Lucara Provides Karowe Underground Expansion Project Update

Corporate Updates

July 16, 2023 

LUCARA PROVIDES KAROWE UNDERGROUND EXPANSION PROJECT UPDATE  

VANCOUVER, July 16, 2023 /CNW/ ‐ (LUC – TSX, LUC – BSE, LUC – Nasdaq Stockholm)  

Lucara  Diamond  Corp.  (“Lucara”  or  the  “Company”)  provides  an  update  on  the  Karowe  Underground  Expansion 

project (the “UGP”). The Karowe UGP is designed to access the highest value portion of the Karowe orebody, extend 

mine life to at least 2040 and deliver approximately $4 billion in additional revenues using conservative diamond 

price assumptions which are un‐escalated and exclude exceptional stone revenues.   

Management initiated an update to the UGP schedule and budget in response to slower than planned ramp up to 

expected sinking rates, and, to account for time incurred to date, as well as for anticipated future grouting programs.  

Grouting  programs  took  longer  than  anticipated  due  to  a  combination  of  high‐water  volumes  in  the  sandstone 

lithologies between 870 and 752 metres above sea level in depth (144 metres to 262 metres below the shaft collar) 

combined  with  technical  challenges  associated  with  the  transition  to  main  sinking.   The  updated  schedule 

incorporates  a  28%  increase  in  the  duration  of  construction,  extending  the  anticipated  commencement  of 

production from the underground from H2 2026 to H1 2028.  As a result, the revised forecast of costs at completion 

is $683 million, a 25% increase to the May 2022 estimated capital cost of $547 million.   

The  project  remains  technically  and  economically  feasible,  however,  the  impact  of  actual  and  modelled  delays 

changes the revenue profile due to the use of lower‐grade, stockpiled ore for mill feed rather than high‐grade ore 

from  the  underground  as  previously  planned.   Sufficient  surface  stockpiles  of  South,  Centre  and  North  Lobe 

kimberlite  ore  are  available  to  maintain  current,  un‐interrupted  mill  feed  to  the  plant  for  the  duration  of  the 

anticipated delay.   The long‐term outlook for diamond prices, combined with the potential for exceptional stone 

recoveries and the continued strong performance of the open pit could mitigate the modelled impact on project 

cash flows due to the schedule slippage.    

Eira  Thomas,  CEO  commented:  “Lucara  has  made  tremendous  progress  on  the  Karowe  underground  expansion 

project, despite many challenges over the last year as we transitioned into the main sink phase of the underground 

development. Schedule delays due to longer than anticipated grouting activity have impacted the project timeline, 

however the grouting methodology selected has proven to be effective in controlling water inflows.  As we transition 

out of the sandstones in early Q4 2023, we look forward to meeting planned sinking rates. Despite these challenges, 

the project continues to deliver strong economics paying back capital in under three years and adding approximately 

$4 billion in revenues from an extended mine life out to at least 2040, using conservative diamond price assumptions. 

The project also comes at a time when the long‐term outlook for the diamond market is stronger than it has been 

for many years representing an exciting growth opportunity for our shareholders and stakeholders in Botswana.” 

Lucara’s major shareholder remains supportive of the Karowe asset and the long‐term potential of the Karowe UGP.  

Adam Lundin commented: “The Karowe underground mine expansion provides access to the highest value portion 

of the orebody responsible for delivering numerous record‐breaking diamonds in respect of size and value, including 

three diamonds in excess of 1,000 carats.  The project remains highly economic, despite the delays incurred, and as 

Lucara’s largest shareholder, we remain fully supportive of the company.” 

HIGHLIGHTS: 

 While the existence of water‐bearing sandstones layers was anticipated, grouting within the regional Ntane 

and Mosolotane sandstone aquifers has required significantly more volumes of chemical grout.  In addition, 

some  remedial  grouting  in  previously  dry  portions  of  the  sandstone  horizons  has  been  required  in  the 

ventilation shaft.  These factors account for most of the incurred delays.  

 Planned grouting events to the base of the Mosolotane sandstone/mudstone transition are expected to be 

completed early in Q4 2023.  After completion of the current sandstone layer being grouted, one further 

2 

grouting  event  is  planned  in  the  ventilation  shaft  (currently  213  metres  below  collar).   Two  additional 

grouting events are planned within the production shaft (currently 185 metres below collar).  Thereafter, 

further grouting is not anticipated to be required until sinking reaches the granite basement lithologies in 

late 2024.  Grouting in the granite lithologies is expected to be localized, rather than formational in nature. 

Total depth of the final shaft bottoms are 765 metres and 731 metres below surface for the production and 

ventilation shafts, respectively. 

 The project has been operating with an excellent safety record including 1,244 days and > 3.3 million hours 

Lost Time Injury free and a Total Recordable Injury Frequency rate of 0.59. 

 The increase of $136 million in estimated capital to reach project completion is predominantly related to 

increased  schedule  duration  and  related  labour  costs  (approximately  56%  of  total),  and  grouting  costs 

(approximately 20% of total capital increase) which have been funded through contingency. The remaining 

cost increases are related to Owner’s costs, procurement, and indirect project costs.   

 As at June 30, 2023, capital expenditures of $264.5 million had been incurred and capital commitments of 

$369.7 million had been made. 

 The remaining forecast to complete construction of the project as of June 30, 2023 is $419 million including 

unallocated contingency of $49.3 million (12%). 

 Karowe Open Pit and Processing units continue to perform to budget expectations and the planned ore 

feed  for  the  remainder  of  2023  has  transitioned  to  a  South  Lobe  dominant  mill  feed.   As  a  result,  the 

recovery of large high value +100 carats diamonds sourced from the M/PK(S) and EM/PK(S) units is in line 

with resource expectations and previous half‐year recoveries. 

QUALIFIED PERSONS 

This press release has been reviewed and approved by Dr. John Armstrong, Ph.D. P.Geol., Vice‐President, Technical 

Services of the Company and a "Qualified Person" for the purposes of National Instrument 43‐101 and Mr. Gord 

Doerksen P.Eng. of JDS Energy and Mining Inc. an Independent Qualified Person under National Instrument 43‐101.   

Eira Thomas 

President and Chief Executive Officer 

Follow Lucara Diamond on Facebook, Twitter, Instagram, and LinkedIn 

For further information, please contact: 

Investor Relations & Communications 

   +1 604 674 0272| [email protected] 

Sweden  Robert Eriksson, Investor Relations & Public Relations 

   +46 701 112615 | [email protected] 

UK Public Relations   Charles Vivian / Jos Simson, Tavistock 

   +44 778 855 4035  | [email protected] 

ABOUT LUCARA 

Lucara  is  a  leading  independent  producer  of  large  exceptional  quality  Type  IIa  diamonds  from  its  100%  owned 

Karowe Mine in Botswana and owns a 100% interest in Clara Diamond Solutions, a secure, digital sales platform 

positioned to modernize the existing diamond supply chain and ensure diamond provenance from mine to finger.  

The  Company  has  an  experienced  board  and  management  team  with  extensive  diamond  development  and 

operations expertise.  The Company operates transparently and in accordance with international best practices in 

the areas of sustainability, health and safety, environment, and community relations. 

3 

The  information  in  this  release  is  accurate  at  the  time  of  distribution  but  may  be  superseded  or  qualified  by 

subsequent news releases. 

This  information  is  information  that  the  Company  is  obliged  to  make  public  pursuant  to  the  EU  Market  Abuse 

Regulation. The information was submitted for publication, through the agency of the contact persons set out, at 

10:00pm Pacific Time on July 16, 2023. 

CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS  

Certain  of  the  statements  made  herein  contain  certain  “forward‐looking  information”  and  “forward‐looking 

statements” as defined in applicable securities laws. Generally, any statements that express or involve discussions 

with  respect to  predictions, expectations, beliefs, plans, projections,  objectives,  assumptions  or  future  events  or 

performance  and  often  (but  not  always)  using  forward‐looking  terminology  such  as  “expects”,  “is  expected”, 

“anticipates”,  “believes”,  “plans”,  “projects”,  “estimates”,  “budgets”,  “scheduled”,  “forecasts”,  “assumes”, 

“intends”,  “strategy”,  “goals”,  “objectives”,  “potential”,  “possible”  or  variations  thereof  or  stating  that  certain 

actions,  events,  conditions  or  results  “may”,  “could”,  “would”, “should”,  “might”  or “will”  be  taken,  occur  or be 

achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and 

may be forward‐looking statements. 

In  particular,  forward‐looking  information  and  forward‐looking  statements  may  include,  but  are  not  limited  to, 

information or statements with respect to the mine life of the Karowe Mine, anticipated revenues from the Karowe 

UGP,  diamond  prices,  timing  of  revenues  from  the  UGP  and  exiting  stockpiles,  the  timing,  scope  and  cost  of 

additional  grouting  events,  total  forecasted  capital  expenditures  for  the  UGP,  and  the  anticipated  schedule  to 

complete the UGP. 

There can be no assurance that such forward looking statements will prove to be accurate, as the Company's results 

and future events could differ materially from those anticipated in this forward‐looking information as a result of 

the inherent uncertainty in developing underground projects and those factors discussed in or referred to under the 

heading  "Risks  and  Uncertainties"  in  the  Company's  most  recent  Annual  Information  Form  available  at 

http://www.sedar.com, as well as changes in general business and economic conditions, changes in interest and 

foreign  currency  rates,  the  supply  and  demand  for,  deliveries  of  and  the  level  and  volatility  of  prices  of  rough 

diamonds, costs of power and diesel, acts of foreign governments and the outcome of legal proceedings, inaccurate 

geological and recoverability assumptions (including with respect to the size, grade and recoverability of mineral 

reserves  and  resources),  and  unanticipated  operational  difficulties  (including  failure  of  plant,  equipment  or 

processes to operate in accordance with specifications or expectations, cost escalations, unavailability of materials 

and  equipment,  government  action  or  delays  in  the  receipt  of  government  approvals,  industrial  disturbances  or 

other job actions, adverse weather conditions, and unanticipated events relating to health safety and environmental 

matters). 

Accordingly, readers are cautioned not to place undue reliance on these forward‐looking statements which speak 

only as of the date the statements were made, and the Company does not assume any obligations to update or 

revise them to reflect new events or circumstances, except as required by law.