Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LUCA.V ·

Altaley Mining Announces Positive Pre-Feasibility Study & Updated Mineral Reserves/Resources Estimates as its Flagship Tahuehueto Mine Nears Production

Resource Estimates Economic Studies

Altaley Mining Corporation

1000 – 1111 Melville St.

Vancouver, BC, V6E 3V6

www.altaleymining.com

1

Altaley Mining Announces Positive Pre-Feasibility Study &

Updated Mineral Reserves/Resources Estimates as its

Flagship Tahuehueto Mine Nears Production

VANCOUVER, BRITISH COLUMBIA, MARCH 07, 2022

Altaley Mining Corporation ( TSXV:ATLY) ( OTCQX:ATLYF) ( FSE:TSGA) (“ Altaley” or the

“Company”) today announced the results of an updated Pre-Feasibility study (the

“PFS”) for its Tahuehueto Gold Mining Project (the “ Project”) located in Durango,

Mexico. (All currencies within this press release are quoted USD.)

 2022 Prefeasibility Study improves 2017 PFS increasing throughput to 1,000

tonnes per day returning a post-tax NPV of US$110 million at 5% discount rate.

 Total Capital Cost estimate of US $56.9 million with only $6 million capital

remaining to be invested to initiate production at 1,000 tpd. Project

construction over 95% complete with initial pre-production targeted during

March 2022.

 Life of Mine All In Sustaining costs (AISC) estimated at US $844 per gold

equivalent ounce at $1,647.52/ounce Au, $21.64/ounce Ag, $0.92/pound Pb,

$1.14/pound Zn and $3.60/pound Cu)

 Proven & Probable Reserves of 3.58 million tonnes grading 2.55g/t gold, 50.06

g/t silver, 1.92% zinc, 1.11% lead, 0.26% copper.

 10.9-year Life of Mine (LOM) utilizing mostly low-cost bulk underground Sub-

level Open Stoping mining method.

 Significant opportunities exist to expand the Projects Mineral Resources and

Reserves base with near mine and regional exploration. Altaley plans to

aggressively pursue exploration as soon as free cash flows allow or alternative

funding is secured.

“As our Tahuehueto Gold Mine Project construction nears completion we are happy to

disclose results of the projects updated pre-feasibility study which continues to show

Altaley Mining Corporation

2

robust economics.” said Ralph Shearing, CEO & President. “The disclosure of the 2022

PFS economics, updated reserve and resource estimation, along with our anticipated

March startup of pre-production operations at Tahuehueto, are the culmination of

many years of hard work by the Altaley team and as our Tahuehueto mine ramps up

to full production during Q2-Q3 2022, increased cash flow will allow Altaley to

recommence exploration drilling and unlock the ultimate potential of our Tahuehueto

district scale project.”

Pre-Feasibility Study Overview

The Project configuration evaluated in the PFS is a conventional, owner-operated

underground mine, that will utilize contractor mining in a combination sub-level long

hole open stope and cut and fill mining methods. Mill feed will be processed in a 1,000

tonnes per day comminution circuit consisting of primary and secondary crushing, wet

grinding to an initial two-circuit flotation/concentration plant producing precious

metal rich lead and zinc concentrates and subsequently, in second year of operation a

third circuit added to produce copper concentrates.

The PFS was prepared by independent third-party consultants, Resource Development

Associates Inc. (“ RDA”) and integrated updated geological interpretations based on

expanded knowledge of the mineral deposit, geological modeling, an optimized mine

plan and production schedule, additional metallurgical work, a mill currently under

construction and updated cost estimates, all of which de-risk the Project.

The PFS provides information on the optimized Project with higher throughput rates,

updated resource estimate, and capital and operating cost estimates as compared to

the project evaluated in the National Instrument 43-101 – Standards of Disclosure for

Mineral Projects (“NI43-101”) January 2017 Technical Report (the “2017 Report”). The final

version of the NI 43-101 technical report containing the PFS will be filed on SEDAR within

45 days. As a result of the changes to the Project as evaluated in the PFS, including

differences in mineral resource estimation methodology and changes to the economic

parameters applied to the geologic block model (metal selling prices, recovery, CAPEX,

and OPEX), all of which resulted in a change in mineral resources, the Project as

evaluated in the 2017 Report is no longer considered current and the 2017 Report

should therefore not be relied upon by investors.

The engineering design to estimate capital costs used in the PFS are within a 20%

accuracy however, the Company in 2021 elected to proceed with construction of the

project which, as of the date of this this press release, 90% of required construction

capital has been invested in the project, advancing construction past 95% completion

with most capital expenditures completed and therefore capital equipment and

construction costs are known with substantially increased accuracy.

The Company cautions that the PFS is preliminary in nature and is based on technical

and economic assumptions which could be further refined and evaluated in a full

feasibility study. The PFS is based on an updated Project reserve and resource

Altaley Mining Corporation

3

estimate effective as of February 23, 2022. As the Company has elected to bring the

Tahuehueto Mining Project into production without the projects mineral reserves

supported by a full feasibility study, the Company cautions that this could result in a

higher risk of economic or technical failure of the operation that if a full feasibility

study had been prepared demonstrating economic and technical viability. There are

no assurances that the Tahuehueto Mining Project will be found to be economic.

The following is a summary of the material aspects and assumptions of the PFS.

Investors are urged to review the complete NI 43-101 report following its filing on

SEDAR for complete details of the PFS.

Project Location

The Tahuehueto Project is located in the northwest portion of the state of Durango,

Mexico, approximately 250 km northwest of the capital city of Durango. The Project is

located about 25 km north of the Topia polymetallic-silver mine, 48 km northwest of

the La Cienega gold, silver, base metal mine, 85 km southwest of the Guanacevi silver

district, 280 km southeast of the Palmarejo silver and gold mine, and 150 km northwest

of the San Dimas mining district, most notable for the Tayoltita silver and gold mine.

IMAGE 1

Altaley Mining Corporation

4

Summary of Results of the 1,000 Tonnes Per Day PFS

TABLE 1

OPERATING METRICS 2022 PFS

Mill Throughput (tonnes/day) 1,000

Mine Life (years) 10.9

Total Ore Processed (tonnes) 3.55M

Annual Mining Rate (tonnes) 336,000

Development-to-ore ratio (waste:ore) 0.6

Head Grade (average for the LOM)

Pb (%) 1.1

Zn (%) 1.9

Au (g/tonne) 2.58

Ag (g/tonne) 50.5

Cu (%) 0.3

AuEq (g/tonne) 6

Recovery (average for the LOM)

Pb (%) 85

Zn (%) 68

Au (%) 87

Ag (%) 85

Cu (%) 85

Metal Produced (total for the LOM)

Pb (tonnes) 33,911

Zn (tonnes) 65,821

Au (troy ounces) 279,359

Ag (troy ounces) 4,879,980

Cu (tonnes) 8,893

Average Monthly Production – LOM

Pb (tonnes) 263

Zn (tonnes) 510

Au (troy ounces) 2,166

Ag (troy ounces) 37,829

Cu (tonnes) 69

Altaley Mining Corporation

5

TABLE 2

FINANCIAL METRICS 2022 PFS US$

Total Net Smelter Return (Pb, Zn, Au, Ag, Cu) 533.1 $Million

Gold Net Revenue 341.5 $Million

Silver Net Revenue 74.0 $Million

Lead Net Revenue 55.8 $Million

Zinc Net Revenue 48.3 $Million

Copper Net Revenue 13.4 $Million

Pre-tax Net Cash flow 240.9 $Million

Post tax Net Cash Flow 186.3 $Million

Annual Average pre-tax net cash flow 21.4 $Million

Pre-tax net cash flow per tonne of ore 67 $/tonne ore

LOM Total Capital cost – Plant, mine development,

infrastructure, working capital (no contingency) 56.9 $Million

OPEX – Development Mining 1,278.1 $/meter

OPEX – Ore Mining 35.0 $/tonne ore

OPEX – Processing 22 $/tonne ore

OPEX – General &Administrative (G&A) 3.0 $/tonne ore

OPEX - Operating Cost – LOM 69.5 $/tonne ore

All-In Sustaining Cost of Production – LOM 844 $/AuEq oz

Pre-tax Net Present Value (NPV) at 5% discount 152.8 $Million

Post-tax NPV at 5% discount* 110.0 $Million

Post-tax NPV at 10% discount 90.6 $Million

EBIDTA LOM 246.1 $Million

Internal Rate of Return (IRR)** 45 %

Payback Period 2.58 Years

*5% discount considered reasonable due to advanced state of Tahuehueto construction where 90% of

required capital has been invested in the project, advancing construction past 95% completion with

most capital expenditures completed and therefore capital costs are known with substantially

increased accuracy.

**IRR is calculated with approximately $34 million of pre-Jan 2022 expenses on the project. $19 million

of pre-2015 costs of exploration, acquisition and carrying costs have been treated as sunk costs.

Altaley Mining Corporation

6

Sensitivity Analysis

Table 3 below shows the average annual free cash flow and EBIDTA generated by the

Project at various Gold Prices. (US Currency)

TABLE 3

FREE CASH

FLOW EBIDTA

Gold Price

($/Oz)

Average Annual

(LOM)

Average Annual

(LOM)

1,200 $5.9 million $12.3 million

1,500 $10.3 million $19.1 million

1,700 $13.2 million $23.6 million

1,900 $16.2 million $28.1 million

2,100 $19.1 million $32.6 million

Table 4 below shows the after-tax economics at various gold prices. (US Currency)

TABLE 4

Gold Price

($/oz)

After Tax

NPV 0%

($M)

After Tax

NPV 5%

($M)

After Tax

NPV 10%

($M) IRR (%)

Payback

(Years)

1,200 64.1 51.2 41.6 14.8 4.33

1,500 112.2 89.3 72.8 33.1 3.08

1,700 144.3 114.7 93.6 44.2 2.75

1,900 176.3 140.2 114.4 55.2 2.33

2,100 208.4 165.6 135.2 66.1 2.00

Altaley Mining Corporation

7

Capital Costs

Key capital expenditures for initial and sustaining capital requirements are identified

in the following Table 5. (All figures in US$ Millions)

TABLE 5

Initial

investment

up to Feb.

28, 2022

Investment

remaining as at

Feb. 28, 2022 to

generate positive

cash flow*

Investment to

reach

continuous &

sustainable

production **

Sustaining

capital

expenditures

***

Total capital

costs****

Processing facilities 10.29 1.86 0.93 0.13 13.21

Infrastructure

facilities 2.22 2.17 0.85 0.15 5.39

Mine equipment 4.05 0.09 0.78 0.53 5.45

Tailings 0.06 0.83 0.38 1.50 2.77

Mine development 0.48 0.25 0.98 27.18 28.89

Mining rights - - 0.11 1.10 1.21

Subtotal 17.10 5.20 4.03 30.59 56.92

Contingency - - 1.19 3.06 4.25

Total 17.10 5.20 5.22 33.65 61.17

* From Feb 28, 2022 to positive cash flow date

** From reaching positive cash-flow date to January 2023

*** From Jan 2023 to end of mine life

**** Life of mine capital costs and Pre-Jan 2022 capitalized costs

All-in Sustaining Costs

Table 6 highlights the all-in sustaining costs and the all-in cost over the life of the Project.

TABLE 6

Life of Mine

US$/AuEq Oz US$ Million

Operating Costs(1) 734 320.5

Sustaining Capital Expenditures (2) 77 33.65

Corporate G&A 18 8.0

Reclamation 17 7.5

All-In Sustaining Costs (3) (4) 846 369.6

Capital Expenditures 32 13.8

All-In Costs (4) 876 383.4

Rounding of some figures may lead to minor discrepancies in totals.

(1) Includes streaming, penalties, and shipping costs.

(2) Includes all mine development capital expenditures after the first 12 months of production.

(3) Includes initial capital expenditures for the first 12 months of production.

(4) All-In Sustaining Costs and All-In-Costs are non-GAAP measures. See reference to “Non-GAAP” below.

Altaley Mining Corporation

8

Annual Metal Production

CHART 1

CHART 2

-

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032

Ounces

Gold production

Gold

-

200,000

400,000

600,000

800,000

1,000,000

1,200,000

2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032

Ounces

Silver production

Silver