Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LUN.TO ·

Lundin Mining Announces 2022 Production Results & Provides 2023 Guidance

Production Results

Corporate Office

150 King Street West, Suite 2200

P.O. Box 38, Toronto, ON M5H 1J9

Phone: +1 416 342 5560

Fax: +1 416 348 0303

lundinmining.com

NEWS RELEASE

Lundin Mining Announces 2022 Production Results & Provides 2023 Guidance

Toronto, January 12, 2023 (TSX: LUN; Nasdaq Stockholm: LUMI) Lundin Mining Corporation (“Lundin Mining”

or the “Company”) announces production results for the year ended December 31, 2022 and provides production

guidance for the three-year period of 2023 through 2025, as well as cash cost, capital and exploration expenditure

forecasts for 2023. The Company will hold a conference call and webcast on January 13, 2023, to answer investor

and analyst questions.

This news release contains non-GAAP measures and forward-looking information about expected future events and financial

and operating performance of the Company. Please refer to the Historical Non-GAAP Measure Comparatives section and the

risks and assumptions set out in our Cautionary Statement on Forwa rd-Looking Information section of this press release . All

dollar amounts are expressed in U.S. dollars, unless otherwise noted.

2022 Production Highlights

• Guidance was substantially achieved on a consolidated basis for copper, nickel, and gold. Nickel and gold

production achieved the top end of the guidance ranges.

• 2022 consolidated copper production was approximately 250,000 t, and total copper -equivalent

consolidated production was over 390,000 t.1

• Candelaria copper production of 152,042 t was modestly below guidance, while gold production of

86,000 oz achieved the top end of the guidance range.

• Chapada copper production of 45,739 t achieved guidance and gold production of 68,000 oz exceeded

the top end of the guidance range.

• Eagle nickel production of 17,475 t and copper production of 15,895 t both achieved guidance.

Summary of 2022 Production

Q4 2022

Production

Full Year 2022

Production

2022 Production

Guidance2

Copper (t)

Candelaria (100% basis) 34,398 152,042 155,000 - 165,000

Chapada 11,306 45,739 45,000 - 50,000

Eagle 3,081 15,895 15,000 - 18,000

Neves-Corvo 7,160 31,906 33,000 - 38,000

Zinkgruvan 607 4,077 2,000 - 3,000

Total Copper 56,552 249,659 250,000 - 274,000

1 Calculated based on the ratios of 2022 average metal prices of Cu: $3.99/lb, Zn: $1.56/lb, Ni: $11.62/lb, Pb: $0.97/lb and Au: $1,802/oz.

2 Guidance as most recently disclosed in the Company’s Management Discussion and Analysis for the three and six months ended June 30, 2022, with trending

commentary in the Company’s MD&A for the three and nine months ended September 30, 2022.

Q4 2022 Full Year 2022 2022 Production

Production Production Guidance3

Zinc (t)

Neves-Corvo 24,523 82,435 90,000 - 100,000

Zinkgruvan 19,785 76,503 78,000 - 83,000

Total Zinc 44,308 158,938 168,000 - 183,000

Gold (oz)

Candelaria (100% basis) 20,000 86,000 83,000 - 88,000

Chapada 16,000 68,000 62,000 - 67,000

Total Gold 36,000 154,000 145,000 - 155,000

Nickel (t)

Eagle 4,096 17,475 15,000 - 18,000

Total Nickel 4,096 17,475 15,000 - 18,000

Three-Year Production Outlook

• Copper production is forecast to be 236,000-260,000 t on a consolidated basis in 2023. Higher consolidated

copper production of 256,000-280,000 t is forecast for 2024 due mainly to mine sequencing and the planned

copper grade profile at Candelaria.

• Zinc production is forecast to increase to 180,000-195,000 t on a consolidated basis in 202 3, increasing

further over the three-year period to reach 225,000-240,000 t in 2025. The increasing zinc production profile

is primarily due to the ramp up of the Neves-Corvo Zinc Expansion Project ( “ZEP”), which is expected t o

consistently achieve nameplate capacity during 2024.

• Consolidated gold production is forecast to be 1 40,000-150,000 oz in 202 3 and to be relatively constant

through the three-year outlook period.

• Nickel production is to be 13,000-16,000 t in 2023 and to moderate over the three-year period driven by the

planned mine sequencing and nickel grade as the Eagle East and Upper Keel orebodies at Eagle are mined.

Production Outlook4

2023 2024 2025

Copper (t)

Candelaria (100% basis) 145,000 - 155,000 165,000 - 175,000 150,000 - 160,000

Chapada 43,000 - 48,000 43,000 - 48,000 45,000 - 50,000

Eagle 12,000 - 15,000 9,000 - 12,000 5,000 - 8,000

Neves-Corvo 33,000 - 38,000 35,000 - 40,000 35,000 - 40,000

Zinkgruvan 3,000 - 4,000 4,000 - 5,000 3,000 - 4,000

Total Copper 236,000 - 260,000 256,000 - 280,000 238,000 - 262,000

Zinc (t)

Neves-Corvo 100,000 - 110,000 130,000 - 140,000 140,000 - 150,000

Zinkgruvan 80,000 - 85,000 85,000 - 90,000 85,000 - 90,000

Total Zinc 180,000 - 195,000 215,000 - 230,000 225,000 - 240,000

3 Guidance as most recently disclosed in the Company’s Management Discussion and Analysis for the three and six months ended June 30, 2022, with trending

commentary in the Company’s MD&A for the three and nine months ended September 30, 2022.

4 Production guidance is based on certain estimates and assumptions, including but not limited to Mineral Resources and Mineral Reserves, geological formations,

grade and continuity of deposits and metallurgical characteristics.

2023 2024 2025

Gold (oz)

Candelaria (100% basis) 5 85,000 - 90,000 95,000 - 100,000 85,000 - 90,000

Chapada 55,000 - 60,000 55,000 - 60,000 45,000 - 55,000

Total Gold 140,000 - 150,000 150,000 - 160,000 130,000 - 145,000

Nickel (t)

Eagle 13,000 - 16,000 10,000 - 13,000 5,000 - 8,000

Total Nickel 13,000 - 16,000 10,000 - 13,000 5,000 - 8,000

• Candelaria: Annual fluctuations in copper and gold production forecasts for the next three years are mainly

due to sequencing of the Candelaria open pit. Ore mining from the open pit is to be primarily from the upper

benches of Phase 11 in 2023, mining towards lower benches in 2024. Mining of Phase 10 is to complete and

initial ore from Phase 12 is to commence in 2024.

Over the guidance period, total mill throughput is forecast to range between 27 -29 million tonnes per

annum (“Mtpa”). Debottlenecking initiatives of the Candelaria plant pebble crushing circuit are planned to

begin increasing mill capacity starting late 2023. B ased on the planned mill feed blend and the ore

hardness throughput model, annual throughput is expected to approximate 29 Mtpa commencing

in 2025.

Candelaria’s 2023 copper and gold production are forecast to be modestly weighted to the first half of the

year, primarily owing to mine sequencing and the resultant grade profiles.

• Chapada: Production guidance is based on the current throughput capacity of approximately 23.5 Mtpa

over the three-year period with annual fluctuations primarily due to mine sequencing and the forecast

copper and gold grade profiles.

Ore mining is planned from the Chapada South, Southwest, Central and North pits through 2023, followed

by mining of the Baru and Chapada Northeast orebodies commencing in 2024, and the North Buriti

orebody commencing in 2025.

Chapada’s 2023 copper and gold production are forecast to be weighted to the second half of the year

due to the forecast grade profiles and seasonal operating considerations. All of Chapada’s gold production

remains unencumbered and is to receive full market pricing.

• Eagle: Guidance incorporates mining of the Upper Keel zone in production plans, with first ore anticipated

in 2024 following development in 2023. Ore mining is to continue from the Eagle and Eagle East orebodies

in 2023 with priority on increasing ore from Eagle East during the second half of the year. Eagle’s 2023

nickel and copper production are forecast to be modestly weighted to the first half of the year, primarily

owing to mine sequencing and the resultant grade profiles.

• Neves-Corvo: Copper production guidance for the three-year period is consistent with prior expectations.

The zinc production guidance reflects the slower than anticipated ramp-up to date of ZEP. Several projects

are underway to enable ZEP to consistently achieve the nameplate processing capacity of 2.5 Mtpa. These

include mine development, additions to increase mine ventilation capacity, and installation of a redundant

SAG feeder, amongst other initiatives. Full ZEP mining and processing rates are expected to be achieved

during 2024.

Neves-Corvo’s 2023 copper production is forecast to be equally weighted throughout the year . Zinc

production is forecast to increase over the course of the year as initiatives to enable ZEP to consistently

5 68% of Candelaria’s total gold and silver production are subject to a streaming agreement.

achieve nameplate capacity are executed and expected to result in improved overall throughput and

metal recovery rates.

• Zinkgruvan: Zinc production is forecast to increase over the three -year period with refinement of

operating plans. Zinc head grades are expected to increase over the period on mine sequencing, and

metal recovery rates and concentrate grades are anticipated to improve with completion of the sequential

flotation project in mid-2023. Zinkgruvan’s 2023 zinc and copper production are foreca st to be modestly

weighted to the second half of the year, primarily owing to mine sequencing and the resultant grade

profiles.

2023 Cash Cost6 Guidance

• Candelaria: cash cost is forecast to be $1.80/lb – $1.95/lb of

copper, after by-product credits. The cash cost is expected

to benefit from an approximately 50% reduction in

electricity rates as a new Power Purchase Agreement (PPA)

commenced at the beginning of the year. The PPA also

ensures a minimum of 80% renewables in the energy mix,

prioritizing wind and solar . By -product credits have been

adjusted for the terms of the streaming agreement.

• Chapada: cash cost is forecast to be $2.55/lb – $2.75/lb of

copper in 202 3, after unencumbered gold by-product

credits. The forecast increase in Chapada’s cash cost s

compared to 2022 reflects mainly higher consumable costs

and lower production volumes . Effects of copper stream

agreements are reflected in the realized copper revenue.

• Eagle: cash cost is forecast to be $1.50/lb – $1.65/lb of nickel in 2023, after by-product copper credits. The

forecast increase compared to 2022 is primarily a reflection of planned lower production volumes.

• Neves-Corvo: cash cost is forecast to be $2.10/lb – $2.30/lb of copper in 2023, after zinc and lead by-product

credits. The cash cost is expected to continue to improve as zinc and lead production volumes increase.

• Zinkgruvan: cash cost is forecast to be $0.60/lb – $0.65/lb of zinc, after copper and lead by-product credits,

consistent with 2022 levels.

6 This is a non-GAAP measure. For equivalent historical non-GAAP financial measure comparatives see the Historical Non-GAAP Measure Comparatives section of this

press release. Please also see the Management’s Discussion and Analysis for the year ended December 31, 2021, for discussion of non-GAAP measures under the

heading “Non-GAAP and Other Performance Measures” on page 26, which is incorporated by reference herein.

7 2023 cash costs are based on various assumptions and estimates, including, but not limited to: production volumes, commodity prices (2023 - Cu: $3.75/lb, Zn:

$1.30/lb, Pb: $0.90/lb, Au: $1,750/oz: Ag: $22.00/oz) foreign currency exchange rates (2023- €/USD:1.00, USD/SEK:10.50, CLP/USD:850, USD/BRL:5.00) and operating

costs.

8 68% of Candelaria’s total gold and silver production are subject to a streaming agreement and as such cash costs are calculated based on receipt of $425/oz and

$4.25/oz, respectively, on gold and silver sales in the year.

Cash Cost 20237

Copper

Candelaria8 $1.80/lb - $1.95/lb

Chapada $2.55/lb - $2.75/lb

Neves-Corvo $2.10/lb - $2.30/lb

Zinc

Zinkgruvan $0.60/lb - $0.65/lb

Nickel

Eagle $1.50/lb - $1.65/lb

2023 Capital Expenditure Guidance

• Capital expenditures are forecast to total $1,100 million on a 100% basis , including expansionary capital

expenditures9 on the Josemaria Project . The majority of sustaining capital expenditures are for open pit

waste stripping, underground mine development , tailings storage facility (“TSF”) and water ma nagement

works.

Capital Expenditures ($ millions) 202310

Sustaining Capital

Candelaria (100% basis) 400

Chapada 70

Eagle 20

Neves-Corvo 130

Zinkgruvan 70

Other 10

Total Sustaining Capital 700

Josemaria Project 400

Total Capital Expenditures 1,100

• Candelaria: Capital expenditures at Candelaria in 2023 are forecast to total $400 million. Of this, capitalized

waste stripping is forecast to be $185 million, and underground mine development, including ramp works,

to be approximately $ 55 million. Capital expenditure for mobile and mine equipment is forecast to be

$55 million, and $55 million is estimated for the continued building of the Los Diques TSF. Pebble crushing

debottlenecking capital expenditures are forecast to be approximately $8 million in 2023 and completed

during the year.

• Chapada: Capital expenditures at Chapada in 202 3 are forecast to total $ 70 million. This includes

approximately $2 5 million for capitalized waste stripping, $ 15 million for TSF and water management

systems, and $5 million for mine and mobile equipment.

• Eagle: Capital expenditures a t Eagle in 2023 are forecast to total $ 20 million in 202 3, composed of

underground mine development, of which approximately $8 million is for development of the Upper Keel

zone, and for mine and mill sustaining initiatives.

• Neves-Corvo: Capital expenditures at Neves -Corvo in 2023 are estimated to total $ 130 million in 202 3.

Approximately $50 million is forecast for underground mine development, including infill drilling, $60 million

for projects to enable ZEP to consistently achieve nameplate capacity, and $10 million for mine and mobile

equipment. Projects to enable ZEP to consistently achieve its 2.5 Mtpa processing capacity include raise and

chiller additions to increase capacity of the ventilation system , installation of a redundant SAG feeder,

expansion of the TSF, and process water treatment plant works.

• Zinkgruvan: Capital expenditures at Zinkgruvan are forecast to total $ 70 million in 202 3, of which

approximately $35 million is for underground development, including development of the Dalby orebody.

9 Expansionary capital expenditure is a non-GAAP measure. For historical comparatives see the Historical Non-GAAP Measure Comparatives section of this press

release. Please also see the Management’s Discussion and Analysis for the year ended December 31, 2021, for discussion of non-GAAP measures. Capital expenditures

have been reported on a cash basis.

10 Capital expenditures are based on various assumptions and estimates, including, but not limited to foreign currency exchange rates (2023- €/USD:1.00,

USD/SEK:10.50, CLP/USD:850, USD/BRL:5.00).

Expenditure on the sequential flotation project, to improve concentrate grades and metal recovery rates, is

forecast to be $8 million. The remainder of the sustaining capital expenditure is primarily for TSF works,

reduced emissions and energy saving programs and other improvement initiatives.

• Josemaria Project: Capital expenditures are estimated to be approximately $400 million in 2023 in support

of advancing the project prior to a potential construction decision. An updated initial capital cost estimate

and project schedule review are progressing well with the updated Technical Report on-track for publication

in the second half of 2023. Capital expenditures primarily include continuation of detail engine ering,

procurement of long -lead equipment, and preconstruction activities such as road upgrades and

geotechnical work.

2023 Exploration Investment Guidance

Exploration expenditures are planned to be $ 45 million in 2023 primarily for in-mine and near-mine targets at

our operations . The largest portion of the planned expenditure is to be at Candelaria and Chapada with the

remaining operations and new business development activities comprising the balance.

Conference Call

The Company will hold a conference call and webcast at 08:00 am ET, 14:00 CET on Friday, January 13, 2023, to

answer analyst and investor questions. Conference call details are provided below. Please dial-in 15 minutes

prior to the call start to ensure placement into the conference on time.

Call-in number for the conference call (North America): +1 416 764 8658

Call-in number for the conference call (North America Toll Free): +1 888 886 7786

Call-in number for the conference call (Sweden): 020 089 9189

To view the live webcast presentation, please log on using this direct link:

https://viavid.webcasts.com/starthere.jsp?ei=1592975&tp_key=12653d08de.

The presentation slideshow will also be available in PDF format on the Lundin Mining website

www.lundinmining.com before the conference call.

A replay of the telephone conference will be available after the completion of the call through January 13, 2024.

Call-in numbers for the replay are (North America): +1 888 886 7786 or (internationally) +1 416 764 8658.

The passcode for the replay is: 352670

A replay of the webcast will be available by clicking on the direct link above.

About Lundin Mining

Lundin Mining is a diversified Canadian base metals mining company with operations and projects in Argentina,

Brazil, Chile, Portugal, Sweden and the United States of America, primarily producing copper, zinc, gold and nickel.

The information in this release is subject to the disclosure requirements of Lundin Mining under the EU Market

Abuse Regulation. The information was submitted for publication, through the agency of the contact persons set

out below on January 12, 2023 at 18:00 Eastern Time.

For Further Information, Please Contact:

Mark Turner, Vice President, Business Valuations and Investor Relations: +1 416 342 5565

Irina Kuznetsova, Manager, Investor Relations: +1 416 342 5583

Robert Eriksson, Investor Relations Sweden: +46 8 440 54 50

Other Information

The Technical Information in this press release has been prepared in accordance with NI 43 -101 and has been reviewed and approved by Arman Barha, P.Eng., Vice

President, Technical Services of the Company, a "Qualified Person" under NI 43-101. Mr. Barha has verified the data disclosed in this release and no limitations were

imposed on his verification process.

Historical Non-GAAP Measure Comparatives

Cash Cost and Sustaini ng and Expansionary Expenditures are non -GAAP financial measures and are not

standardized financial measures under generally accepted accounting principles under IFRS and, therefore,

amounts presented may not be comparable to similar data presented by other mining companies.

Cash Cost – Year Ended December 31, 2021

Operations Candelaria Chapada Eagle Neves-Corvo Zinkgruvan

($ thousands, unless otherwise noted) (Cu) (Cu) (Ni) (Cu) (Zn) Total

Sales volumes (Payable metal contained metal in concentrate):

Tonnes 148,213 47,123 15,012 36,618 64,056

Pounds (000s) 326,753 103,888 33,096 80,729 141,219

Production costs 1,436,278

Less: Royalties and other (57,887)

Ore stockpile inventory write-down (65,025)

1,313,366

Deduct: By-product credits (646,950)

Add: Treatment and refining charges 122,330

Cash cost 494,213 108,782 (40,883) 152,416 74,218 788,746

Cash cost per pound ($/lb) 1.51 1.05 (1.24) 1.89 0.53

Cash cost is a non-GAAP measure. See the Management’s Discussion and Analysis for the year ended December 31, 2021, for discussion of non -GAAP

measures under the heading “Non-GAAP and Other Performance Measures” on page 26 which is incorporated by referenc e herein.

Capital Expenditures – Year Ended December 31, 2021

($ thousands) Sustaining Expansionary

Capitalized

Interest Total

Candelaria 312,388 - - 312,388

Chapada 52,275 - - 52,275

Eagle 16,279 - - 16,279

Neves-Corvo 52,552 56,388 336 109,276

Zinkgruvan 41,325 - - 41,325

Other 554 - - 554

475,373 56,388 336 532,097

Capital expenditures are reported on a cash basis, as presented in the consolidated statement of cash flows.

Expansionary capital expenditures are non-GAAP measures. See the Management’s Discussion and Analysis for

the year ended December 31, 2021, for discussion of non -GAAP measures heading “Non-GAAP and Other

Performance Measures” on page 26 which is incorporated by reference herein.

Cautionary Statement on Forward-Looking Information

Certain of the statements made and information contained herein is “forward -looking information” within the meaning of applicable Canadian securities laws. All

statements other than statements of historical facts included in this document constitute forward -looking information, including but not limited to statements

regarding the Company’s plans, prospects and business strategies; the Company’s guidance on the timing and amount of future p roduction and its expectations

regarding the results of operations; expected costs; permitting requirements and timelines; timing and possible outcome of pending litigation; the results of any

Preliminary Economic Assessment, Feasibility Study, or Mineral Resource and Mineral Reserve estimati ons, life of mine estimates, and mine and mine closure plans;

anticipated market prices of metals, currency exchange rates, and interest rates; the development and implementation of the C ompany’s Responsible Mining

Management System; the Company’s ability to comply with contractual and permitting or other regulatory requirements; anticipated exploration and development

activities at the Company’s projects; the Company’s integration of acquisitions and any anticipated benefits thereof; and exp ectations for other economic, business,

and/or competitive factors. Words such as “believe”, “expect”, “anticipate”, “contemplate”, “target”, “plan”, “goal”, “aim”, “intend”, “continue”, “budget”, “estimate”,

“may”, “will”, “can”, “could”, “should”, “schedule” and similar expressions identify forward-looking statements.

Forward-looking information is necessarily based upon various estimates and assumptions including, without limitation, the expectations and beliefs of management,

including that the Company can access financing, appropriate equipment and sufficient labor; assumed and future price of copper, nickel, zinc, gold and other metals;

anticipated costs; ability to achieve goals; the prompt and effective integration of acquisitions; that the political environ ment in which the Company operates will

continue to support the development and operation of mining projects; and assumptions related to the factors set forth below. While these facto rs and assumptions

are considered reasonable by Lundin Mining as at the date of this document in light of management’s experience a nd perception of current conditions and expected

developments, these statements are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors

could cause actual results to differ materia lly from those projected in the forward -looking statements and undue reliance should not be placed on such statements

and information. Such factors include, but are not limited to: risks inherent in mining including but not limited to risks to the environment, industrial accidents,

catastrophic equipment failures, unusual or unexpected geological formations or unstable ground conditions, and natural phenomena such as earthquakes, flooding

or unusually severe weather; uninsurable risks; global financial conditions and inflation; changes in the Company’s share price, and volatility in the equity markets in

general; volatility and fluctuations in metal and commodity demand and prices; changing taxation regimes; delays or the inabi lity to obtain, retain or compl y with

permits; reliance on a single asset; unavailable or inaccessible infrastructure, infrastructure failures, and risks related to ageing infrastructure; risks related to negative

publicity with respect to the Company or the mining industry in general; health and safety risks; pricing and availability of key supplies and services; the threat

associated with outbreaks of viruses and infectious diseases, including the COVID -19 virus; exchange rate fluctuations; risks relating to attracting and retaining of

highly skilled employees; risks inherent in and/or associated with operating in foreign countries and emerging markets; clima te change; regulatory investigations,

enforcement, sanctions and/or related or other litigation; existence of significant shareholders; uncertain political and economic environments, including in Argentina,

Brazil and Chile; risks associated with acquisitions and related integration efforts, including the ability to achieve antici pated benefits, unanticipated difficulties or

expenditures relating to integration and diversion of management time on integration; indebtedness; liquidity risks and limited finan cial resources; funding

requirements and availability of financing; exploration, development or mining results not being consistent with the Company’s expectations; risks related to the

environmental regulation and environmental impact of the Company’s operations and products and management thereof; activist shareholders and proxy solicitation

matters; reliance on key personnel and re porting and oversight systems, as well as third parties and consultants in foreign jurisdictions; historical environmental

liabilities and ongoing reclamation obligations; information technology and cybersecurity risks; risks related to mine closur e activities, reclamation obligations, and

closed and historical sites; social and political unrest, including civil disruption in Chile; the inability to effectively c ompete in the industry; financial projections,

including estimates of future expenditures and ca sh costs, and estimates of future production may be unreliable; actual ore mined and/or metal recoveries varying

from Mineral Resource and Mineral Reserve estimates, estimates of grade, tonnage, dilution, mine plans and metallurgical and other characteristics; ore processing

efficiency; risks associated with the estimation of Mineral Resources and Mineral Reserves and the geology, grade and continuity of mineral deposits including but not

limited to models relating thereto; enforcing legal rights in foreign jurisdictions; community and stakeholder opposition; changes in laws, regulations or policies

including but not limited to those related to mining regimes, permitting and approvals, environmental and tailings management , labor, trade relations, and

transportation; risks associated with the structural stability of waste rock dumps or tailings storage facilities; dilution; risks relating to dividends; conflicts of interest;

counterparty and credit risks and customer concentration; the estimation of asset car rying values; challenges or defects in title; internal controls; relationships with

employees and contractors, and the potential for and effects of labor disputes or other unanticipated difficulties with or sh ortages of labor or interruptions in

production; compliance with foreign laws; potential for the allegation of fraud and corruption involving the Company, its customers, su ppliers or employees, or the

allegation of improper or discriminatory employment practices, or human rights violations; compliance with environmental, health and safety regulations and laws;

and other risks and uncertainties, including but not limited to those described in the “Risk and Uncertainties” section of th e Company’s AIF and the “Managing Risks”

section of the Company’s MD&A for the year ended December 31, 2021, which are available on SEDAR at www.sedar.com under the Company’s profile. All of the