Lundin Mining Provides Operational Outlook & Update

Mine Development & Operations

NEWS RELEASE 

Lundin Mining Provides Operational Outlook & Update 

Toronto, November 29, 2017 (TSX: LUN; OMX: LUMI) Lundin Mining Corporation (“Lundin Mining” or 

the  “Company”)  provides  the  following  production  guidance  for  the  three‐year  period  beginning  in 

2018, cash costs, capital and exploration expenditure guidance for 2018, as well as ten‐year guidance 

for our Candelaria operation.  Key highlights are as follows: 

 The Company will make significant investments in both the mine and mill at Candelaria to increase 

the copper production profile over the life‐of‐mine. A particular focus is on improvements in years 

2021  and  beyond.  Forecasts  for  2018  and  2019  have  been  lowered  from  the  previous  outlook 

under  the  new  re‐phased  open  pit  life‐of‐mine  plan  and  to  address  localized  pit  wall  instability, 

reflecting the short‐term impact on production from a recent slide.  

 Zinc production guidance has increased for 2019 incorporating the Zinc Expansion Project (ZEP) at 

Neves‐Corvo, though lowered for 2018. Total zinc production is on‐track to increase in 2020 by a 

forecast 60% over 2018 levels with the ZEP to be contributing at full production rates.       

 Nickel  production  forecasts  remain  in  line  with  previous  guidance.  Final  approval  of  permit 

amendments to develop and mine Eagle East were received November 20, 2017. 

 Eagle and Zinkgruvan are to remain first‐quartile producers, and Candelaria and Neves‐Corvo well 

positioned on global cash operating cost curves in 2018. 

Paul Conibear, President and CEO commented, “We are significantly expanding investment in our own 

assets  including  a  number  of  low‐risk,  positive  return  initiatives,  further  positioning  all  of  our 

operations for sustained reliability of production and lower operating costs, taking a long‐term view.  

“The life‐of‐mine copper production profile of Candelaria has once again been improved as we reinvest 

in the mine fleet, advance a mill optimization project, and expand underground production.  

“The  Zinc  Expansion  Project  at  Neves‐Corvo  and  development  of  Eagle  East  remain  on  budget  and 

schedule with first production from both growth projects anticipated in the second half of 2019, and 

early 2020, respectively.” 

Corporate Office 

150 King Street West, Suite 1500 

P.O. Box 38 

Toronto, ON M5H 1J9 

Phone: +1 416 342 5560 

Fax:     +1 416 348 0303 

Attributable Production Outlook (tonnes of metal) 2018 ‐ 20201 

 Candelaria:  The  copper  production  profile  for  Candelaria  has  been  improved  over  the  life‐of‐

mine and  next ten years. Re‐phasing of the open pit mine  plan, increased planned production 

from underground mines, mine fleet reinvestment and initiatives to increase mill capacity have 

all  contributed  to  the  improved  production  profile.  An  updated  NI  43‐101  Technical  Report  is 

being  completed  and  expected  to  be  released  before  the  end  of  2017.  Ten‐year  guidance  for 

Candelaria is provided in Appendix A. 

The latest open pit plan considers new phase designs, production sequences and a change in pit 

ore excavation and truck loading methodology. It also addresses recent instability in a localized 

area  of  the  pit’s  east  wall  and  a  slide  which  occurred  October  31,  2017.  Both  have  impacted 

2018  and  2019  production  forecasts.  Production  guidance  for  2017  remains  unchanged. 

Candelaria attributable copper production guidance of 104,000 to 109,000 tonnes in 2018 is less 

(20%) than the previous outlook for the year. As a result of the recent slide and to take a more 

conservative approach in mining this area of the pit, the near‐term plans have been altered to 

focus  on  waste  push  backs  above  the  area  prior  to  mining  where  the  slide  occurred.  In  the 

meantime, low grade stockpile ore will make up the difference in mill feed.  

Forecast copper production over the next ten years has increased in aggregate by approximately 

290,000 tonnes (20%) with particular focus on improvements in years 2021 and beyond.  

 Eagle:  Consistent  with  original  expectations,  year‐over‐year  production  levels  of  nickel  and 

copper  are  expected  to  gradually  decline  as  the  highest‐grade  ore  is  mined  earlier  in  the  plan 

and  prior  to  production  commencing  from  the  Eagle  East  ore  body.  Forecast  2018  copper 

production from Eagle has increased modestly to 15,000 to 18,000 tonnes with forecast nickel 

production  remaining  consistent  with  our  prior  outlook,  while  forecast  2019  levels  have 

decreased modestly.  

Final  approval  of  permit  amendments  to  develop  and  mine  Eagle  East  was  granted  by  the 

Michigan  Department  of  Environmental  Quality  (MDEQ)  on  November  20,  2017.  Permit 

1 

Production Guidance is based on certain estimates and assumptions, including but not limited to; mineral resources and mineral reserves, geological 

formations, grade and continuity of deposits and metallurgical characteristics.   

Copper

Candelaria (80%) 104,000 ‐ 109,000 116,000 ‐ 121,000 132,000 ‐ 137,000

Eagle 15,000 ‐ 18,000 12,000 ‐ 15,000 12,000 ‐ 15,000

Neves‐Corvo 39,000 ‐ 44,000 40,000 ‐ 45,000 41,000 ‐ 46,000

Zinkgruvan 1,000 ‐ 2,000 1,000 ‐ 2,000 2,000 ‐ 3,000

Total Attributable Copper 159,000 ‐ 173,000 169,000 ‐ 183,000 187,000 ‐ 201,000

Zinc

Neves‐Corvo 68,000 ‐ 73,000 88,000 ‐ 93,000 155,000 ‐ 160,000

Zinkgruvan 76,000 ‐ 81,000 78,000 ‐ 83,000 79,000 ‐ 84,000

Total Zinc 144,000 ‐ 154,000 166,000 ‐ 176,000 234,000 ‐ 244,000

Nickel

Eagle 14,000 ‐ 17,000 10,000 ‐ 13,000 13,000 ‐ 16,000

Total Nickel 14,000 ‐ 17,000 10,000 ‐ 13,000 13,000 ‐ 16,000

2018 2019 2020

amendment  requests  for  processing  of  Eagle  East  ore  at  our  Humboldt  plant  continue  to 

progress and are anticipated by mid‐2018.  Full production from Eagle East in 2020 is reflected in 

our three‐year production outlook.   

 Neves‐Corvo:   Forecast zinc and copper production guidance now incorporate the ZEP which is 

expected  to  approximately  double  zinc  production  from  current  levels.  First  production  from 

ZEP  remains  on  schedule  for  the  second  half  of  2019.  Forecast  zinc  and  copper  production 

guidance  for  2018  are  modestly  less  than  (3%  and  6%,  respectively)  the  previous  outlook 

provided  on  November  30,  2016,  as  average  mill  feed  grades  and  recoveries  have  been 

reassessed.  Zinc  production  is  expected  to  increase  significantly  in  2019  and  ramp  up  to  full 

tonnage  in  2020.  Both  copper  and  zinc  production  are  forecast  to  benefit  from  metallurgical 

improvements  in  the  process  plants  undertaken  as  part  of  the  ZEP  and  result  in  better  metal 

recoveries. 

 Zinkgruvan:   The  1350  Zinc  Expansion  Project  was  commissioned  on  schedule  and  budget  in 

mid‐2017 increasing mill capacity to approximately 1.35 million tonnes per annum (1.17 million 

tonnes  of  zinc‐lead  ore  and  0.18  million  tonnes  of  copper  ore).  Average  zinc  and  lead  mill 

recoveries  have  been  reassessed  in  this  production  outlook.  Significant  focus  is  being  given  to 

improvement  projects  in  the  process  plant  including  initiatives  to  improve  ore  feed 

characteristics,  throughput,  metal  recoveries  and  overall  concentrate  quality.  Prioritization 

remains  on  the  processing  of  zinc‐lead  ores.  An  updated  NI  43‐101  Technical  Report  is  being 

completed and expected to be released before the end of 2017.   

2018 Cash Cost Guidance2 

  At  Candelaria,  estimated  C1  cash  costs  are  expected  to 

approximate  $1.70/lb3  copper  after  by‐product  credits.  By‐

product  credits  have  been  adjusted  for  the  terms  of  the 

streaming agreement but exclude any allocation of upfront cash 

received.  

 Eagle’s  estimated  C1  cash  costs  are  expected  to  approximate 

$1.35/lb nickel after by‐product credits, primarily copper as well 

as  cobalt  and  precious  metals.  Eagle  cash  costs  are  to  remain 

well  positioned  in  the  lowest  quartile  of  the  global  nickel 

producer cost curve. 

 At  Neves‐Corvo,  estimated  C1  cash  costs  for  2018  are  expected 

to  approximate  $1.30/lb  copper  after  zinc  and  lead  by‐product 

credits.   

 Zinkgruvan’s  estimated  C1  cash  costs  are  expected  to 

approximate  $0.45/lb  zinc  after  copper  and  lead  by‐product 

2

 C1 cash costs are based on various assumptions and estimates, including, but not limited to; production volumes, as noted above, commodity 

prices (2018 ‐ Cu: $2.75/lb, Zn: $1.30/lb, Pb: $1.00/lb, Ni: $5.00/lb) foreign currency exchange rates (2018 ‐ €/USD:1.20, USD/SEK:8.00, 

CLP/USD:625) and operating costs. All figures in are in US$ unless otherwise noted. 

3

 68% of Candelaria’s total gold and silver production are subject to a streaming agreement and as such C1 cash costs are calculated based on 

receipt of $404/oz and $4/oz, respectively, on gold and silver sales in the year. No consideration has been made for the upfront payment 

received in the calculation of C1 cash costs.  

C1 Cash Cost2 2018

Copper

Candelaria (80%) $1.70/lb3

Neves‐Corvo $1.30/lb

Zinc

Zinkgruvan $0.45/lb

Nickel

Eagle $1.35/lb

credits.  Zinkgruvan  is  expected  to  remain  a  low  cost  zinc 

producer for the foreseeable future. 

2018 Capital Expenditure Guidance 

 Capital expenditures in 2018 for mines operated by the Company are expected to be approximately 

$850 million on a 100% basis, which includes: 

4 

 Candelaria:  At  Candelaria  capital  expenditures  are  expected  to  total  $510  million  in  2018.  The 

Company will invest in several low‐risk positive return initiatives focussed on improving the life‐of‐

mine production profile and increasing the value of the operation.    

Capitalized  stripping  expenditures  are  estimated  to  be  $200  million  in  2018  under  the  new  mine 

plan as more waste material is moved to ensure production requirements and flexibility for future 

years.  Short  term  use  of  a  mining  contractor  is  planned  to  accelerate  stripping  rates,  supporting 

both the short‐term mine plan changes and the new improved life of mine production plan. 

The  Los  Diques  Tailings  Project  remains  on  budget  and  on  schedule  for  tailings  deposition  in  the 

first  quarter  of  2018.  Estimated  costs  to  complete  remain  unchanged  at  $295  million  with  $45 

million  to  be  spent  in  2018,  from  $30  million  previously  disclosed  due  to  timing  of  payments,  to 

complete  the  construction  of  the  first  phase  of  the  main  embankment.  Future  lifts  of  the 

embankment  have  been  initiated  ahead  of  schedule  to  benefit  from  synergies  with  the  current 

project and readily available mine waste. An additional $15 million of capital is forecast in 2018 to 

construct  two  additional  lifts,  bringing  the  forecast  total  capital  expenditures  on  the  facility  to 

$60 million for the year. 

New Mine Fleet Investment is estimated to be $75 million in 2018. Ongoing exploration efforts have 

significantly increased Candelaria Mineral Reserves and extended mine life well beyond the original 

20‐year  life  when  the  open  pit  began  production  in  1994.  Mine  equipment  has  been  rebuilt  and 

4

 Forecast capital expenditures have been reported on a cash basis. Discrepancies may exist with other external reports which have been 

reported on an accrual basis, most notably for the Los Diques Tailings Project in 2018. 

Capital Expenditures ($ millions)4 2018

Candelaria (100% basis):

Capitalized Stripping 200

Los Diques Tailings 60

New Mine Fleet Investment 75

Mill Optimization Investment 50

Candelaria Sur Development 20

Other Sustaining  105

Candelaria Sustaining 510

Eagle Sustaining 25

Neves‐Corvo Sustaining 55

Zinkgruvan Sustaining 40

Total Sustaining Capital 630

Eagle East 30

Zinc Expansion (Neves‐Corvo)  190

Total Expansionary Capital 220

Total Capital Expenditures 850

maintained in line with industry standards, however reinvestment in a latest generation loading and 

haulage fleet is expected to generate a positive payback gained through increased ore loading and 

haulage capacity and efficiency, while improving equipment availability and reliability. Management 

believes upside potential exists, for additional productivity gains which have not yet been reflected 

in the open pit plan.  

Mill  Optimization  Investment  studies  have  identified  several  low‐risk  improvements  to  increase 

metal  production,  reduce  maintenance  costs  and  improve  safety.  Mill  Optimization  Investment 

capital expenditures are expected to be $50 million in 2018. Upgrades are planned for the primary 

crusher,  cyclones,  ball  mills,  pebble  crushing  and  flotation  circuits.  In  addition,  desalination  plant 

debottlenecking and pipeline improvements will increase fresh water supply. These investments are 

forecast  to  take  approximately  two  years  to  come  on  line  and  are  expected  to  increase  mill 

throughput  by  approximately  4,000  tonnes  per  day  and  improve  metal  recovery  rates  for  an 

approximate  increase  of  more  than  6,000  tonnes  of  copper  per  year.  The  Mill  Optimization 

Investment  presents near‐term low‐risk initiatives that would also provide benefit  under potential 

future expansions.    

Increased  production  from  Candelaria  underground  mines  also  contribute  meaningfully  to  the 

improved  forecast  production  profile.  In  the  third  quarter  of  2017  the  Company  received  an 

environmental  permit  to  expand  production  from  the  Candelaria  underground  deposits  to  14,000 

tonnes  per  day  from  6,000.  Production  ramp‐up  from  Candelaria  underground  North  sector  has 

begun with levels currently in the range of 8,000 tonnes per day and 10,000 tonnes per day targeted 

by  2019.  Development  of  Candelaria  underground  South  sector  (Susana‐Damiana  deposits)  has 

been brought forward and is expected to contribute to production in the second half of 2019 at a 

mining rate of 4,000 tonnes per day. The total pre‐production capital is $47 million, $20 million of 

which will be spent in 2018.        

The  Other  Sustaining  Capital  noted  in  Appendix  A  includes  funds  for  horizontal  and  vertical 

development,  ventilation,  self‐perform  mining  equipment  purchase  and  supporting  infrastructure 

being invested to expand the Candelaria, Alcaparrosa and Santos underground mine production.  

 Eagle: Capital expenditures at Eagle are estimated to total $55 million in 2018, of which $30 million 

is development of Eagle East. The Eagle East project remains on schedule and on budget. Recently 

approved  permit  amendments  from  the  MDEQ  have  authorized  complete  ramp  development  as 

well as mine development and mining of the orebody.  

 Neves‐Corvo: At Neves‐Corvo capital costs are expected to total $245 million in 2018, $190 million 

of  which  is  expansionary  capital  expenditure  on  the  ZEP.  The  project  remains  on  budget  and  on 

target  to  commence  production  ramp  up  in  the  second  half  of  2019.  Review  by  authorities  of  the 

ZEP project engineering and construction permit (RECAPE) package is in progress and construction 

of  the  process  plant  expansion  and  surface  infrastructure  is  expected  to  commence  in  the  first 

quarter of 2018 once RECAPE approvals are in hand.  

 Zinkgruvan: At Zinkgruvan sustaining capital expenditures are estimated to total $40 million in 2018.  

Approximately half is for underground development and half for mine and plant maintenance and 

improvement initiatives. 

2018 Exploration Investment Guidance 

Exploration expenditures are planned to be $83 million in 2018. This is a 12% increase over estimated 

2017  expenditures  reflecting  a  results‐driven  commitment  to  aggressive  exploration  programs. 

Approximately  $70  million  will  be  spent  on  in‐mine  and  near‐mine  targets  ($34  million  at  Candelaria, 

$18  million  at  Eagle,  $13  million  at  Zinkgruvan  and  $5 million  at  Neves‐Corvo),  with  the  remainder  to 

advance exploration activities for new South American and Eastern European exploration projects. 

About Lundin Mining 

Lundin Mining is a diversified Canadian base metals mining company with operations in Chile, the United 

States of America, Portugal, and Sweden, primarily producing copper, nickel and zinc. In addition, Lundin 

Mining holds an indirect 24% equity stake in the Freeport Cobalt Oy business, which includes a cobalt 

refinery located in Kokkola, Finland.  

This is information that Lundin Mining Corporation is obliged to make public pursuant to the EU Market 

Abuse Regulation. The information was submitted for publication, through the agency of the contact 

persons set out below on November 29, 2017 at 5:00 p.m. Eastern Time. 

For further  information,  please contact:  

Mark Turner, Director,  Business  Valuations  and Investor  Relations:   +1‐416‐342‐5565 

Sonia Tercas, Senior Associate,  Investor  Relations:   +1‐416‐342‐5583 

Robert Eriksson,  Investor  Relations  Sweden:   +46 8 545 015 50 

Cautionary Statement in Forward‐Looking Information  

Certain  of  the  statements  made  and  information  contained  herein  or  incorporated  by  reference  is  “forward‐

looking  information”  within  the  meaning  of  applicable  Canadian  securities  laws.  All  statements  other  than 

statements  of  historical  facts  in  this  news  release  constitute  forward‐looking  information  based  on  current 

expectations,  estimates,  forecasts  and  projections  as  well  as  beliefs  and  assumptions  made  by  the  Company’s 

management.  Such  forward‐looking  statements  include  but  are  not  limited  to  those  regarding  the  Company’s 

outlook  and  guidance  on  estimated  metal  production  and  production  profile,  costs,  and  exploration  and  capital 

expenditures;  the  Zinc  Expansion  Project  at  Neves‐Corvo  and  the  Eagle  East  project  ;  Mineral  Reserves,  Mineral 

Resources,  life‐of‐mine  (or  mine  life);  all  of  which  are  estimates  (and  the  parameters,  expectations  and 

assumptions underlying, and realization of, such estimates including, but not limited to metal price assumptions, 

and permitting and development expectations. Words such “aim”, “anticipate”, “assumption”, “believe”, “budget”, 

“commitment”, “estimate, “expansionary”, “expect”, “exploration”, “flexibility”, “focus”, “forecast”, “foreseeable”, 

“forward”,  “future”,  “growth”,  “guidance”,  “initiative”,  “on‐track”,  “outlook”,  “plan”,  “positioning”,  “potential”, 

“priority”, “profile”, “project”, “ramp‐up”, “risk”, “schedule”, “study”, “target” or “view” , or variations of or similar 

such terms, or statements that certain actions, events or results could, may, might or will be taken or occur or be 

achieved,, or variations of these terms or similar terminology or statements that certain actions, events or results 

could  ,  may,  might  or  will  be  taken  or  occur  or  be  achieved  are  intended  to  identify  such  forward‐looking 

information.  These  estimates,  expectations  and  other  forward‐looking  statements  are  based  on  a  number  of 

assumptions and are subject to a variety of risks and uncertainties which could cause actual events or results to 

differ  materially  from  those  reflected  in  the  forward‐looking  statements.  Such  risks  and  uncertainties  include, 

without  limitation,  risks  and  uncertainties  inherent  in  and/or  relating  to:  estimates  of  future  production  and 

operations, cash and all‐in sustaining costs; metal and commodity price fluctuations; foreign currency fluctuations; 

mining  operations  including  but  not  limited  to  environmental  hazards,  industrial  accidents,  ground  control 

problems  and  flooding;  geology  including,  but  not  limited  to,  unusual  or  unexpected  geological  formations, 

estimation  and  modelling  of  grade,  tonnes,  metallurgy  continuity  of  mineral  deposits,  dilution,  and  Mineral 

Resources and Mineral Reserves, and actual ore mined and/or metal recoveries varying from such estimates; mine 

plans, and life of mine estimates; the possibility that future exploration, development or mining results will not be 

consistent with expectations; the expected strike by union workers (and potential further such strikes) at Neves‐

Corvo, and the potential for and effects of other labour disputes or shortages, or other unanticipated difficulties 

with or interruptions in production; potential for unexpected costs and expenses including, without limitation, for 

mine closure and reclamation at current and historical operations; uncertain political and economic environments; 

changes  in  laws  or  policies,  foreign  taxation,  delays  or  the  inability  to  obtain  necessary  governmental  approvals 

and/or  permits,  including  but  not  limited  to  the  Alcaparrosa  underground  mine  operating  license,  the  Punta 

Padrones  process  operating  license  and  the  Ojos  del  Salado  mill  tailings  line  permit  at  Candelaria  which  are 

required  by  the  end  of  the  year;  regulatory  investigations,  enforcement,  sanctions  and/or  related  or  other 

litigation; and other risks and uncertainties, including but not limited to those described in the “Managing Risks” 

section  of  the  Company’s  Management’s  Discussion  and  Analysis  for  the  financial  period  ending  December  31, 

2016 and completed financial quarters in 2017, and the “Risks and Uncertainties” section of our most recently filed 

Annual  Information  Form.  In  addition,  forward‐looking  information  is  based  on  various  assumptions  including, 

without limitation, the expectations and beliefs of management; assumed prices of copper, nickel, zinc and other 

metals; that the Company can access financing, appropriate equipment and sufficient labour; and that the political 

environment  where  the  Company  operates  will  continue  to  support  the  development  and  operation  of  mining 

projects. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove 

incorrect,  actual  results  may  vary  materially  from  those  described  in  forward‐looking  statements.  Accordingly, 

there  can  be  no  assurance  that  forward‐looking  information  will  prove  to  be  accurate,  and  readers  should  not 

place undue reliance on forward‐looking statements. The Company disclaims any intention or obligation to update 

or revise forward‐looking statements or to explain any material difference between such and subsequent actual 

events, except as required by applicable law.