Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LUN.TO ·

Lundin Mining First Quarter Results

Financials

Lundin Mining First Quarter Results

TORONTO, April 25, 2018 -- (TSX:LUN) (Nasdaq Stockholm:LUMI) Lundin Mining Corporation (“Lundin Mining” or the

“Company”) today reported cash flows of $172.9 million generated from operations in its first quarter of the year. Net earnings

from continuing operations attributable to Lundin Mining shareholders were $81.2 million ($0.11 per share) for the quarter.

Mr. Paul Conibear, President and CEO commented, “We are pleased with our performance in the first quarter. Operational

performance was in line with plan, with particularly strong results from Neves-Corvo and Zinkgruvan. We have improved cash

cost guidance at Eagle, and are well positioned to deliver the full year production outlook at each operation.

Excellent progress continues on exploration and multiple projects to further improve the value of our operations. At the Neves-

Corvo Zinc Expansion Project, underground development of the conveyor ramps and crushing station area is more than 50%

complete and surface work has commenced. Eagle East ramp development continues ahead of schedule. At Candelaria,

continuous placement of tailings is underway in the commissioning of Los Diques, ahead of schedule. The Candelaria mill

optimization, underground production expansions, and mine fleet reinvestment initiatives are all advancing well in support of

delivering greater value over the improved life-of-mine plan.”    

    Summary financial results for the quarter:     

          Three months ended

          March 31,

    US$ Millions (except per share amounts)     2018 2017  

    Revenue     470.5  487.8   

    Gross profit     149.9  164.0   

    Attributable net earnings 1     81.3  91.6   

    Net earnings     87.1  106.4   

    Basic and diluted earnings per share2     0.11  0.13   

    Cash flow from operations     172.9  244.7   

    Cash and cash equivalents     1,639.1  928.8   

    Net cash (debt)3     1,183.2  (71.3)  

1 Attributable to shareholders of Lundin Mining Corporation. 

2 Basic and diluted earnings per share attributable to shareholders of Lundin Mining Corporation.

3 Net cash / (debt) is a non-GAAP measure defined as cash and cash equivalents, less long-term debt and finance leases,

before deferred financing fees.

Highlights

Operational Performance

Production and cash costs 1 across all operations and for all metals were in line with expectations for the quarter, on target to

achieve or better the Company’s annual guidance. Lower copper production in the quarter compared to the prior year quarter is

a result of planned lower throughput and grades at Candelaria. Strong operating performance was achieved at both Neves-

Corvo and Zinkgruvan. Significant progress was made on projects at Candelaria, Eagle and Neves-Corvo.

Candelaria (80% owned): The Candelaria operations produced, on a 100% basis, 31,847 tonnes of copper, and approximately

17,000 ounces of gold and 275,000 ounces of silver in concentrate during the quarter. Copper production largely met

expectations but was lower than the prior year comparable period due to planned mining and processing of lower grade

materials and routine mill maintenance resulting in lower throughput. Copper cash costs of $1.71/lb for the quarter were in line

with full year guidance ($1.70/lb), but higher than the prior year quarter due primarily to lower planned sales volumes, higher

mill maintenance costs and foreign exchange in the current quarter.

The first phase of the Los Diques Tailings Storage Facility (“TSF”) is complete and continuous tailings placement commenced

in April. The facility has satisfied all regulatory requirements and operating permit applications have been submitted.

Construction of subsequent phases has been initiated early, with excellent progress to date.

Eagle (100% owned): Eagle production remains on track to achieve full year guidance producing 5,141 tonnes of nickel and

4,773 tonnes of copper during the quarter. Quantities were lower than the prior year as a result of planned mine sequencing.

Nickel cash costs of $0.49/lb for the quarter benefited from lower nickel treatment and refining charges, bettering both

guidance and the prior year.

Development of the Eagle East access ramp continues ahead of schedule, and underground definition drilling is scheduled to

commence in Eagle East in the second quarter of this year.

Neves-Corvo (100% owned): Neves-Corvo produced 10,760 tonnes of copper and 17,835 tonnes of zinc for the quarter with

excellent mill throughput for both zinc and copper and remains on track to achieve full year guidance. Zinc production was in

line with the prior year comparable period, despite lower head grades, while copper production was higher resulting from

improved mine productivity and higher mill throughput driven by improvements in mine plan execution. Overall cash costs, on a

copper basis, of $1.14/lb for the quarter were higher than the prior year comparable period, negatively impacted by foreign

exchange, but remain better than guidance ($1.30/lb).

The Zinc Expansion Project (“ZEP”) advanced, however some delays have been experienced due to both labour action and

underground contractor progress.

Constructive dialogue with the Neves-Corvo workforce continues. The labour situation continues to be managed so as to

minimize the risk of future work stoppages.

Zinkgruvan (100% owned): Zinc production of 19,045 tonnes for the quarter was in line with both guidance and prior year

comparative period production. Lead production of 7,023 tonnes was lower than the prior year quarter driven by lower head

grades as a result of mine sequencing. Zinc cash costs of $0.43/lb for the quarter were better than full year guidance, but

higher than the prior year comparable quarter due primarily to foreign exchange.

1 Cash cost/lb of copper, zinc and nickel are non-GAAP measures defined as all cash costs directly attributable to mining

operations, less royalties and by-product credits.

Financial Performance

• Revenue for the quarter ended March 31, 2018 was $470.5 million, a decrease of $17.3 million in comparison to the

$487.8 million reported in the first quarter of the prior year. The decrease was due to lower sales volumes ($74.9

million), partially offset by higher metal prices, net of price adjustments ($36.7 million) and lower treatment and refining

charges ($16.5 million).

• Cost of goods sold for the quarter ended March 31, 2018 was $320.6 million, a decrease of $3.2 million in comparison

to the $323.8 million reported in the first quarter of the prior year. Higher per unit production costs ($25.0 million) and

the negative impact of foreign exchange ($16.4 million) were offset by lower sales volumes ($43.1 million).

• Gross profit for the quarter ended March 31, 2018 was $149.9 million, a decrease of $14.1 million in comparison to the

$164.0 million reported in the first quarter of the prior year. The decrease was primarily due to higher per unit production

costs ($25.0 million) and lower sales volumes ($31.5 million), partially offset by higher realized metal prices, net of price

adjustments ($36.7 million).

• Net earnings for the quarter ended March 31, 2018 were $87.1 million, a decrease of $19.3 million over the $106.4

million reported in the first quarter of 2017. Net earnings, in comparison with the prior year quarter, were negatively

impacted by:

   --  lower earnings from discontinued operations ($34.0 million); and

   --  lower gross profit ($14.1 million); partially offset by

   --  lower net income tax expense ($18.6 million).

• Cash flow from operations for the quarter ended March 31, 2018 was $172.9 million, a decrease of $71.8 million in

comparison to the cash flow of $244.7 million reported in the first quarter of 2017. The decrease was primarily

attributable to a comparative change in non-cash working capital.

Financial Position and Financing

• Cash and cash equivalents increased $72.1 million over the quarter ended March 31, 2018, from $1,567.0 million to

$1,639.1 million. The increase is primarily a result of cash generated from operating activities of $172.9 million and

proceeds from the sale of marketable securities of $35.4 million, partially offset by investments in mineral properties,

plant and equipment of $150.7 million.

• Net cash position at March 31, 2018 was $1,183.2 million compared to $1,110.5 million at December 31, 2017.   

• The Company has a revolving credit facility available for borrowing up to $350 million. As at March 31, 2018, the

Company had no amount drawn on the credit facility, only letters of credit in the amount of $26.6 million.

• As at April 25, 2018, cash and net cash balances were approximately $1.7 billion and $1.2 billion, respectively.

Outlook

Production and exploration guidance for 2018 remains unchanged from that provided on November 29, 2017 (see news release

entitled “Lundin Mining Provides Operational Outlook & Update”). Eagle’s 2018 cash cost guidance has been reduced to

$1.10/lb, from $1.35/lb, largely in recognition of higher expected copper by-product prices. 

2018 Production and Cost Guidance

  (contained tonnes in concentrate)   Tonnes   Cash Costsa  

   Copper Candelaria (80%)  104,000 - 109,000  $1.70/lb  

     Eagle  15,000 - 18,000     

     Neves-Corvo  39,000 - 44,000  $1.30/lb  

     Zinkgruvan  1,000 - 2,000     

     Total attributable  159,000 - 173,000     

   Zinc Neves-Corvo  68,000 - 73,000     

     Zinkgruvan  76,000 - 81,000  $0.45/lb  

     Total  144,000 - 154,000     

   Nickel Eagle  14,000 - 17,000  $1.10/lb  

a. Cash costs remain dependent upon exchange rates (forecast at €/USD:1.25, USD/SEK:8.00, USD/CLP:600) and metal

prices (forecast at Cu: $3.00/lb, Zn: $1.40/lb, Ni: $5.50/lb, Au: $1,250/oz, Pb: $1.00/lb, Ag: $18.00/oz).  

2018 Capital Expenditure and Exploration Guidance

Total capital expenditures, excluding capitalized interest, are forecast to be $850 million as previously disclosed. Minor,

offsetting changes in sustaining capital expenditures at Eagle (from $25 million to $20 million) and Neves-Corvo (from $55

million to $60 million) are expected. A comprehensive project cost review for the ZEP will be conducted and updates provided

with the second quarter results.

  2018 Guidance     $ millions  

    Candelaria (100% basis)        

      Capitalized Stripping     200  

      Los Diques TSF     60  

      New Mine Fleet Investment     75  

      Candelaria Mill Optimization Project     50  

      Candelaria Underground Development     20  

      Other Sustaining     105  

    Candelaria Sustaining     510  

    Eagle Sustaining     20  

    Neves-Corvo Sustaining     60  

    Zinkgruvan Sustaining     40  

    Total Sustaining Capital     630  

    Eagle East     30  

    ZEP (Neves-Corvo)     190  

    Total Expansionary Capital     220  

    Total Capital Expenditures     850  

2018 Exploration Investment Guidance

Exploration expenditures are expected to remain unchanged at $83 million in 2018.

This is information that Lundin Mining Corporation is obliged to make public pursuant to the EU Market Abuse Regulation. The

information was submitted for publication, through the agency of the contact persons set out below on April 25, 2018 at 5:00

p.m. Eastern Time.

For further information, please contact:

Mark Turner, Director, Business Valuations and Investor Relations:  +1-416-342-5565

Sonia Tercas, Senior Associate, Investor Relations:  +1-416-342-5583

Robert Eriksson, Investor Relations Sweden:  +46 8 545 015 50

Cautionary Statement in Forward-Looking Information and Non-GAAP performance measures                               

Certain of the statements made and information contained or incorporated by reference herein is "forward-looking information"

within the meaning of applicable Canadian securities laws. All statements other than statements of historical facts in this

document constitute forward-looking information based on current expectations, estimates, forecasts and projections as well

as beliefs and assumptions made by the Company’s management. Such forward-looking statements include but are not

limited to those regarding the Company’s outlook and guidance on metal production, costs and capital expenditures;

exploration; the Zinc Expansion Project (or ZEP) at Neves-Corvo, Eagle East and the Los Diques Tailings Storage Facility

(TSF) at Candelaria; and life-of-mine estimates and plans. Words such as “advancing”, “anticipate”, “assumption”, “believe”,

“estimate”, “expectation”, “exploration”, “further”, “forecast”, “guidance”, “initiative”, “outlook”,  “phase”, “plan”, “potential”,

“progress”, “project”, “schedule”, “target” or “track”, or variations of or similar such terms, or statements that certain actions,

events or results could, may, might or will be taken or occur or be achieved, identify forward-looking information. Although the

Company believes that the expectations reflected in the forward-looking information herein are reasonable, these statements

by their nature involve risks and uncertainties and are not guarantees of future performance. These estimates, expectations

and other forward-looking statements are based on a number of assumptions and are subject to a variety of risks and

uncertainties which could cause actual events or results to differ materially from those reflected in the forward-looking

statements. Such risks and uncertainties include, without limitation, risks and uncertainties inherent in and/or relating to:

estimates of future production and operations, cash and all-in sustaining costs; metal and commodity price fluctuations;

foreign currency fluctuations; mining operations including but not limited to environmental hazards, industrial accidents,

ground control problems and flooding; geology including, but not limited to, unusual or unexpected geological formations and

events (including but not limited to rock slides and falls of ground), estimation and modelling of grade, tonnes, metallurgy

continuity of mineral deposits, dilution, and Mineral Resources and Mineral Reserves, and actual ore mined and/or metal

recoveries varying from such estimates; mine life and life-of-mine plans and estimates; the possibility that future exploration,

development or mining results will not be consistent with expectations; the potential for and effects of labour actions, disputes

or shortages (including but not limited to at Neves-Corvo), community or other civil protests or demonstrations or other

unanticipated difficulties with or interruptions to operations; potential for unexpected costs and expenses including, without

limitation, for mine closure and reclamation at current and historical operations; uncertain political and economic

environments; changes in laws or policies, foreign taxation, delays or the inability to obtain and maintain necessary

governmental approvals and/or permits; regulatory investigations, enforcement, sanctions and/or related or other litigation; and

other risks and uncertainties, including but not limited to those described in the “Managing Risks” section of the Company’s

full-year 2017 and subsequent Management’s Discussion and Analysis, and the “Risks and Uncertainties” section of the

Company’s most recently filed Annual Information Form. In addition, forward-looking information is based on various

assumptions including, without limitation, the expectations and beliefs of management; assumed prices of copper, zinc,

nickel and other metals; that the Company can access financing, appropriate equipment and sufficient labour; and that the

political environment where the Company operates will continue to support the development and operation of mining projects.

Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual

results may vary materially from those described in forward-looking statements. Accordingly, there can be no assurance that

forward-looking information will prove to be accurate, and readers should not place undue reliance on forward-looking

statements. The Company disclaims any intention or obligation to update or revise forward ‐looking statements or to explain

any material difference between such and subsequent actual events, except as required by applicable law.

Certain financial measures contained herein, such as net debt and cash costs, have no meaning within generally accepted

accounting principles under IFRS and therefore amounts presented may not be comparable to similar data presented by other

mining companies. This data is intended to provide additional information and should not be considered in isolation or as a

substitute for measures or performance prepared in accordance with IFRS.