Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LUCA.V ·

Tahuehueto Pre-Production Update

Production Results

Altaley Mining Corporation

1000 – 1111 Melville St.

Vancouver, BC, V6E 3V6

www.altaleymining.com

Page 1

Altaley Mining Corporation

TAHUEHUETO PRE-PRODUCTION UPDATE

AVERAGE RECOVERIES SINCE SEPT 1, 2022 - GOLD 89.9% AND SILVER 83.2%

VANCOUVER, BRITISH COLUMBIA – January 09, 2023

Altaley Mining Corporation (the “ Company” or “Altaley”) is pleased to provide the following update on

its pre-production efforts during mill commissioning at its Tahuehueto Gold Mine Project.

Tahuehueto is currently operating one ball mill in a commissioning phase, as part of the initial 500tpd

project, producing precious metals- rich, commercial grade lead and zinc concentrate s. All the

associated production systems are operating satisfactorily, and pre -production will continue to

generate revenue whilst the remaining definitive operations systems are completed.

Sept. 2022 to Dec. 2022 – Lead and Zinc Concentrate Production

During September and October 2022 approximately 11,259 tonnes of mill feed was provided by a

temporary crushing system, whilst the definitive crusher circuit was being completed. During this

period throughput was constrained by the non-ideal feed sizing from these temporary systems to the

mill, but this was resolved in late October with the commissioning of the definitive crushing system.

The current installed comminution capacity is 350 tpd, and s ince crusher commissioning the mill has

processed approximately 18,341 tonnes of ore at an average of 297 tonnes per day over 62 operating

days. The nameplate 500 tpd installed comminution capacity will be achieved by the installation of

closed-circuit cyclones , and this is expected to be completed before end Q1, 2023 , subject to a

successful outcome from the forthcoming rights offering.

Recoveries

Excellent precious metal recoveries have been achieved since Sept 1, averaging 89.95% gold and 83.23%

silver, with a peak daily recovery of gold at 97.52% and silver 92.33%. Over the same period, average base

metal recoveries of 76.68% lead report ing to the lead concentrate and 54.31% zinc report ing to z inc

concentrate were also achieved.

CONCENTRATE PRODUCTION AND AVERAGE GRADES

(Sep 1st to Dec 31st, 2022)

Lead Concentrate - 882 Tonnes

Lead Gold Silver

Grades 26.31% 46.92 g/t 642.86 g/t

Recoveries 76.68% 76.72% 68.11%

Zinc Concentrate - 878 Tonnes

Zinc Gold Silver

Grades 47.51% 7.50 g/t 145.14 g/t

Recoveries 54.31% 13.23% 15.12%

News Release

Page 2

Recoveries and concentrate grades continue to improve, and in December exceed ed expectations ,

partly as a result of the mining of fresh and high -grade ores from underground. December 2022

recoveries and grades for lead concentrates were 84.23% (grade 29.22% Pb), gold 81.32% (grade 55.74

g/t Au) and silver 73.94% (grade 693.20 g/t Ag) respectively. Similarly for zinc concentrates; zinc 6 5.28%

(grade 51.30% Zn), gold 10.62% (grade 5.96 g/t), silver 10.85% (grade 77.91 g/t Ag).

CONCENTRATE PRODUCTION AND AVERAGE GRADES (December 2022)

Lead Concentrate - 223 Tonnes

Lead Gold Silver

Grades 29.22% 55.74 g/t 693.20 g/t

Recoveries 84.23% 81.32% 73.94%

Zinc Concentrate - 287 Tonnes

Zinc Gold Silver

Grades 51.30% 5.96 g/t 77.91 g/t

Recoveries 65.28% 10.62% 10.85%

Mike Struthers, CEO commented : “We have been very pleased with the progressive

improvements in the pre-production plant performance at Tahuehueto, thanks largely to the team on

site and helped by the mining of higher-grade ores from the Creston vein. Early pre -production was

largely from stockpiled material, and some of this was partially oxidized which impacted on the plant

performance. However, the fresh ores are performing well, in line with expectations from metallurgical

testwork. This gives us confidence in future plant performance. Some initial challenges with zinc

suppression in the lead circuit were resolved, so we are now producing zinc concentrates with grades

above the minimum commercial specification. The precious metals grades in our lead concentrates

are also especially pleasing with, for example, an average of 55.74 g/t Au and 693.2 g/t Ag in December.

I look forward to providing further updates as we finalize Tahuehueto construction.”

Debt Settlement

The Company has also entered into a debt settlement agreement with an arms’ length mining

contractor (the “Creditor”) to settle CDN$1,176,297 which is owing to the Credit or as a result of

underground mine development work. The Company and the Creditor have agreed that the issuance

to the Creditor of 735,186 common shares of the Company at a deemed price of CDN$1.60 per common

share will extinguish and settle the debt. The completion of the debt settlement and issuance of the

common shares is subject to TSXV approval. All shares issued in connection with the debt settlement

will be subject to a hold period of four months and one day from the date of issuance.

The Company is pleased to have this vote of confidence , with the settlement being made at a

significant premium to the market, from such a reputable mining contractor.

News Release

Page 3

About Altaley Mining Corporation

Altaley Mining Corporation is a Canadian based mining company with two 100% owned Mexican gold,

silver, and base metal mining projects.

Altaley’s Tahuehueto Gold Mine Project is in north-western Durango State, Mexico where construction

of an initial 500 tonnes pe r day (“ tpd”) operation is well advanced. The second stage, the 1000 tpd

expansion project, will follow. The operation is generating gold, silver, lead, and zinc in concentrates.

Campo Morado is an operating polymetallic base and precious metals mine currently producing at an

average of 2,400 tpd and is currently estimated to be Mexico’s 6th largest zinc producer and is

progressively increasing its copper revenues.

Visit: www.altaleymining.com

On Behalf of the Board of Directors

(signed) Mike Struthers

Mike Struthers,

CEO and Director

Cautionary Note Regarding Production Decisions and Forward-Looking Statements

It should be noted that Altaley declared commercial production at Campo Morado and elected to initiate construction to go into

production at Tahuehueto prior to completing full feasibility stud ies demonstrating economic and technical viability.

Accordingly, readers should be cautioned that Altaley’s production decisions have been made without comprehensive feasibility

studies of established reserves at Campo Morado and prefeasibility level reserves at Tahuehueto, such that there is greater risk

and uncertainty as to future economic results from the Campo Morado mine and at Tahuehueto mine where reserves are

established to the prefeasibility level of confidence and therefore a higher technical risk of failure than would be the case if full

feasibility studies were completed and relied upon to make production decisions. Altaley has completed a preliminary economic

assessment (“PEA”) mining study on the Campo Morado mine and a prefeasibility study (‘PFS”) at Tahuehueto mine that provides

a conceptual life of mine plan and a preliminary economic analysis based on the previously identified mineral resources (see

News Release dated November 8, 2017, April 4, 2018, and April 25, 2022).

Statements contained in this news release that are not historical facts are "forward -looking information" or "forward -looking

statements" (collectively, "Forward-Looking Information") within the meaning of applicable Canadian securities laws. Forward -

Looking Information includes but is not limited to conditions or financial performance that are based on assumptions about

future economic conditions and courses of action; the timing and costs of future activities on the Company's properties, such as

production rates and increases; success of exploration, development and bulk sample processing activities, and timing for

processing at its own mineral processing facility on the Tahuehueto project site. In certain cases, Forward -Looking Information

can be identified using words and phrases such as "plans," "expects," "scheduled," "estimates," "forecasts," "intends," "anticipates"

or variations of such words and phrases. In preparing the Forward -Looking Information in this news release, the Company has

applied several material assumptions, including, but not limited to, that the current exploration, development, environmental

and other objectives concerning the Campo Morado Mine and the Tahuehueto Project can be achieved: the continuity of the

price of gold and other metals, economic and political conditions, and operations. Forward-Looking Information involves known

and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the

Company to be materially different from any future results, performance or achievements expressed or implied by the Forward-

Looking Information. There can be no assurance that Forward -Looking Information will prove to be accurate, as actual results

and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue

reliance on Forward-Looking Information. Except as required by law, the Company does not assume any obligation to release

publicly any revisions to Forward-Looking Information contained in this news release to reflect events or circumstances after the

date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

News Release

Page 4

For further information about Altaley Mining Corporation, please contact:

Glen Sandwell

Corporate Communications Manager

[email protected]

Tel: +1 (604) 684-8071