminated

throughout the host rock and that the oxide mineralization responds positively to cyanidation.

Residual

gold contents following leaching in multiple series of bottle roll tests (conventional and coarse particle)

appear to trend towards a typical range of ultimate values near 0.10 g/t Au.

Leach kinetics were

generally rapid in nature with low to moderate reagent consumptions (lime and cyanide).

A limited

number of column tests have been completed resulting in leach extractions consistent with those

observed from bottle roll studies.

Additional studies have been recommended to better define leaching

parameters and any variability that may exist between the different mineralized zones and lithologies.

The process design for the Cerro de Oro gold project includes crushing of high grade material to less

than 3/4-7/8" (30-35% of total with remaining low grade sent to leach pad as run-of-mine), a heap

leaching pad, solution ponds and carbon column recovery of gold from pregnant leach solutions. The

current design excludes carbon desorption and gold refining facilities as gold-loaded carbon will be

shipped off-site for final dore production.

The overall plant design was based on a nominal rate of

7,000,000 tonnes per year of mineralized material stacked to the leach pad at an average grade of 0.4

g/t Au.

Sufficient excess capacity is included in the design to allow for expected annual variations in mine

production around these nominal values.

Base case leach solution flow rate to the carbon column

recovery area was set at 800 m

3

/h with allowances to expand to 1,200 m

3

/h to accommodate increases

in annual production rates and/or an expansion in the overall project resources.

The overall Cerro de Oro gold recovery facilities consist of the following unit operations and support

facilities:

Low grade run-of-mine material leach pad loading via direct truck dump

Two stage crushing (jaw and cone) and screening operations for higher grade mine material with

conveyor/stacker transport to leach pad

Lined heap leach pad area sufficient to handle current life-of-mine resource (40-50% constructed

initially as Phase 1 with subsequent expansions)

Lined leach solution ponds adjacent to the leach pad - barren, pregnant and emergency overflow

solution capacity

Four trains of 4 stage carbon in columns with area to expand to six trains

All required process pumping and loaded and barren carbon handling

Reagent preparation and storage facilities

Metallurgical laboratory (necessary production samples only)

Utilities including water supply system (surface wells) and diesel power generation

Infrastructure

Access

The Cerro de Oro Project is accessible by road from the city of Saltillo in neighbouring Coahuila State, a

driving distance of approximately 165 km, about a two-hour drive.

The exit to Melchor Ocampo is off

Federal Highway 54 approximately 5 km northeast of the town of Concepción del Oro.

The site access

road is approximately 2.5 km east of Melchor Ocampo, and itself is a 3 km gravel road that provides

access to the Project site.

All roads to the town are paved and in good condition.

Based on preliminary engineering a total of approximately 11km of new access roads are required for

initial site development and early mine production.

Roads will consist of gravel surface suitable for the

operation of mining trucks and general purpose vehicles.

An allowance has also been included for some

upgrading of existing roads including the widening of sections that pass through/near the project mining

operations in order to better accommodate two-way truck traffic

Power

Details of the complete modifications to the existing crushing system previously purchased by the

company have not yet been completed but the arrangement will include a truck dump hopper/feeder, two

stage crushing and screening as well as required transfer conveyors and area sufficient for short term

material stockpiles.

It is planned that "grasshopper" style conveyors will be utilized to transfer crushed

rock to a mobile stacker located at the leach pad for final stacking/placement.

In total an allowance has

been included for a connected load of approximately 1.5 MW to power all the major crusher and transfer

equipment unit operations.

An existing 2MW backup diesel generator was acquired as part of the overall

used crushing circuit equipment and will be installed as a backup.

The nearest federal electricity ("CFE") connection to the planned crushing area is a local line

approximately 0.5 km to the east.

The main line supplying the town of Melchor Ocampo runs along the

primary access road to the town approximately 2 km to the south.

The company is currently discussing

the project requirements with the CFE to confirm sufficient capacity exists within the local network and to

confirm acceptable locations for connection to the power grid.

It is assumed for the foreseeable future that all power required for the Cerro de Oro gold leaching and

recovery plant operations will be generated at site via diesel generators. The total maximum operating

plant power load is estimated at 780 kW (actual draw will vary over LOM and as leach pad evolves)

which will be supplied via a single diesel generator unit (1 MW).

A backup generator (300-400 kW) will

also be installed to manage basic requirements during maintenance periods or periods of reduced

solution pumping.

Generators are to be located within close proximity to the processing plant area, so

transmission line requirements will be negligible. Wherever possible, smaller power consumers not

associated with the processing plant (i.e., test wells, local offices) will be self-contained with local diesel

hydraulic/electric generation.

At current fuel prices in Mexico diesel generation is equivalent to an electric power cost in the range of

$0.30/kWh, which has been used for budgeting purposes in the PEA.

Should the project resources

continue to grow further studies would be warranted to investigate the economics of extending grid

power to the process plan area.

Water Management

The sources of process water available for the Cerro de Oro project consist of groundwater wells.

In mid

2022, a hydrogeological consulting group was retained by the Company to perform reviews of the Cerro

de Oro area and to better understand the regional water flows around Melchor Ocampo.

A series of

reconnaissance visits were completed to review available regional geology maps for the area and to

make local field investigations (including electromagnetic geophysical surveys -- TEM).

Seven (7) high

priority targets have been selected by the company for test drilling down to a maximum depth of 300

meters.

The majority of the target areas are located north of the planned leach pad/processing plant

facilities and at a distance of less than 5km.

Other Infrastructure

Preliminary estimates were completed to calculate the total amount of material to be excavated during

the overall site preparations.

Of this total approximately 40% will be moved short distances and utilized

as compacted fill.

The remainder will be moved to one of the site waste storage dumps.