Lundin GOLD Now Past One Kilometre of Underground MINE Development at Fruta Del Norte

Mine Development & Operations

NEWS RELEASE

LUNDIN GOLD NOW PAST ONE KILOMETRE OF UNDERGROUND

MINE DEVELOPMENT AT FRUTA DEL NORTE

April 16, 2018 (Vancouver, Canada) Lundin Gold Inc. ("Lundin Gold" or the "Company")

(TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce that is has reached major

construction milestones and is now past one kilometre of underground mine development at

its Fruta del Norte gold project (“Fruta del Norte” or the “Project”) in Ecuador.

Construction Highlights:

• Process plant SAG and ball mill foundation bases have been poured

• Major earthworks continue with completion of River road, which significantly improves

site logistics

• Completion of first major pond for site water management system

• Powerline contractor mobilizing to start construction later this quarter

• 1,000-person construction camp completed

“We continue to advance Fruta del Norte on budget and on schedule. Overall engineering is

26% co mplete and construction is 16% complete, and we are continuously looking for

efficiencies as we move the Project forward,” said Ron Hochstein, President and CEO of

Lundin Gold.

Mine Development

As at March 31, 2018, a total of 1,193 metres (“m”) of underground mine development has

been achieved, with 531 m and 632 m in the Kuri and K’isa declines, respectively. The average

advance rate for March was 5.95 m per decline per day, versus a target of 5.17 m per day

based on ground type encountered. All underground development in March was classified as

good ground type conditions.

As well, earlier this month the Company awarded the underground drill/bolt mining fleet to

Epiroc Rock Drills AB. With this order, over 84% of the production fleet contracts have been

placed. The outstanding mine equipment left to be ordered is the explosives delivery, shotcrete

equipment and mine support equipment.

Process Plant Construction

Process plant excavation was 65% complete at the end of March. The ball mill and the SAG

mill base concrete foundation s were poured on March 10 and March 25 respectively.

Excavation of the CIL plant area is progressing well. Over the next couple of months, the

Company is planning on completing the mill foundations, and concrete work on the CIL plant

area is expected to commence.

As part of the overall water management system, the first of several large lined collection ponds

was completed.

2

Major Earthworks

With the completion of the River road connecting the camp to the Project site, site logistics

have greatly improved. Travel time between camp and the Project site is now approximately

10-15 minutes, whereas it previously took up to 45 minutes using the Mountain Pass road.

The North Access road is now an estimated 42% complete, and work is substantially complete

on the road to the tailings storage facility.

Powerline

The powerline engineering, procurement and construction contractor is mobilizing and

anticipated to begin construction later this quarter. Easement agreements have been reached

with nearly all the affected landholders, and the remaining easements are expected to be

obtained in the coming weeks.

Construction Camp

The new 1,000-person construction camp is complete, and all rooms are available for

occupancy. Combined with the existing Las Pe ñas camp, over 1,700 people can be

accommodated at site. Occupancy averaged 1,165 people in March, and total project

employment now exceeds 2,200 people, including contractors. The new kitchen and dining

room are expected to be finished by the end of the month.

About Lundin Gold

Lundin Gold, headquartered in Vancouver, Canada, is developing its wholly -owned Fruta del

Norte gold project in south east Ecuador. Fruta del Norte is one of the highest -grade and

largest gold projects currently under construction. The Company’s board and management

team have extensive expertise in mine construction and operations and are dedicated to

advancing this project through to first gold production in 2019.

The Company operates with transparency and in accordance with international best practices.

Lundin Gold is committed to delivering value to its shareholders, while simultaneously

providing economic and social benefits to impacted communities, fostering a healthy and safe

workplace and minimizing the environmental impact. The Company believes that the value

created through the development of Fruta del Norte will benefit its shareholders, the

Government and the people of Ecuador.

This press release has been reviewed and approved by Ron Hochstein, P. Eng., a

metallurgical engineer and the Company's President and CEO, who is a Qualified Person

under Canadian National Instrument 43-101.

Additional Information

The information in this release is subject to the disclosure requirements of Lundin Gold under

the EU Market Abuse Regulation. This information was submitted for publication on April 16,

2018 at 3:00 am PT through the contact persons set out below.

3

For more information, please contact:

Lundin Gold Inc.

Ron F. Hochstein

President and CEO

+593-2-299-6400

+1-604-806-3589

Lundin Gold Inc.

Sabina Srubiski

Manager, Investor Relations

+1-604-806-3089

[email protected]

www.lundingold.com

Follow Lundin Gold on Twitter

Caution Regarding Forward-Looking Information and Statements

Certain of the information and statements in this press release are considered “forward-looking

information” or “forward -looking statements” as those terms are defined under Canadian

securities laws (collectively referred to as “forward-looking statements”). Any statements that

express or involve discussions with respect to predictions, expectations, beliefs, plans,

projections, objectives, assumptions or future events or performance (often, but not always,

identified by words or phrases such as “believes” , “anticipates”, “expects”, “is expected”,

“scheduled”, “estimates”, “pending”, “intends”, “plans”, “forecasts”, “targets”, or “hopes”, or

variations of such words and phrases or statements that certain actions, events or results

“may”, “could”, “would”, “ will”, “should” “might”, “will be taken”, or “occur” and similar

expressions) are not statements of historical fact and may be forward-looking statements.

By their nature, forward -looking statements and information involve assumptions, inherent

risks and uncertainties, many of which are difficult to predict, and are usually beyond the control

of management, that could cause actual results to be materially different from those expressed

by these forward -looking statements and information. Lundin Gold belie ves that the

expectations reflected in this forward -looking information are reasonable, but no assurance

can be given that these expectations will prove to be correct. Forward -looking information

should not be unduly relied upon. This information speaks only as of the date of this press

release, and the Company will not necessarily update this information, unless required to do

so by securities laws.

This press release contains forward -looking information in a number of places, such as in

statements pert aining the timing of first production and the progress of the development,

construction and operation of the Project , improvements to site logistics and completion of

camp infrastructure and the acquisition of land and surface rights . Factors that could ca use

actual results to differ materially from the Company’s expectations include, but are not limited

to; the ability to arrange financing and the risk to shareholders of dilution from future equity

financings; the ability to maintain its obligations under its current project financing and other

debt; risks related to carrying on business in Ecuador; volatility in the price of gold; the timely

receipt of regulatory approvals, permits and licenses; risks associated with the performance of

the Company’s contra ctors; risks inherent in the development of an underground mine;

deficient or vulnerable title to mining concessions and surface rights; shortages of critical

resources, labour and key executive personnel, such as input commodities, equipment and

skilled labour, and the dependence on key personnel; risks associated with the Company’s

community relationships; unreliable infrastructure; volatility in the market price of the

4

Company’s shares; and the potential influence of the Company’s largest shareholders;

uncertainty with the tax regime in Ecuador; measures required to protect endangered species;

the cost of compliance or failure to comply with applicable laws; exploration and development

risks; the accuracy of the Mineral Reserve and Resource estimates for the Fruta del Norte

Project and the Company’s reliance on one project; risks related to artisanal and illegal mining;

uncertainty as to reclamation and decommissioning; risks associated with the Company’s

information systems; competition in the mining indu stry; the ability to obtain adequate

insurance; risks of bribery or corruption; the potential for litigation; and limits of disclosure and

internal controls.

There can be no assurance that such statements will prove to be accurate, as Lundin Gold's

actual results and future events could differ materially from those anticipated in this forward -

looking information as a result of the factors discussed in the "Risk Factors" section in Lundin

Gold's Annual Information Form dated March 20, 2018, which is avail able under the

Company’s profile at www.sedar.com.

Figure 1. Over 1 km of underground development has been achieved at Fruta del Norte

5

Figure 2. SAG and ball mill base concrete foundations

Figure 3. First major pond for site water management completed

6

Figure 4. New construction camp and original Las Peñas camp provide capacity for over

1,700 personnel