Lundin GOLD Underground MINE Development into HARD ROCK at Fruta Del Norte

Mine Development & Operations

NEWS RELEASE

LUNDIN GOLD UNDERGROUND MINE DEVELOPMENT INTO HARD

ROCK AT FRUTA DEL NORTE

January 10, 2018 (Vancouver, Canada) Lundin Gold Inc. ("Lundin Gold" or the "Company")

(TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce that soft tunneling was

completed in December 2017 and mine development is now into hard rock at its Fruta del

Norte gold project (“Fruta del Norte” or the “Project”) in Ecuador.

Further Highlights

• Award of all major process plant equipment packages

• Mobile equipment packages, including underground mine scoop trams and haul trucks,

have been awarded

• Process plant excavation is progressing ahead of schedule

• 1,000-person construction camp is nearing completion

• Approval of powerline Environmental Impact Assessment (“EIA”)

“Tunneling through soft clay was a significant risk factor to underground mine development

due to the potential for ground failure. We were able to get through this challenging task, and

the mine development is now advancing at a quicker pace ,” said Ron Hochstein, President

and CEO of Lundin Gold. “We are also ramping up other major projects, including the process

plant and powerline.”

Mine Development

The Company transitioned from soft tunneling to hard rock tunneling in December 2017,

working through 77 metres of saprolite (soft clay) in the first decline and 69 metres in the

second. Drilling and blasting in hard rock commenced on December 7th in the first decline and

December 17th in the second, and currently the advance in hard rock reached 100 metres and

78 metres, in the first and second declines, respectively.

Process Plant Equipment Procurement

In October 2017, Lundin Gold awarded the long-lead time grinding equipment package s,

including the SAG and ball mills (complete with motors) and the flotation and filtration packages

to Outotec Chile S.A.

The gravity mill, CIL and detox tanks, and ADR plant and gold room packages were recently

awarded to FLSmidth USA Inc. TelSmith Inc. will provide the crushing packages for both the

process plant and aggregate quarry crushers. ABB Inc. has been awarded switchgear and

substation equipment and transformers packages.

2

Mobile Equipment

Most of the mobile mine equipment orders have been placed. Importadora Industrial Agricola

S.A./Caterpillar will provide the underground m ine scoop trams and trucks, as well as the

surface earthworks and quarry equipment. Orders for the mine jumbos and bolters are

expected to be awarded this quarter.

Powerline

The EIA for the powerline received final approval at the end of 2017. Easement agreements

have been reached with 91% of affected landholders, and the Company expects the remaining

easements to be obtained this quarter. Detailed engineering and procurement is well

underway, and the engineering, procurement and construction contractor is on track to begin

building the powerline this quarter.

Major Earthworks

Regardless of difficult ground conditions, site earthworks are on schedule. Earthworks on the

process plant is 13% complete with concrete mill foundations planned to start this quarter.

The North Access Road is progressing well, and 32% of the road has been built. A second

earthworks contractor was mobilized at El Pindal, where the North Access Road will link to the

national highway system. Approximately six kilometres needs to be built to connect the North

Access Road from either side.

Construction Camp

All other construction disciplines are actively working on t he 1,000-person construction camp

which is nearing completion, with over 60% of the units currently available for occupancy.

Combined with the existing camp, there are more than 1,200 beds available. During the last

month, approximately 800 people were at site, including contractors.

About Lundin Gold

Lundin Gold, headquartered in Vancouver, Canada, is developing its wholly -owned Fruta del

Norte gold project in southeast Ecuador. Fruta del Norte is one of the highest -grade and

largest gold projects currently under construction. The Company’s board and management

team have extensive expertise in mine construction and operations, and are dedicated to

advancing this project through to first gold production in 2019.

The Company operates with transparency and in accordance with international best practices.

Lundin Gold is committed to delivering value to its shareholders, while simultaneously

providing economic and social benefits to impacted communities, fostering a healthy and safe

workplace and minimizing the environmental impact. The Company believes that the value

created through the development of Fruta del Norte will benefit its shareholders, the

Government and the people of Ecuador.

3

This press release has been reviewed and approved by Ron Hochstein, P. Eng., a

metallurgical engineer and the Compan y's President and CEO, who is a Qualified Person

under Canadian National Instrument 43-101.

Additional Information

The information in this release is subject to the disclosure requirements of Lundin Gold under

the EU Market Abuse Regulation and the Swedish Securities Markets Act. This information

was publicly communicated at 5:00 am Pacific Time on January 10, 2018.

For more information, please contact:

Lundin Gold Inc.

Ron F. Hochstein

President and CEO

+593-2-299-6400

+1-604-806-3589

Lundin Gold Inc.

Sabina Srubiski

Manager, Investor Relations

+1-604-806-3089

[email protected]

www.lundingold.com

Follow Lundin Gold on Twitter

Caution Regarding Forward-Looking Information and Statements

Certain of the information and statements in this press release are considered “forward -looking

information” or “forward-looking statements” as those terms are defined under Canadian securities laws

(collectively referred to as “forward -looking statements” ). Any statements that express or involve

discussions with respect to predictions, expectations, beliefs, plans, projections, objectives,

assumptions or future events or performance (often, but not always, identified by words or phrases such

as “believes” , “anticipates”, “expects”, “is expected”, “scheduled”, “estimates”, “pending”, “intends”,

“plans”, “forecasts”, “targets”, or “hopes”, or variations of such words and phrases or statements that

certain actions, events or results “may”, “could”, “would”, “will”, “should” “might”, “will be taken”, or “occur”

and similar expressions) are not statements of historical fact and may be forward-looking statements.

By their nature, forward -looking statements and information involve assumptions, inherent risks and

uncertainties, many of which are difficult to predict, and are usually beyond the control of management,

that could cause actual results to be materially different from those expressed by these forward-looking

statements and information. Lundin Gold believes that the expectations reflected in this forward-looking

information are reasonable, but no assurance can be given that these expectations will prove to be

correct. Forward -looking information should not be unduly relied upon. This information speaks only

as of the date of this press release, and the Company will not necessarily update this information, unless

required to do so by securities laws.

This press release contains forward -looking information in a number of places, such as in statements

pertaining to the timing of first gold production, the timing and progress of the development, construction

and operation of FDN, the timing and progress of the development and construction the powerline, the

timing and success of permitting and regulatory approvals and the award of certain purchase orders and

contracts and the acquisition of easements . Lundin Gold’s actual results could differ materially from

those anticipated. Management has identified the following risk factors which could have a mater ial

impact on the Company or the trading price of its shares: the ability to arrange financing and the risk to

shareholders of dilution from future equity financings; risks related to carrying on business in an

emerging market such as possible government instability and civil turmoil and economic instability;

4

volatility in the price of gold; the timely receipt of regulatory approvals, permits and licenses; risks

associated with the performance of the Company’s contractors; risks inherent in the development of an

underground mine; deficient or vulnerable title to mining concessions and surface rights; shortages of

resources, such as labour, and the dependence on key personnel; risks associated with the Company’s

community relationships; unreliable infrastructure and local opposition to mining; volatility in the market

price of the Company’s shares; uncertainty with the tax regime in Ecuador; measures required to protect

endangered species; difficulty complying with changing government regulations and policies , including

without limitation, compliance with environment, health and safety regulations, and the cost of

compliance or failure to comply with applicable laws; exploration and development risks; the accuracy

of the Mineral Reserve and Resource estimates for FDN and the Company’s reliance on one project;

the Company’s lack of operating history in Ecuador; illegal mining; uncertainty as to reclamation and

decommissioning; adverse global economic conditions; risks associated with the Company’s information

systems; the inadequacy of insurance; risks of bribery or corruption; the potential for litigation; limits of

disclosure and internal controls; and the potential influence of the Company’s largest shareholders.

There can be no assurance that such statements will prove to be accurate, as Lundin Gold's actual

results and future events could differ materially from those anticipated in this forward-looking information

as a result of the factors discussed in the "Risk Factors" section in Lundin Gold's Annual Information

Form for the financial year ended December 2016 and the Prospectus dated December 21, 2017, both

of which are available on SEDAR at www.sedar.com.

Figure 1. Hard rock tunneling at Fruta del Norte underground mine

5

Figure 2. Process plant earthworks

Figure 3. 1,000-person construction camp