Vancouver, B.C., February 18, 2026: Luca Mining Corp. (“Luca” or the “Company”) (TSX-V: LUCA; OTCQX:

LUCMF; Frankfurt: Z68) is pleased to announce that the Company’s board of directors has approved a mill

optimization and expansion study and mine plan update for the Campo Morado mine (the “Campo

Morado Expansion” or “ CME”) to be prepared as a technical report in accordance with National

Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”), expected to be delivered

in the second half of 2026.

Highlights

• Ausenco PTY Ltd. (“Ausenco”), a global leader in metallurgical design, flotation and precious

metals recovery methods, has been selected as the technical third -party engineering consultant

to lead the Campo Morado Expansion

• Ausenco is designing the CME as a two-phase optimization and expansion project:

 Phase 1 will consider a bulk sulphide flotation processing flowsheet with

increased grinding capacity to achieve optimal separation of sulphide minerals

and produce high-quality copper and zinc concentrates, targeting higher recovery

rates of all metals and increased mill throughput rates

 Phase 2 will evaluate the recovery to doré of the gold and silver contained in a

precious metals-rich pyrite concentrate remaining after the Phase 1 optimized

flotation process

• Additional metallurgical test work to support the CME Phase 1 and Phase 2 optimization is

underway at third-party testing facilities and will be released as available

• Alongside the CME mill optimization, a life of mine plan, including the currently unmined high -

grade Reforma and El Rey deposits will be evaluated

• The CME, life of mine plan and Mineral Reserve statement will be delivered in a Technical Report

to be prepared in accordance with NI 43-101, expected to be released in the second half of 2026

• Luca is evaluating the purchase of key long-lead-time items to support the timely delivery of the

CME optimization project

Dan Barnholden, Luca’s CEO and Director, commented, “The initiation of the Campo Morado Expansion is

a significant event for Luca and our shareholders. We are targeting improved metal recoveries, particularly

for precious metals, at what we expect could be a long -lived mining operation with increased production

levels at expanded margins. Given our existing processing facilities and mining operations at Campo

Morado, we anticipate that the CME may be implemented for a capital cost reflective of the brownfield

nature of the project. We are pleased to partner with industry-leading processing and metallurgical

engineers at Ausenco as we advance and derisk this opportunity at Campo Morado.”

Campo Morado Expansion – Phase 1

Phase 1 of the CME is being considered with the goal to achieve greater consistency in operational

performance at the Campo Morado processing facilities, with improved pre-flotation, on-stream analysis

of flotation concentration, and the addition of ultra-fine grinding capacity to achieve a target grind size of

8-10 microns (from current operational levels of a target regrind size of 15 microns).

The Phase 1 flowsheet at the Campo Morado mill is expected to reconfigure the current sequential

flotation of copper and zinc concentrates to a bulk flotation of all sulphides, followed by additional

regrinding to effectively separate sulphide species prior to a sequential flotation process to produce

copper and zinc concentrates. The final tailings from this Phase 1 bulk flotation-regrinding flowsheet are

expected to be primarily a pyrite concentrate containing gold and silver.

The Company anticipates that the additional grinding capacity contemplated under the Phase 1

optimization will allow the current grinding capacity bottlenecks at the operation to be relieved . The

Company hopes that the study will prove that under this proposed flowsheet , overall mill throughput

capacity at Campo Morado could materially increase. Luca and Ausenco are evaluating various proven

grinding technologies in order to achieve targeted grind sizes under the CME, including both Glencore

Technology’s IsaMill and vertical stirred mill options. Given existing grid power and transformer capacity

at Campo Morado, the Company does not expect power costs to be a primary sensitivity under the CME

Phase 1 flowsheet.

Additional metallurgical testwork is ongoing both at Luca’s metallurgical laboratories and at independent

third-party testing facilities to support the CME Phase 1 flowsheet. It is expected that these test results

will be released in the first half of 2026.

Campo Morado Expansion – Phase 2

Following the flotation of high-quality zinc and copper concentrates under the CME Phase 1 optimization,

Ausenco will evaluate if a tailing s product containing high grades of precious metals and consisting

primarily of pyrite-associated gold and silver will be available for further processing.

Under the CME Phase 2, Ausenco will evaluate various conventional methodologies to recover gold and

silver from this high-grade pyrite concentrate to produce a gold-silver doré at the mine. Currently at the

Campo Morado operation, there is no gold leaching capacity and all precious metals produced are

contained in concentrates with no existing doré production.

As a base case, CME Phase 2 will evaluate direct conventional cyanide leaching of th is high-grade pyrite

concentrate. The Phase 2 op timization is being evaluated to include the construction of leach tanks,

counter current decantation filters, and a Merrill-Crowe process to recover gold and silver to doré.

Additional metallurgical testwork to support the CME Phase 2 , including samples from the currently

unmined high-grade Reforma and El Rey deposits at Campo Morado are being evaluated at both Luca’s

metallurgical laboratories and at independent third-party testing facilities. Metallurgical test results will

be released as they become available.

When considering the CME Phase 2 flowsheet, alternate gold recovery methods to direct cyanide leaching,

including Glencore Technology’s Albion process and Pressure Oxidation will also be evaluated under

trade-off analysis scenarios.

Figure 1 – CME Phase 1 and 2 Design Targets

Updated Campo Morado Mine Plan

In parallel with the ongoing metallurgical and engineering studies to advance the CME, Luca is working

with third-party consultants to update the Campo Morado mine plan to include , amongst other items,

updated metal prices, updated ore characterization, optimized metals recovery assumptions, and recent

drilling success at the mine. Luca expects to complete a life of mine plan and Mineral Reserve statement

in a Technical Report to be prepared in accordance with NI 43-101 in the second half of 2026.

As part of the mine plan update, all mineralized deposits at the operation will be evaluated in context of

the current metals price environment and the potential benefits of the CME. In particular, the high-grade

and unmined Reforma and El Rey deposits are expected to be included in the updated mine plan as

Mineral Reserves.

CME Execution Plan

Luca is working with Ausenco to derisk the timeline and execution of the CME optimization project. Efforts

underway to ensure delivery of the project include:

• Ongoing metallurgical testwork at independent metallurgical laboratories, including ALS

Environmental, located in Kamloops, BC

• Advanced procurement of long lead time items , including: Courier 6G SL Elemental Analyzer

(Metso), Jameson cleaner flotation cell, regrind ing mills, flotation cell mechanisms , as well as

various pumps, tanks and filters

• Delivery of the CME optimization study and mine plan

• Establishment of a technical team to execute on the CME timeline and budget

• Luca expects a significant portion of the capital for the CME Phase 1 and 2 could be funded from

cash flow from existing operations ; however, discussions with various capital providers will be

advanced to secure funding when required to execute on the CME

• Although not expected to be a critical path item for the CME, advanced permitting efforts are

underway to support required permit modifications and amendments

Figure 2 – Proposed CME Study Flowsheet

Source: Ausenco PTY Ltd.

Qualified Person

The technical information contained in this news release has been reviewed and approved by Mr. Ramon

Mendoza Reyes, P.Eng., Chief Operating and Technical Officer at Luca Mining. Mr. Mendoza is a Qualified

Person for the Company as defined by NI 43-101.

Richard Whittering, Principal Process Engineer at Ausenco PTY Ltd., is acting as technical lead for Luca’s

third-party independent consultant for the Campo Morado Expansion study. Mr. Whittering is a Qualified

Person as defined by NI 43-101.

About Luca Mining Corp.

Luca Mining Corp. (TSX-V: LUCA, OTCQX: LUCMF, Frankfurt: Z68) is a Canadian mining company with two

wholly owned mines located in the prolific Sierra Madre mineralized belt in Mexico. These mines produce

gold, copper, zinc, silver, and lead and generate strong cash flow. Both mines have considerable

development and resource upside as well as significant exploration potential.

The Company’s Campo Morado Mine hosts VMS-style, polymetallic mineralization within a large land

package comprising 121 square kilometres. It is an underground operation, producing zinc, copper, gold,

silver and lead. The mine is located in Guerrero State.

The Tahuehueto Mine is a large property of over 100 square kilometres in Durango State. The project

hosts epithermal gold and silver vein -style mineralization. Tahuehueto is a newly constructed

underground mining operation producing primarily gold and silver. Luca has successfully commissioned

its mill and is now in commercial production at Tahuehueto.

About Ausenco

Ausenco is a global company redefining what's possible. The team is based out of 21 offices working across

five continents to deliver services worldwide. Combining deep technical expertise with a 30 -year track

record, Ausenco delivers innovative, value-add consulting, studies, project delivery, asset operations and

maintenance solutions to the minerals and metals and industrial sectors (www.ausenco.com).

On Behalf of the Board of Directors

(signed) “Dan Barnholden”

Dan Barnholden, Chief Executive Officer

Contact Information:

Sophia Shane

Director of Investor Relations

[email protected]

+1 604 306 6867

Glen Sandwell

Corporate Communications Manager

[email protected]

For more information, please visit: www.lucamining.com

Cautionary Note Regarding Forward-Looking Statements

Statements contained in this news release that are not historical facts are “forward-looking information”

or “forward -looking statements” (collectively, “Forward -Looking Information”) within the meaning of

applicable Canadian securities laws. Forward Looking Information includes, but is not limited to,

conditions or performance that are based on assumptions about the proposed exploration programs and

its anticipated results; the timing and costs of future activities on the Company ’s properties; success of

exploration and development; anticipated time and results of forthcoming reports on the Campo Morado

mine; capital requirements of the CME; the CME and targets, expectations and results thereof; inclusion

of the Reforma and El Rey deposits in the updated mine plan as Mineral Reserves; and benefits from

Campo Morado expansion and structure thereof . In certain cases, Forward -Looking Information can be

identified using words and phrases such as “plans”, expects ”, “scheduled”, “estimates”, “forecasts”,

“intends”, “anticipates” or variations of such words and phrases. In preparing the Forward -Looking

Information in this news release, the Company has applied several material assumptions, including, but

not limited to, that the Company will be able to raise additional capital as ne cessary; the current

exploration, development, environmental and other objectives concerning the Campo Morado mine can

be achieved; that consistent and sustainable mill feed at Campo Morado mine will be achieved; the CME

will yield anticipated results; the continuity of the price of gold and other metals and economic and

political conditions. Forward-Looking Information involves known and unknown risks, uncertainties and

other factors which may cause the actual results, performance, or achievements of th e Company to be

materially different from any future results, performance or achievements expressed or implied by the

Forward-Looking Information. There can be no assurance that Forward-Looking Information will prove to

be accurate, as actual results and future events could differ materially from those anticipated in such

statements. Accordingly, readers should not place undue reliance on Forward -Looking Information.

Except as required by law, the Company does not assume any obligation to release publicly any revisions

to Forward-Looking Information contained in this news release to reflect events or circumstances after

the date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.