Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LUCA.V ·

Shares Issued: 130,061,745 Page 1 of 4 Telson Issues Tahuehueto Q1 2018 Preproduction Results for Mining, Concentrate Production & Metallurgical Balances Q1 2018 Combined Estimated Cash Sale Value of Produced Concentrates from Tahuehueto and

Metallurgy & Processing

Telson Resources Inc.

TSX.V: TSN OTCBB: SOHFF

Frankfurt: TSGN

Shares Issued: 130,061,745

Page 1 of 4

Telson Issues Tahuehueto Q1 2018 Preproduction Results for Mining, Concentrate Production &

Metallurgical Balances

Q1 2018 Combined Estimated Cash Sale Value of Produced Concentrates from Tahuehueto and

Campo Morado total US $10.7 million.

Vancouver, British Columbia, May 0 3, 2018

Highlights:

• Tahuehueto Toll Milling processed 9,503 tonnes of ore during first three months 2018, “Q1”,

• Average Head Grade of ore milled in Q1 2018 was 5.44 g/t gold, 61.59 g/t silver, 4.54% zinc, 2.25% lead.

• Average payable recoveries of ore processed in Q1 2018 – 79.4% gold, 85.7% silver, 84.4% lead, 76.4%

zinc.

• Produced 360.29 tonnes of lead concentrate and 712.71 tonnes of zinc concentrate in Q1 2018

• Shipped and invoiced for sale 348 tonnes lead and 548 tonnes zinc concentrates during Q1 with

estimated unit value of US $5,825 per tonne for lead concentrate and US $1,320 for Zinc concentrate

as calculated under Offtake sale terms with Trafigura. (see note 1)

• Average grade of Q1 lead concentrate - 50.18% Pb, 99.25 g/t Au, 1,185 g/t Ag, 12.19 % Zn.

• Average grade of Q1 zinc concentrate – 46.28% Zn, 7.41 g/t Au, 105 g/t Ag, 0.93% Pb.

• Estimated total cash sale value of Tahuehueto concentrates produced during Q1 - US$3,039,487

Telson Mining Corporation ("Telson" or the "Company") (TSX

Venture – TSN.V) is pleased to announce the results of first

quarter 2018 pre-production toll milling at its 100% own ed

Tahuehueto Mine Development Project located in Durango,

Mexico. Pre-production toll milling from Tahuehueto

processed 9,503 tonnes of ore at the Atocha Mill during the

Q1 2018 for an average of 106 tonnes per day.

Mining and milling daily average preproduction rate reduced

by approximately 20% during Q1 from the previous 2017 preproduction as the Company directed

production equipment from the preproduction mining to commence its Tahuehueto mine construction

Telson Resources Inc.

TSX.V: TSN OTCBB: SOHFF

Frankfurt: TSGN

Shares Issued: 130,061,745

Page 2 of 4

phase. Additional mining equipment has been sourced and purchased and when delivered to the mine

site the Company expects to increase its daily preproduction rate to former levels.

During Q1 2018 toll milling at the Atocha Processing Plant milled approximately 9,503 tonnes of ore. The

average head grade of the total pre-production ore processed was 5.44 g/t gold, 61.59 g/t silver, 4.54%

zinc, 2.25% lead.

Click here for a video of the flotation process at Atocha Mill

This toll milling produced 360.29 tonnes of lead concentrate with average grades of 50.18 % lead, 99.25

g/t gold, 1,185 g/t silver, 12.19 % zinc and 712.71 tonnes of zinc concentrate with average grades of 46.28

% zinc, 7.41 g/t gold, 105 g/t silver, 0.93 % lead.

The estimated total cash sale value of the lead and zinc concentrates produced during Q1 was

approximately US $3,039,487 based upon those concentrates delivered to Trafigura and invoiced by the

Company to date.

Note1: Shipped concentrates are paid at 90% estimated metal content as determined by preliminary assaying, less

deductions upon delivery to Trafigura warehouse in Manzanillo. The estimated 100% cash selling price is subject to

minor changes once final assaying results are agreed to by the Company and Trafigura at which time the final

approximate 10% is paid.

Antonio Berlanga, CEO of Telson, states “Tahuehueto concentrate preproduction continues to impress

Telson’s management, capturing premium sale values with excellent concentrate quality and payable

metal grade with only very minimal penalizing impurities. The Q1 2018 toll milling campaign has, more

or less , duplicated previous preproduction toll milling results obtained during 2017. Payable metal

recoveries for total Q1 2018 preproduction are once again excellent, averaging 79.4% gold, 85.7% silver,

84.4% lead, 76.4% zinc. During the quarter we redirected equipment from mining to mine construction

activities which resulted in the production rate being reduced approximately 20%. We have acquired and

are shipping additional new equipment to the mine site so anticipate increasing our preproduction rates

to previous 2017 averages or better, in the near future. I’d like to point out to our shareholders that

when you combine Q1 preproduction sales from Campo Morado (see News Release dated April 18, 2018)

and Ta huehueto, Telson generated approximately US $10,743,609 or CAD $13,751,819 (using 1.28

exchange rate from US to CAD ) in Q1, 2018 which is very impressive considering we are still in the

development stage. I’d like to thank all our employees for the great progress we have made so far in

2018.”

Readers should be cautioned that cash sales should not be equated with revenues, as until commercial

production is achieved at Tahuehueto, which is not expected until early 2019, once Telson completes

construction of its proposed onsite mineral processing facility, any proceeds from the sale of concentrates are

considered under IFRS to be applied as an offset to development costs and not counted as revenues on Telson’s

Telson Resources Inc.

TSX.V: TSN OTCBB: SOHFF

Frankfurt: TSGN

Shares Issued: 130,061,745

Page 3 of 4

income statement. Furthermore, Telson is not, du ring the pre -production stage, able to disclose the

costs/expenses associated with generating such cash sales or provide guidance on profitability (if any).

Click here for a video of Tahuehueto concentrate leaving the Atocha Mill on it way to Trafigura.

About Telson Mining Corporation

Telson Mining Corporation is a Canadian based junior resource mining company currently in pre-

production at two Mexican gold, silver and base metal mining projects and is advancing both towards

commercial production over the coming months of 2018. At the Campo Morado Mine in Guerrero,

Mexico, Telson has re-commenced mining and processing operations with pre-production from mine

development on a trial basis at an average 1,500 tonnes per day during the recommissioning stage and

intends to advance towards commercial production at a rate of over 2,000 tonnes per day and

thereafter advance towards full capacity of approximately 2,500 tonnes per day during 2018. Telson's

Tahuehueto Project, located in north-western Durango State, Mexico is currently in pre-production

utilizing a toll mill for processing and has entered a construction phase with a timeline to be producing

on site in its own mineral processing plant capable of milling at least 1,000 tonnes per day towards the

end of 2018. Regular metal concentrate delivery and sales are underway from both projects.

Visit: www.telsonmining.com

On behalf of the board of directors

(signed) “Ralph Shearing”

Ralph Shearing, P.Geol, President and Director

Qualified Person

This press release was prepared under the supervision and review of Ralph Shearing, P.Geol., President

and Director of Telson Resources Inc., a Professional Geologist registered in Alberta as a member of the

professional association APEGA, and a Qualified Person as defined by NI 43-101. Data verification by Mr.

Shearing includes personal inspection of the Tahuehueto mine site, reviewing mining facilities, drill core,

underground development and discussing work programs and results with geology and mining

personnel.

Cautionary Note Regarding Production Decisions and Forward-Looking Statements

It should be noted that Telson has commenced pre-production mining at both projects. At Tahuehueto,

Telson is mining reserves supported by a pre -feasibility published early 2017 while at Campo Morado

pre-production mining is proceeding without the benefit of pre -feasibility or feasibility studie s that

outline mineral reserves.

Telson Resources Inc.

TSX.V: TSN OTCBB: SOHFF

Frankfurt: TSGN

Shares Issued: 130,061,745

Page 4 of 4

Statements contained in this news release that are not historical facts are “forward-looking information”

or “forward -looking statements” (collectively, “Forward -Looking Information”) within the meaning of

applicable Canadian securities laws. Forward Looking Informa tion includes, but is not limited to,

disclosure regarding possible events, conditions or financial performance that is based on assumptions

about future economic conditions and courses of action; the timing and costs of future activities on the

Company’s properties, such as production rates and increases; success of exploration, development and

bulk sample processing activities; timing for the restart of continuous mining operations at the Campo

Morado Mine, and timing for processing at its own mineral processing facility on the Tahuehueto project

site. In certain cases, Forward -Looking Information can be identified by the use of words and phrases

such as “plans”, “expects”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or variations of

such words and phrases. In preparing the Forward -Looking Information in this news release, the

Company has applied several material assumptions, including, but not limited to, that the current

exploration, development, environmental and other objectives concerning the Campo Morado Mine and

the Tahuehueto Project can be achieved, the continuity of the price of gold and other metals, economic

and political conditions and operations. Forward -Looking Information involves known and unknown

risks, uncertainties and other factors which may cause the actual results, performance or achievements

of the Company to be materially different from any future results, performance or achievements

expressed or implied by the Forward -Looking Information. There can be no assurance that Forward-

Looking Information will prove to be accurate, as actual results and future events could differ materially

from those anticipated in such statements. Accordingly, readers should not place undue reliance on

Forward-Looking Information. Except as required by law, the Company does not assume any obligation

to release publicly any revisions to Forward-Looking Information contained in this news release to reflect

events or circumstances after the date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of

the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information about Telson Mining Corporation

Glen Sandwell

Corporate Communications Manager

[email protected]

Tel: +1 (604) 684-8071

TSX Venture: TSN

OTCBB: SOHFF

Frankfurt: TSGN (Formerly trading under the symbol SQ82)