Lundin GOLD Orders Long-Lead Time Process Plant Equipment and Confirms MINE Development is Underway

Mine Development & Operations Metallurgy & Processing

NEWS RELEASE

LUNDIN GOLD ORDERS LONG-LEAD TIME PROCESS PLANT

EQUIPMENT AND CONFIRMS MINE DEVELOPMENT IS UNDERWAY

October 18, 2017 (Vancouver, Canada) Lundin Gold Inc. ("Lundin Gold" or the "Company")

(TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce that long-lead time process plant

equipment for its Fruta del Norte gold project (“Fruta del Norte” or the “Project” ) in Ecuador

has been ordered and that soft tunneling is well advanced.

Further Highlights

• Detailed e ngineering contracts for the process plant, tailings facility and water

management have been awarded

• Engineering, procurement and construction (“EPC”) contract for the power

transmission line from the Bomboiza substation to Fruta del Norte has been awarded

• Major earthworks activities are progressing and work on the process plant has started

“The Project has very quickly transitioned from basic to detailed engineering and onsite

earthwork and mining act ivities have successfully ramped up according to plan, ” said Ron

Hochstein, President and CEO of Lundin Gold. “We continue to de-risk Fruta del Norte with

long-lead time purchase orders confirmed, advancement of the Project’s infrastructure and

significant progress on the civil earthworks programs.”

Mine Development

The mine contractor, SME, which is a consortium of Ingeniería y Construcciones Mas Errazuriz

Limitada y Filiales (Chilean) and Sevilla y Martínez Ingenieros C.A. (Semaica) (Ecuadorian)

began work on the twin portals in May of this year. Both portals are in place and soft tunneling

through the initial clay commenced on September 20th for the first decline and October 7th for

the second. Currently, soft tunneling has advanced approximately 23 metres in the first decline

and seven metres in the second. The transition from soft tunneling to hard rock development

is expected to begin as scheduled by the end of the year.

The facilities to support mine development, including offices, mine dry, warehouse,

maintenance, and batch plant have also been built and are operational.

Process Plant Equipment Procurement

Lundin Gold is moving forward with the engineering and procurement of the process plant.

The long-lead time grinding equipment package, including the SAG and ball mills, complete

with motors, was awarded to Outotec Chile S.A. (“Outotec”). Outotec was also awarded the

flotation and filtration packages. The procurement of the remaining process plant equipment

packages is well advanced and is expected to be awarded by the end of the year.

2

Detail Engineering Contracts

Process plant detailed engineering was awarded to Ausenco Engineering Canada Inc.

(“Ausenco”) and is expected to be completed in the fourth quarter of 2018. Earlier this year,

Ausenco also completed optimization work for the process plant.

Klohn Crippen Berger Ltd. will provide detailed designs and site quality control for the tailings

storage facility and site geotechnical engineering . S ite-wide water management design has

been awarded to SRK Consulting (Canada) Inc.

Bidding for the design and supply of the mine paste plant has commenced , and this contract

is expected to be awarded in the first quarter of 2018.

Powerline

The EPC contract for the 42 kilometre, 230 kilovolt transmission line that will connect the

national grid at Bomboiza to Fruta del Norte was awarded to a consortium that will be formed

by two Ecuadorian companies, Coinfect S.A Ingenieros Contratistas and Energic y Petrolia’s

Inexpertly, S.A. Detailed engineering has started and construction is expected to begin in the

first quarter of 2018.

The draft Environmental Impact Assessment report for the powerline was submitted to the

Ministry of Environment in May 2017 and the Company anticipates receiving final approval and

granting of the license by the end of the year.

Major Earthworks Activities

Major earthworks activities are advancing, including clearing of the plant site, construction of

the main North Access road and the River road on site. The earthworks for the 1,000 person

construction camp is mostly complete along with the installation of utilities. Building out of the

facilities has begun and the construction camp is expected to be completed in the first quarter

of 2018.

About Lundin Gold

Lundin Gold, headquartered in Vancouver, Canada, is developing its wholly -owned Fruta del

Norte gold project in southeast Ecuador. Fruta del Norte is one of the highest -grade and

largest gold projects currently under constructi on. The Company’s board and management

team have extensive expertise in mine construction and operations, and are dedicated to

advancing this project through to first gold production in 2019.

The Company operates with transparency and in accordance with international best practices.

Lundin Gold is committed to delivering value to its shareholders, while simultaneously

providing economic and social benefits to impacted communities, fostering a healthy and safe

workplace and minimizing the environmental im pact. The Company believes that the value

created through the development of Fruta del Norte will benefit its shareholders, the

Government and the people of Ecuador.

3

This press release has been reviewed and approved by Ron Hochstein, P. Eng., a

metallurgical engineer and the Company's President and CEO, who is a Qualified Person

under National Instrument 43-101.

Additional Information

The information in this release is subject to the disclosure requirements of Lundin Gold under

the EU Market Abuse Regulation and the Swedish Securities Markets Act. This information

was publicly communicated at 5:00 am Pacific Time on October 18, 2017.

For more information, please contact:

Lundin Gold Inc.

Ron F. Hochstein

President and CEO

+593-2-299-6400

+1-604-806-3589

Lundin Gold Inc.

Sabina Srubiski

Manager, Investor Relations

+1-604-806-3089

[email protected]

www.lundingold.com

Caution Regarding Forward-Looking Information and Statements

Caution Regarding Forward -Looking Information and Statements Certain of the information and

statements in this press release are considered “forward -looking information” or “forward -looking

statements” a s those terms are defined under Canadian securities laws (collectively referred to as

“forward-looking statements”). Any statements that express or involve discussions with respect to

predictions, expectations, beliefs, plans, projections, objectives, ass umptions or future events or

performance (often, but not always, identified by words or phrases such as “believes”, “anticipates”,

“expects”, “is expected”, “scheduled”, “estimates”, “pending”, “intends”, “plans”, “forecasts”, “targets”, or

“hopes”, or variations of such words and phrases or statements that certain actions, events or results

“may”, “could”, “would”, “will”, “should” “might”, “will be taken”, or “occur” and similar expressions) are

not statements of historical fact and may be forward-looking statements.

By their nature, forward -looking statements and information involve assumptions, inherent risks and

uncertainties, many of which are difficult to predict, and are usually beyond the control of management,

that could cause actual results to be materially different from those expressed by these forward-looking

statements and information. Lundin Gold believes that the expectations reflected in this forward-looking

information are reasonable, but no assurance can be given that these expectations will prove to be

correct. Forward -looking information should not be unduly relied upon. This information speaks only

as of the date of this press release, and the Company will not necessarily update this information, unless

required to do so by securities laws.

This press release contains forward -looking information in a number of places, such as in statements

pertaining to the timing and progress of the development, construction and operation of FDN; the timing

and success of permitting and regulator y approvals and the award of certain purchase orders and

contracts. Lundin Gold’s actual results could differ materially from those anticipated. Management has

identified the following risk factors which could have a material impact on the Company or the trading

price of its shares: the ability to arrange financing and the risk to shareholders of dilution from future

equity financings; risks related to carrying on business in an emerging market such as possible

government instability and civil turmoil and economic instability; volatility in the price of gold; the timely

receipt of regulatory approvals, permits and licenses; risks associated with the performance of the

Company’s contractors; risks inherent in the development of an underground mine; deficient or

4

vulnerable title to mining concessions and surface rights; shortages of resources, such as labour, and

the dependence on key personnel; risks associated with the Company’s community relationships;

unreliable infrastructure and local opposition to mining; volatility in the market price of the Company’s

shares; uncertainty with the tax regime in Ecuador; measures required to protect endangered species;

difficulty complying with changing government regulations and policies, including without limit ation,

compliance with environment, health and safety regulations, and the cost of compliance or failure to

comply with applicable laws; exploration and development risks; the accuracy of the Mineral Reserve

and Resource estimates for FDN and the Company’s reliance on one project; the Company’s lack of

operating history in Ecuador; illegal mining; uncertainty as to reclamation and decommissioning; adverse

global economic conditions; risks associated with the Company’s information systems; the inadequacy

of insurance; risks of bribery or corruption; the potential for litigation; limits of disclosure and internal

controls; and the potential influence of the Company’s largest shareholders.

There can be no assurance that such statements will prove to be acc urate, as Lundin Gold's actual

results and future events could differ materially from those anticipated in this forward-looking information

as a result of the factors discussed in the "Risk Factors" section in Lundin Gold's Annual Information

Form for the financial year ended December 2016, which is available on SEDAR at www.sedar.com.