Altaley Mining Closes Non-Brokered Private Placement and Reports on Q1 2022 Financials

Financings Financials

Altaley Mining Corporation

1000 – 1111 Melville St.

Vancouver, BC, V6E 3V6

www.altaleymining.com

1

Altaley Mining Closes Non-Brokered Private Placement

and Reports on Q1 2022 Financials

VANCOUVER, BRITISH COLUMBIA – MAY 31, 2022

Altaley Mining Corporation (TSXV: ATLY) (OTCQX: ATLYF) (FSE: TSGA) (the " Company" or

"Altaley") is pleased to announce that it has closed the final tranche (the “Final Tranche”) of its

non-brokered private placement previously announced on March 17, 2022 and has released

its Q1 2022 financial results.

Private Placement

The Company has closed a Final Tranche and issued 2,169,418 units (each, a " Unit") at a price

of $0.35 per Unit for gross proceeds of $759,296.30. In total, the Company issued 14,285,714

Units at a price of $0.35 per Unit for aggregate gross proceeds of $5,000 ,000. Each Unit

consists of one common share (a " Common Share ") and one -half of one common share

purchase warrant (each whole such warrant, a "Warrant"). Each Warrant will entitle the holder

to purchase one additional Common Share of the Company at a price of $0.55 per Common

Share within 24 months from the relevant closing date (the "Closing Date "), s ubject to an

acceleration clause. If, at any time between the Closing Date and the expiry date, the closing

price of the C ompany's common shares on the TSX Ve nture Exchange (the ” Exchange”)

exceeds $0.75 for 15 consecutive trading days, then the C ompany will earn the right, by

providing notice to the warrant holder via news release or written notice, to accelerate the

expiry date of the warrants to 4 p.m. (Vancouver time) on that date which is 30 days from the

date of the acceleration notice. See April 21, 2022, news release regarding first tranche closing.

All securities issued under the Private Placement are subject to a hold period expiring four

months and one day after the Closing Date. Total issued and outstanding Common Shares of

the Company after completion of the Private Placement is 277,894,422.

In accordance with applicable securities laws and the policies of the Exchange, the Company

will issue 42,000 Units of the Company as a finder’s fee to certain finders in connection with

the Final Tranche.

A portion of the F inal T ranche closing was purchased by an affiliate of a director of the

Company. Accordingly, this participation in the Private Placement is considered a related -

party transaction as such term is defined under Multilateral Instrument 61 -101 (Protection of

Minority Security Holders in Special Transactions). The Company is relying on exemptions

from the formal valuation and minority shareholder approval requirements provided under

MI 61-101 (sections 5.5(b) and 5.7(1)(b) of MI 61 -101) on the basis that the Company is listed on

the Exchange (and has no shares listed on the Toronto Stock Exchange or certain other

Altaley Mining Corporation

2

named exchanges) and the fair market value of the securities distributed to the related party

under the Private Placement was less than $2,500,000. The Private Placement was approved

by the board of directors of the Company, which includes at least one independent director

who is not an employee of the Company, which considered the best interests of the Company

in completing the Private Placement. The Company did not file a material change report

more than 21 days before the expected closing of the insider transactions as the details of the

Private Placement and the participation therein by related parties of the Company were not

settled until shortly prior to closing and the Company wished to close on an expedited basis

for sound business reasons and in a time frame consistent with usual market practices for

transactions of this nature.

The net proceeds from the Units will be used by the Company for working cap ital purposes

related to the ramp -up of mining and milling operations at the Tahuehueto Mine and for

general working capital purposes.

The private placement financing is subject to final Exchange approval

Q1 2022 Financials

During the three months ended Ma rch 31, 2022, Campo Morado p roduced 9,657 tonnes of

zinc concentrate grading an average of 46% zinc, 1.58 g/t gold, 609 g/t silver and sold

approximately 9,781 tonnes of zinc concentrate generating Q1 -2022 revenue from zinc

concentrate of US$ 12.34 million. Additionally, p roduced 2,379 tonnes of lead concentrate

grading an average of 19% lead, 2.37% copper, 4.66 g/t gold, 647 g/t silver and sold 2,626 tonnes

generating Q1-2022 revenue from lead concentrate of US$1.84 million.

Approximately 176,610 tonnes of mineralized material were mined with average grades of

3.59% zinc, 0.91% lead, 103 g/t silver, 0.83 g/t gold achieving recoveries of 70.1% in zinc, 27.7% in

lead, 9.8% in gold, and 27.6% in silver.

An estimated 176,610 tonnes of mineralized material were processed through the processing

plant at a C1 cash cost per lb of US$1.26.

Ralph Shearing states, "Q1 2022 was a difficult quarter at Campo Morado where mechanical

issues resulting in excessive mill downtime combined with lower recoveries, lower mill feed

head grade mineralized material plus increased off taker charges all combined to

substantially reduce operating profit and increase costs during the quarter. The mechanical

issues have been resolved and the mine plan is producing increased grade mill feed with

recoveries of zinc back on track. In addition, the mine started copper concentrate production

during mid-May which we are expecting will add an additional revenue source to the project.

We anticipate a much improved second quarter.”

The following table and subsequent discussion provide a summary of the operating

performance of the Company for the three months ended March 31, 2022, and 2021.

Altaley Mining Corporation

3

TABLE 1

Campo Morado Mine

Production and concentrate sales in Q1 -2022 were negatively affected compared to all

quarters of 2021 as a result of the following;

• lost production days largely related to mechanical issues with the SAG mill reduction

gear box and scheduled maintenance, where a combined 11 days of operation were

lost during the quarter,

• maintenance costs for both plants increased as a result of the above mechanical

issue.

• average head grades and recoveries were lower by the following amounts:

o Gold Head Grade from 1.07 g/T 2021 to 0.82 g/t 2022

o Silver Head Grade from 124.7 g/t 2021 to 102.2 g/t 2022

o Au recoveries from 13% in Zn con and 8% in Pb con to 10% and 6% respectively

o Ag recoveries from 35% in Zn con and 9% in Pb con to 30% and 7% respectively

o Pb recoveries from 29% to 25%

• approximately 75% increase in offtake charges in Q1 2022 vs Q1-2021 (9% increase Q1-

2022 vs Q4-2021) largely related to rollback, treatment, and escalator charges.

The graphics below illustrate changes in costs, treatment charges, and credits between Q1-

2021 and Q1-2022.

Altaley Mining Corporation

4

CHART 1

CHART 2

Altaley Mining Corporation

5

About Altaley Mining Corporation

Altaley Mining Corporation is a Canadian based mining company with two 100% owned

Mexican gold, silver, and base metal mining projects.

Altaley's Tahuehueto mining project is in north -western Durango State, Mexico where

construction has been advanced to near completion on its 1,000 tonne per day processing

facility and related mine infrastructure for production of gold, silver, lead, and zinc in

concentrates at Tahuehueto. The Company began initial pre -production in May 2022 and

ramping up to full production capacity late 2022.

Campo Morado is an operating polymetallic base metal mine with mining and milling

equipment currently pr oducing at an average of 2, 200 tonnes per day and is currently

estimated to be Mexico’s 6th largest zinc producer.

Visit: www.altaleymining.com

On Behalf of the Board of Directors

(signed) “Ralph Shearing”

Ralph Shearing, P. Geol,

CEO, President, and Director

CAUTIONARY NOTE REGARDING PRODUCTION DECISIONS AND FORWARD -LOOKING

STATEMENTS

It should be noted that Altaley declared commercial production at Campo Morado and elected to initiate construction to go into

production at Tahuehueto prior to completing full feasibility stud ies demonstrating economic and technical viability.

Accordingly, readers should be cautioned that Altaley’s production decisions have been made without comprehensive feasibility

studies of established reserves at Campo Morado and prefeasibility level reserves at Tahuehueto, such that there is greater risk

and uncertainty as to future economic results from the Campo Morado mine and at Tahuehueto mine where reserves are

established to the prefeasibility level of confidence and therefore a higher technical risk of failure than w ould be the case if full

feasibility studies were completed and relied upon to make production decisions. Altaley has completed a preliminary economic

assessment (“PEA”) mining study on the Campo Morado mine and a prefeasibility study (‘PFS”) at Tahuehueto mine that provides

a conceptual life of mine plan and a preliminary economic analysis based on the prev iously identified mineral resources (see

News Release dated November 8, 2017, April 4, 2018, and April 25, 2022).

Statements contained in this news release that are not historical facts are "forward -looking information" or "forward -looking

statements" (collectively, "Forward-Looking Information") within the meaning of applicable Canadian securities laws. Forward -

Looking Information includes but is not limited to conditions or financial performance that are based on assumptions about

future economic conditions and courses of action; the timing and costs of future activities on the Company's properties, such as

production rates and increases; success of exploration, development and bulk sample processing activities, and timing for

processing at its own mineral processing facility on the Tahuehueto project site. In certain cases, Forward -Looking Information

can be identified using words and phrases such as "plans," "expects," "scheduled," "estimates," "forecasts," "intends," "anticipates"

or variations of such words and phrases. In preparing the Forward -Looking Information in this news release, the Company has

applied several material assumptions, in cluding, but not limited to, that the current exploration, development, environmental

and other objectives concerning the Campo Morado Mine and the Tahuehueto Project can be achieved: the continuity of the

price of gold and other metals, economic and political conditions, and operations. Forward-Looking Information involves known

and unknown risks, uncertainties and other factors which may cause the actual results, performance, or achievements of the

Company to be materially different from any future results, performance or achievements expressed or implied by the Forward-

Looking Information. There can be no assurance that Forward -Looking Information will prove to be accurate, as actual results

and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue

Altaley Mining Corporation

6

reliance on Forward-Looking Information. Except as required by law, the Company does not assume any obligation to release

publicly any revisions to Forward-Looking Information contained in this news release to reflect events or circumstances after the

date hereof or to reflect the occurrence of unanticipated events.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.