Lundin Gold Announces a Positive Feasibility Study for the Fruta del Norte Project and Conference Call

Resource Estimates Technical Reports (NI 43-101) Economic Studies

NEWS RELEASE

LUNDIN GOLD ANNOUNCES A POSITIVE FEASIBILITY STUDY FOR THE FRUTA DEL NORTE PROJECT AND CONFERENCE CALL

June 6, 2016 (Vancouver, Canada)… Lundin Gold Inc. ("Lundin Gold" or the "Company") (TSX: “LUG”, Nasdaq Stockholm: “LUG”) is pleased to announce the results of an independent Feasibility Study (“FS”) for its 100% owned Fruta del Norte Project (“FDN” or the “Project”) in Ecuador.  The FS has been prepared  by  Amec  Foster  Wheeler,  with  the  support  of  four  other  globally  recognized,  leading engineering firms, and is being summarized into a Technical Report (the “FDN Technical Report”) to be filed on SEDAR in accordance with National Instrument 43‐101 (“NI 43‐101”).  The FS confirms that the Project will support an economically viable and robust, high grade underground gold mine.  All dollar amounts are quoted in U.S. dollars (“$”) and all cash cost information is net of silver by‐product credits.

Lundin Gold President and Chief Executive Officer, Ron Hochstein, remarked that “the Feasibility Study provides a solid basis to enable Fruta del Norte to advance immediately into development, ultimately becoming  a  landmark,  high  quality  and  profitable  mining  operation,  adding  great  value  to  the Company,  its  shareholders  and  the  people  of  Ecuador.    With  the  support  of  the  Government  of Ecuador, we look forward to building a historic high grade gold mine in Ecuador.”

“The Feasibility Study results present a unique opportunity for the Company and its shareholders”, remarked Lundin Gold Chairman, Lukas Lundin.  “The results confirm our expectations for Fruta del Norte,  which  is  one  of  the  world’s  largest  undeveloped  gold  deposits,  validating  the  original commitment of the Board of Directors, management, our investors and Ecuador’s stakeholders to push forward with this exciting project.”

Feasibility Study Highlights 

  • Mineral Reserves totaling 4.82 million ounces of gold and 6.34 million ounces of silver (15.5 million tonnes at 9.67 g/t Au and 12.7 g/t Ag);
  • Average annual gold production of 340,000 ounces at an average life of mine (“LOM”) total cash cost of $553/oz and a LOM all‐in sustaining cash cost (“AISC”) of $623/oz, placing FDN in the lowest cash cost quartile globally;
  • LOM production of approximately 4.4 million ounces of gold and 5.2 million ounces of silver over an initial 13‐year mine life using an average gold recovery of 91.7% and average silver recovery of 81.5%;
  • Estimated Project capital cost, including contingency, of $669 million, net of taxes;
  • Targeted start of construction in mid‐2017;
  • Expected first gold production in first quarter 2020 with first year of full production in 2021;
  • Project economics at a gold price of $1,250/ounce and a silver price of $20/ounce resulted in the following:
Pre‐taxAfter Tax
Net Present Value at a 5% discount rate (NPV ) 5$1,283 million$676 million
Internal Rate of Return (IRR)23.8%15.7%
Capital Payback (yrs)3.74.5

Notes:

1. All figures are reported on a 100% equity project basis valuation.   Capital payback is calculated based on start of production.

2. Economic valuation is presented using a start date of July 1, 2017.

  • The cash flow to be generated over the initial three years, annual average over the first 10 years and LOM are shown in the following table.

Average $M  2020  2021  2022  LOM Yrs 1 – 10

Doré Revenue621211511331,669
Concentrate Revenue1172473142803,631
Total Revenue1793684654145,301
Operating Costs1071511491471,961
Operating Profit722163162673,339
Taxes & Royalties16(6)1659914
Capex139161128975
Changes in Working Capital468116‐
Cash Flow (After Tax)(129)1982791741,449

Note: Numbers may not add due to rounding.

Gold Price Sensitivity 

The Project sensitivity analysis indicated that a $100/oz variation from the base case gold price had the following impact on the Project after tax economics, with silver held at $20/oz.

$1,150 oz AuBase Case $1,250 oz Au$1,350 oz Au
NPV ($M) 5506676844
IRR (%)13.415.717.8
Payback (yrs)5.04.54.2

Further Optimization, Cost Reductions and Project Potential

The Company believes there are potential opportunities to further improve the economics of the FDN Project through:

  • Review of the mine plan to potentially improve the production ramp‐up and optimization of the mining methods to increase the use of transverse‐long‐hole stoping (“TS”) over the higher cost, lower productivity drift and fill (“D&F”) methods;
  • Further  metallurgical  testwork  to  increase  the  ratio  of  doré  versus  gold  in  concentrate produced through gravity concentration of flotation concentrate to recover additional free gold;
  • Evaluation of aggregate supply for the Project construction and supply of aggregate for backfill. Currently the Project is relying on a quarry operation to be developed on site.  Further analysis of alternative sources needs to be completed which could result in lower capital and operating costs;
  • Evaluation of owner self‐perform construction, which could result in capital cost savings versus the traditional Engineering, Procurement and Construction Management approach that was used for the FS.  The Company will also study other potential ways to reduce the capital cost; and
  • Potential  extension  of  LOM,  perhaps  materially,  in  two  ways:  (i)  through  the  inclusion  of significant additional Mineral Resources not included in the initial mine plan; and (ii) through the  identification  of  mineralization  as  a  result  of  on‐going  and  future  exploration  on  the Company’s concessions which could support the conversion of Mineral Resources to Mineral Reserves.

Benefits to Ecuador

The FS confirms that FDN will provide significant benefit to Ecuador at the local, provincial and national levels.  Some of the direct benefits include:

  • During construction direct employment, including employees of the Company and contractors is estimated to peak at approximately 2,000;
  • During operations the estimated employment is approximately 900, including employees of the Company and contractors.  This does not take into account the numerous indirect jobs created with suppliers, services, etc. for the mine operations;
  • Improvement of local and regional infrastructure;
  • Continuation of existing community investment programs, small business development and support of cultural development; and
  • Based on a gold price of $1,250 per ounce, the Project is anticipated to generate payments to the Government in the form of royalties, taxes and profit sharing of approximately $928 million over the LOM.

Feasibility Study Details

Mineral Resources 

Mineral Resources for the FDN deposit were estimated using drill hole data available to December 31, 2015 as shown in Tables 1 and 2 at a cutoff grade of 3.5 g/t Au.  The Mineral Resources are contained within three main geological domains; Xh_Vn, Xh_Ip, and M_South.  The Xh_Vn domain represents 85% of the tonnage classified within the Indicated Mineral Resource category.  It also has the highest average gold grade compared to the other two domains.  More than half the tonnage in Xp_Ip is classified into the Indicated Mineral Resource category.  All of M_South domain is classified as Inferred Mineral Resources.

Table 1 – Mineral Resources, inclusive of Mineral Reserves as at December 31, 2015 

CategoryTonnage (M t)Grade (g/t Au)Contained Metal (M oz Au)Grade (g/t Ag)Contained Metal (M oz Ag)
Indicated23.89.617.3512.99.89
Inferred11.65.692.1310.84.05

Table 2 – Mineral Resources by Domain as at December 31, 2015 

CategoryTonnage (Mt)Grade (g/t Au)Contained Metal (M oz Au)Grade (g/t Ag)Contained Metal (M oz Ag)
Indicated
Xh Vn _20.29.946.4413.08.46
Xp Ip _3.67.700.9112.31.43
Total Indicated23.89.617.3512.99.89
Inferred
Xh Vn _3.05.670.556.00.58
Xp Ip _2.36.480.4910.50.79
M South6.35.411.0913.32.68
Total Inferred11.65.692.1310.84.05

Notes:

1. The Qualified Person for the estimate is David Ross, P.Geo., an employee of Roscoe Postle and Associates (“RPA”).  The estimate has an effective date of December 31, 2015.

2. Mineral  Resources  are  reported  inclusive  of  those  Mineral  Resources  that  were  converted  to  Mineral Reserves; Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3. Mineral Resources are reported at a cut‐off grade of 3.5 g/t Au; which was calculated using a long‐term gold price of $1,500/oz.

4. Mineral Resources are constrained within underground mineable shapes that assume a minimum thickness of 2 m; metallurgical recovery of 94%; total operating costs of $145/t milled (mining cost of $60/t milled; process  costs  of  $35/t  milled;  G&A  costs  of  $15/t  milled;  surface  infrastructure  costs  of  $28/t  milled; concentrate transport and treatment costs of $7/t milled); royalties of $71/oz and selling costs of $65/oz.

5. Numbers may not add due to rounding.

Mineral Reserves and Mining 

The estimated Mineral Reserves, presented by mining method, are shown in the following table.

Table 3 – Probable Mineral Reserves as at April 30, 2016 

Material SourceTonnes (kt)Au Grade (g/t)Contained Metal (koz Au)Ag Grade (g/t)Contained Metal (koz Ag)
Transverse Long Hole Stope8,4048.972,42310.42,813
Drift & Fill5,53311.151,98416.93,003
Development >4.7 g/t Au1,1589.7036111.6434
Development >2.7 g/t Au3943.72477.494
Total15,4909.674,81612.76,344

Notes:

1. The Qualified Person for the Mineral Reserve estimate is Alejandro Sepulveda, RM CMC an NCL employee.

2. Mineral Reserves have an effective date of April 30, 2016.  All Mineral Reserves in this table are Probable Mineral Reserves.  No Proven Mineral Reserves were estimated.

3. Mineral Reserves were estimated using a $1,250/oz gold price.  Mining cost assumptions for transverse stoping (TS) $61.0/t; mining costs for drift‐and‐fill (D&F) stoping $80/t.  Other costs and factors common to both mining methods were process and other costs $75.8/t, dilution factor 10%, concentrate transport and treatment charges of $6.7/t. A royalty of $71.1/oz/t Au and a gold metallurgical recovery of 93.9% was assumed.

4. Gold cutoff grades were 4.7 g/t for TS and 5.3 g/t (elevated to 6.8 g/t) for the D&F.

5. Silver was not used in the estimation of cutoff grades but is recovered and contributes to the revenue stream. The average silver metallurgical recovery is 81.6%.  The silver price assumption was $20/oz.

6. Tonnages are rounded to the nearest 1,000 t, gold grades are rounded to two decimal places, and silver grades are rounded to one decimal place. Tonnage and grade measurements are in metric units; contained gold and silver are reported as thousands of troy ounces.

7. Rounding as required by reporting guidelines may result in summation differences.

Twin declines will be constructed, and will use a spiral to gain depth to maximize the distance from the surface, so that a vertical distance of approximately 155 m below the Machinaza River can be obtained. The  mine  ramp  will  be  located  central  to,  and  will  be  approximately  50  m  offset  from,  the  main workings to the east of the deposit.  The ramp configuration will enable haulage trucks to achieve higher average haul speeds and maintain safety standards.  The ramp will be developed nominally at a 15% gradient.

Levels will be developed to access the strike extents of the deposit and connect the development to the return air raise (RAR in the north) and fresh air raise (FAR in the south) in order to establish flow‐ through ventilation.

Stope cross‐cuts are required to access sill development from the haulage drifts, as well as connecting sill development within a given stope line separated by waste.  Development will be centrally located within a given stope.  The top development in a stope will initially serve as the drill horizon for the stope below, and then as the mucking horizon for the stope above.  The bottom development in a stope will serve as the mucking horizon for the stope above.

Computerized  mine  planning  and  scheduling  techniques  were  employed  for  the  planning  and optimization of the underground mine.  DESWIK and other mine design computer software packages were used extensively.  In the good‐fair geotechnical domains a TS size of 20 m long x 12 m wide x 25 m high was designed.  In the more challenging geotechnical zones D&F with 4 m wide x 4 m high flat back drives was designed.  Production levels will have a 25 m spacing for TS and 20 m spacing for D&F. There are a total of 15 working levels.  The TS stopes will be mainly backfilled using paste backfill while the D&F stopes will be backfilled using cemented rock fill.

Process 

The Fruta del Norte ore contains gold in the following forms:

  • Fine free gold;
  • Coarse free gold;
  • Gold contained in sulphides (refractory); and
  • Gold contained in other forms (silicates etc.).

FDN ore will be processed using a gravity, flotation and leaching (“GFL”) flow sheet.  The GFL process is best placed for recovery of the FDN gold because of the manner in which the gold is contained in the ore.  Following a conventional SAG/ball mill grinding circuit, the gravity circuit will recover the coarse free gold, and small amounts of fine free gold and gold contained in sulphides.  Following grinding and gravity, the flotation circuit is capable of recovering the gold associated with sulphides (pyrite).  The flotation tailings will be treated in a CIL circuit that will recover the fine gold.  The final tailings will be either filtered and sent to the mine as paste back fill or deposited in a conventional tailings storage facility.

Over the life of the mine, approximately 70% of the gold will be produced in concentrate and the remainder in doré.  The silver production is approximately 82% in concentrate and 18% in doré.  The concentrate  is  anticipated  to  have  an  average  gold  grade  of  149.3  g/t  and  will  be  a  marketable concentrate  with  no  significant  penalty  elements.    The  doré  is  anticipated  to  contain  above  98% precious metals.  The precious metals portion is expected to contain approximately 60% gold and 40% silver.

Capital & Operating Costs 

The initial capital cost is estimated to be $669 million.  This capital cost was estimated under the assumption that any expenditures by the Company prior to the start of construction on July 1, 2017 in the FS are a sunk cost and are not included the estimate shown in Table 4.  The sustaining capital is estimated to be $263 million and closure costs are projected to be $29 million.

Table 4 – Capital Cost Summary 

Reclamation &  Capital Items ($M)  Initial Capital  Sustaining Capital  Closure 

Underground Mine  120  187 Ore Handling  8

Process Plant742
Tailings / Reclaim Water Facilities3168
On‐Site Infrastructure1226

Off‐Site Infrastructure  71 Mine Closure  29

Sub‐Total ‐ Direct Costs  426 

Indirect Costs  126 Owners Costs  49 Contingency  68

Total  669  263  29 

Note: Numbers may not add due to rounding.

The initial capital cost estimate does not include taxes estimated at $91 million.  Approximately $78 million  of  the  taxes  will  be  recovered  once  production  begins.    The  financial  model  assumes  an additional $15 million in employee severance allowance to be paid between 2031 and 2033.  A total of $430 million in sunk costs through June 30, 2017 has also been assumed, which includes costs incurred by Lundin Gold and previous owners.

The LOM operating cost estimate is $118/t of ore.  The operating costs were estimated based on process design criteria, equipment lease rates (if applicable), labor, reagents, power, fuel, explosives, maintenance and other miscellaneous costs.  All costs are in Q1 2016 dollars.  Table 5 shows that the mining costs are the largest component of the overall operating cost, followed by process, G&A and surface infrastructure.

Table 5 – LOM Operating Cost by Area  Operating Cost Area  ($/t) 

Mining  60 Process  34 Surface Infrastructure  9 G&A  15

Total  118 

Table 6 – LOM All in Sustaining Cash Cost ($/oz Au) 

Cash Cost Area  ($/oz Au) 

On site operating cost  422 Treatment & Refining charges  78 Royalties & production taxes  75 By‐product silver credit  (22)

Cash Cost  553 

Sustaining Capital  61 Closure cost  10

AISC per oz  623 

Note: Numbers may not add due to rounding.

Infrastructure 

The planned access to the FDN site will be from the nearby community of Los Encuentros, where the Company has a local office.  The new access road will be 22 km long, a portion of which will benefit public traffic.

The power requirements are expected to be met by a short extension to the regional high voltage transmission network.  A single circuit 230 kV dedicated transmission line, 11 km long, will be built extending from the El Pindal substation, to feed the Project.

Social & Environmental 

In January 2013, FDN applied for and was granted an Environmental License for the mine, following submission of an Environmental Impact Assessment (“EIA”).  The changing footprint due to the new Feasibility Study and the implementation of the beneficiation phase (process plant and associated facilities) requires an amended EIA and likewise a revision to the existing Environmental License.

The  Terms  of  Reference  for  the  amended  EIA  were  approved  in  late‐April,  which  allowed  for  the immediate submission of the draft amended EIA to the Environmental Ministry.  The Ministry had previously unofficially commented on the draft amended EIA and its observations were reviewed and resolved.  In conjunction with the Ministry, the public participation process has begun and will take approximately  60  days.    The  EIA  schedule  indicates  that  formal  approval  of  the  EIA  and  the Environmental License are expected to be issued early in fourth quarter 2016.

The  two  water  permits  required  for  project  development  have  been  submitted  to  the  relevant authorities for review and approval.

Project Milestones 

  • Submittal of Phase Change Application for La Zarza concession, which hosts the Project, in June, 2016;
  • Approval of Phase Change Application expected prior to the end of August, 2016;
  • Start of basic engineering and Early Works program in third quarter 2016;
  • Receipt of Environmental License and water permits in fourth quarter 2016;
  • Signing of Exploitation Agreement and payment of $25.0 million advance royalty payment by January, 2017;
  • Mobilization of portal and mine contractors in second quarter 2017;
  • Project financing in place by mid‐2017;
  • Start of massive earthworks to prepare site in fourth quarter 2017;
  • Start of construction of process plant in first quarter 2018; and,
  • Expected first gold production in the first half of 2020 with first year of full production in 2021.

Next Steps 

The  next  phase  of  the  FDN  Project  is  Basic  Engineering  and  an  Early  Works  program.    The  main objectives of the Early Works programs are to provide the infrastructure, services and facilities to support commencement of the mine twin decline construction and to advance the Project in a fast tracked  manner.    Basic  engineering  will  focus  on  completing  optimizations  and  remaining  field investigations and other activities to support an efficient project start.  These programs are planned to start in the third quarter 2016 and are anticipated to be completed by the end of the second quarter 2017.

Technical Information

The FDN Technical Report summarizing the results of the FS is being prepared in accordance with NI 43‐101 and will be filed under the Company’s profile on SEDAR within 45 days of this press release. The Qualified Persons (QPs) for the FDN Technical Report will include:

  • Amec Foster Wheeler:  Ignacy (Tony) Lipiec, P.Eng., Juleen Brown, MAusIMM CP, Simon Allard, P.Eng., Charles Masala, P.Eng. and Stella Searston, RM SME
  • Klohn Crippen Berger:  Bryan D. Watts, P.Eng.
  • MM Consultores:  Anthony Maycock, P.Eng.
  • NCL:  Alejandro Sepulveda, RM CMC
  • RPA:  David Ross, P.Geo.

In this news release, the QP for the Mineral Resource estimate is David Ross, P.Geo., an RPA employee, and the QP for the Mineral Reserve estimate is Alejandro Sepulveda, RM CMC., an employee of NCL.

This press release has been reviewed and approved by Anthony George, P. Eng., a mining engineer and the  Company’s  Vice‐President  Project  Development,  and  Nicholas  Teasdale,  MAusIMM  CP(Geo), Lundin Gold's Vice President, Exploration, who are both QPs under NI 43‐101.

Information on sample preparation, analyses and security and data verification is contained in the technical report on the Mineral Resource Estimate, Fruta Del Norte Project, Ecuador, prepared by RPA for  Fortress  Minerals  Corp.  (now  Lundin  Gold),  dated  October  21,  2014  and  filed  on  SEDAR  at www.sedar.com, and will be included in the FDN Technical Report to be filed on SEDAR within the next 45 days.

For information with respect to the key assumptions, parameters and risks associated with the results of the FS for the Project, the Mineral Resource and Mineral Reserve estimates included therein and other technical information, please refer to the FDN Technical Report to be filed on SEDAR within the next 45 days.

Feasibility Study Conference Call 

A conference call will be held tomorrow, Tuesday, June 7, 2016 at 10:00 a.m. Eastern or 16:00 CET to discuss the Feasibility Study.  Please call in 10 minutes before the conference call starts and stay on the line (an operator will be available to assist you).

Dial‐In Numbers:

Toll‐Free North America:  +1‐866‐393‐4306 North America:   +1‐734‐385‐2616 Sweden:  +46 (0) 8‐5661‐9361

Conference ID:  Lundin Gold 24888612

To view the live webcast presentation, please log on using this direct link:

http://www.investorcalendar.com/IC/CEPage.asp?ID=175062

The presentation slideshow will also be available in PDF format for download from the Lundin Gold website www.lundingold.com before the conference call.

A replay of the telephone conference will be available after the completion of the conference call until June 14, 2016.

Replay number (Toll Free North America):  +1‐855‐859‐2056 Replay number (International):    +1‐404‐537‐3406

The pass code for the replay is: 24888612

About the Company  

Lundin Gold Inc. owns the Fruta del Norte (”FDN”) gold project located in southeast Ecuador.  FDN is one  of  the  largest  and  highest  grade  undeveloped  gold  projects  in  the  world.    The  Company  is advancing FDN in order to realize the significant potential of this asset.

The Company believes that the value created will not only greatly benefit shareholders, but also the Government  and  people  of  Ecuador  who  are  the  Company's  most  important  stakeholders  in  this project. Lundin Gold views its commitment to corporate social responsibility as a strategic advantage that enables it both to access and effectively manage business opportunities in increasingly complex environments.  Lundin Gold is committed to addressing the challenge of sustainability ‐ delivering value to  its  shareholders,  while  simultaneously  providing  economic  and  social  benefits  to  impacted communities and minimizing its environmental footprint.

Additional Information 

The information in this release is subject to the disclosure requirements of Lundin Gold under the Swedish Securities Market Act and/or the Swedish Financial Instruments Trading Act. This information was publicly communicated on June 6, 2016 at 2:00 p.m. Pacific Time.

For more information, please contact 

Lundin Gold Inc.

Ron F. Hochstein President and CEO +593‐2‐299‐6400 +1‐604‐806‐3589

Lundin Gold Inc.

Sophia Shane Corporate Development +1‐604‐689‐7842 [email protected] www.lundingold.com

Forward‐Looking Statements

This  press  release  contains  or  refers  to  forward‐looking  information  under  Canadian  securities legislation, including statements regarding the results of the feasibility study, including, but not limited to, gold price and exchange rate assumptions, cash flow forecasts, projected capital and operating costs, metal or mineral recoveries, mine life and production rates; the Company’s potential plans and operating performance; the estimation of the tonnage, grades and content of deposits, and the extent of the resource and reserves estimates; potential production from and viability of the Company’s properties; estimates of future production and operating costs; estimates of permitting submissions and timing; the timing and receipt of necessary permits and project approvals for future operations; access to project funding, exploration results, and expected filing of the FDN Technical Report, and is based on current expectations that involve a number of business risks and uncertainties. Forward‐ looking statements are subject to significant risks and uncertainties, and other factors that could cause actual results to differ materially from expected results. Readers should not place undue reliance on forward‐looking statements.

Factors that could cause actual results to differ materially from any forward‐looking statement include, but are not limited to, capital and operating costs varying significantly from estimates, metallurgical test results not being representative, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, political risks, uncertainties relating to the availability and costs of financing needed in the future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, delays in the development of projects and the other risks involved in the mineral exploration and development industry. The forward‐looking statements contained in this press release are made as of the date hereof and the Company assumes no responsibility to update them or revise them to reflect new events or circumstances other than as required by law.