Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LUG.TO ·

Lundin GOLD Inc. Reports Third Quarter 2017 Results

Financials

NEWS RELEASE

LUNDIN GOLD INC. REPORTS THIRD QUARTER 2017 RESULTS

November 7, 2017 (Vancouver, Canada) Lundin Gold Inc. ("Lundin Gold" or the "Company")

(TSX: “LUG”, Nasdaq Stockholm: “LUG”) is pleased to announce its results for the three and

nine months ended September 30, 2017. All amounts in this release are in U.S. dollars unless

otherwise indicated.

During the quarter , Lundin Gold ramp ed up construction at the Fruta del Norte gold project

(“Fruta del Norte” or “the Project”) and there are now approximately 800 people at site ,

including contractors. The Company also advanced exploration targets to prepare for drill

testing, which is expected to begin later this year.

“We have made a remarkable amount of progress in a short period of time and are well into

the construction phase at Fruta del Norte,” said Ron Hochstein, Lundin Gold’s President and

Chief Executive Officer. “We plan to hit hard rock before the end of the year in the underground

mine, keeping the critical path on track, and we are making ex cellent progress on the

procurement and design of both the process plant and powerline, both of which are key to the

advancement of the Project.”

Highlights

Fruta del Norte

• Mine portals were completed and soft tunneling is well advanced.

• Key infrastructure at site to support mine development was completed.

• Detailed engineering contracts for the process plant, tailings facility and water

management were awarded and work began on all areas.

• Long-lead time process plant equipment was ordered.

• Engineering, procurement and construction (“EPC”) contract for the power

transmission line from the Bomboiza substation to the site was awarded.

• Major earthworks activities are progressing and work on the process plant area started.

Exploration

• Targets in preparation for drill testing were better defined, with geochemical sampling

and mapping completed on the Barbasco and Puente -Princesa epithermal gold-silver

targets within the Suarez pull-apart basin (the “Basin”) that hosts the Fruta del Norte.

Both targets are located approximately 7 kilometers south of the Project.

2

Financial Results

(in thousands, except per share

amounts)

Three months ended

September 30,

Nine months ended

September 30,

2017 2016 2017 2016

Results of Operations:

Net loss for the period $ (16,032) $ (11,785) $ (21,635) $ (38,925)

Basic and diluted loss per share (0.13) (0.10) (0.18) (0.37)

(in thousands)

As at

September

30, 2017

As at

December

31, 2016

Financial Position:

Cash 62,951 8,503

Working capital 66,196 1,022

Property, plant and equipment 87,312 7,822

Mineral properties 245,669 236,874

Total assets 434,198 278,906

Long-term liabilities 170,738 974

Note: the complete analysis of the Q3 2017 financial results can be found in the MD&A and financial statements

dated November 7, 2017 filed on SEDAR.

The Company’s net loss in the current quarter is higher compared to the net loss during the

third quarter of 2016 mainly due to a derivative loss of $8.3 million from the fair value

revaluation of its long-term debt at September 30, 2017. This balance is valued using Monte

Carlo simulation valuation models. The key inputs used by the Monte Carlo simulation include:

the gold and silver forward curve based on Comex futures, the Company’s expectation about

long-term gold yields, gold a nd silver volatility, risk -free rate of return, non -performance risk,

and production expectations.

The loss in the nine months ended September 30, 2017 is lower compared to that of the nine

months ended September 30, 2016 due to the commencement of capitalization of expenses

which is offset by a derivative loss from the revaluation of the Company’s long-term debt.

Liquidity and Capital Resources

As at September 30, 2017, the Company had cash of $63.0 million and a working capital of

$66.7 million compared to cash of $8.5 million and a working capital balance of $1.0 million at

December 31, 2016. The change in cash was primarily due to proceeds from a project finance

package of $ 300 million (the “Financing”) with Orion Mine Finance Group and Blackstone

Tactical Opportunities (the “Lenders”) of which $150 million has been drawn to date, offset by

costs incurred for the development of the Project of $67.8 million and exploration expenditures

of $4.7 million.

3

The Financing

On May 30, 2017, the Company's operating subsidiary, Aurelian Ecuador S.A. ("Aurelian"),

which holds Fruta del Norte, closed the Financing comprised of a gold prepay credit facility for

$150 million, a stream loan credit facility of $150 million and an offtake agreement. The

Lenders also committed to participate in future equity financings of the Company required to

fund the Project, in an aggregate amount of not less than $100 million and not more than $150

million, as and when initiated by the Company and subject to minimum financing thresholds.

Outlook

The third quarter of 2017 marked the commencement of construction at the Fruta del Norte

Project. The Company’s focus now is on advancing the Project through to first gold production

in 2019. To achieve that goal, the following activities are planned over the next twelve months:

• Completion of all Early Works activities by the end of the year.

• Completion of soft tunnelling and commence ment of underground hard rock

development in 2017.

• Advancement of detailed engineering of the process plant, tailings storage facility and

site-wide water management into 2018.

• Ordering of remaining process plant equipment and electrical packages and m obile

mine equipment in 2017.

• Approval of the Mountain Pass Quarry EIA and signing of an exploitation agreement

for the quarry to permit the extraction of construction materials in 2018.

• Continuation of e arthworks activities, including the clearing of the plant site ,

construction of the North Access and River Roads and site preparation for the tailings

dam.

• Commencement of concrete work on the process plant in 2018.

• Commencement of construction of the Bomboiza / Fruta del Norte powerline in 2018.

During the next several months, the Company will also continue to work with its financial

advisors to put in place the remaining funding for the construction of Fruta del Norte, including

continuing advanced discussions with a syndicate of banks.

A helicopter Z -Tipper Axis Electromagnetic resistivity geophysical survey of the Basin and

surrounding terrain is planned to take place by the end of 2017. Soil sampling has been

completed on most of the Company’s concessions in the Basin, and geological mapping is

continuing on selected targets; targets will be prioritized for drilling scheduled to begin before

the end of 2017.

Qualified Person

The technical information relating to the Fruta del Norte Project contained in this news release

has been reviewed and approved by Ron Hochstein P. Eng, Lundin Gold’s President & CEO

who is a Qualified Person under National Instrument 43-101 (“NI 43-101”). The disclosure of

exploration information contained in this press release was prepared by Steve Leary,

MAusIMM CP(Geo), a consultant to the Company, who is a Qualified Person under NI 43-101.

Full details of the Feasibility Study can be found in a technical report entitled "Fruta del Norte

- NI 43-101 Technical Report on Feasibility Study" which has an effective date of April 30,

4

2016. The Technical Report is available for review under the Company's profile on SEDAR

(www.sedar.com) and on the Company's website (www.lundingold.com).

Additional Information

The Company’s consolidated financial statements for the three months and nine months ended

September 30, 2017 and related management’s discussion and analysis are available on the

Company’s website at www.lundingold.com or under its profile on SEDAR at www.sedar.com.

The information in this release is subject to the disclosure requirements of Lundin Gold under

the EU Market Abuse Regulation and the Swedish Securities Markets Act. This information

was publicly communicated on November 7, 2017 at 2:30 pm PT.

About Lundin Gold

Lundin Gold, headquartered in Vancouver, Canada, is developing its wholly -owned Fruta del

Norte gold project in southeast Ecuador. Fruta del Norte is one of the largest, highest-grade

gold projects currently under construction. The Company's board and management team have

extensive expertise in mine construction and operations, and are dedicated to advancing this

project through to first gold production in 2019.

The Company operates with transparency and in accordance with international best practices.

Lundin Gold is committed to delivering value to its shareholders, while simultaneously

providing economic and social benefits to impacted communities, fostering a healthy and safe

workplace and minimizing the environmental impact. The Company believes that the value

created through the development of Fruta del Norte will benefit its shareholders, the

Government and the people of Ecuador.

For more information, please contact

Lundin Gold Inc.

Ron F. Hochstein

President and CEO

+593 2-299-6400

+604-806-3589

Lundin Gold Inc.

Sabina Srubiski

Manager, Investor Relations

+1-604-806-3089

[email protected]

www.lundingold.com

Caution Regarding Forward-Looking Information and Statements

Certain of the information and statements in this press release are considere d “forward -looking

information” or “forward-looking statements” as those terms are defined under Canadian securities laws

(collectively referred to as “forward -looking statements”). Any statements that express or involve

discussions with respect to predic tions, expectations, beliefs, plans, projections, objectives,

assumptions or future events or performance (often, but not always, identified by words or phrases such

as “believes”, “anticipates”, “expects”, “is expected”, “scheduled”, “estimates”, “pending ”, “intends”,

“plans”, “forecasts”, “targets”, or “hopes”, or variations of such words and phrases or statements that

5

certain actions, events or results “may”, “could”, “would”, “will”, “should” “might”, “will be taken”, or “occur”

and similar expressions) are not statements of historical fact and may be forward-looking statements.

By their nature, forward -looking statements and information involve assumptions, inherent risks and

uncertainties, many of which are difficult to predict, and are usually beyond the control of management,

that could cause actual results to be materially different from those expressed by these forward-looking

statements and information. Lundin Gold believes that the expectations reflected in this forward-looking

information are re asonable, but no assurance can be given that these expectations will prove to be

correct. Forward -looking information should not be unduly relied upon. This information speaks only

as of the date of this press release, and the Company will not necessarily update this information, unless

required to do so by securities laws.

This press release contains forward-looking information in a number of places, such as in statements

pertaining to: the timing and success of the Early Works and construction programs, the success of the

Company’s exploration plans and activities, exploration and development expenditures and reclamation

costs, timing and success of permitting and regulatory approvals, p roject financing and future sources

of liquidity, capital expenditures and requirements, the results of the project update and, development,

construction and operation of the Fruta del Norte Project, future tax payments and rates, cash flows and

their uses.

Lundin Gold’s actual results could differ materially from those anticipated. Management has identified

the following risk factors which could have a material impact on the Company or the trading price of its

shares: the ability to arrange financing a nd the risk to shareholders of dilution from future equity

financings; risks related to carrying on business in an emerging market such as possible government

instability and civil turmoil and economic instability; volatility in the price of gold; the time ly receipt of

regulatory approvals, permits and licenses; risks associated with the performance of the Company’s

contractors; risks inherent in the development of an underground mine; deficient or vulnerable title to

mining concessions and surface rights; shortages of resources, such as labour, and the dependence on

key personnel; risks associated with the Company’s community relationships; unreliable infrastructure

and local opposition to mining; volatility in the market price of the Company’s shares; unce rtainty with

the tax regime in Ecuador; measures required to protect endangered species; difficulty complying with

changing government regulations and policies, including without limitation, compliance with

environment, health and safety regulations, and t he cost of compliance or failure to comply with

applicable laws; exploration and development risks; the accuracy of the Mineral Reserve and Resource

estimates for FDN and the Company’s reliance on one project; liabilities; the Company’s lack of

operating history in Ecuador; illegal mining; uncertainty as to reclamation and decommissioning; adverse

global economic conditions; risks associated with the Company’s information systems; the inadequacy

of insurance; risks of bribery or corruption; the potential fo r litigation; limits of disclosure and internal

controls; and the potential influence of the Company’s largest shareholders.

There can be no assurance that such statements will prove to be accurate, as Lundin Gold's actual

results and future events could differ materially from those anticipated in this forward-looking information

as a result of the factors discussed in the "Risk Factors" section in Lundin Gold's Annual Information

Form for the financial year ended December 2016, which is available on SEDAR at www.sedar.com.