Lucara Announces Q1 2023 Results; Underground Expansion Continues
May 11, 2023
NEWS RELEASE
LUCARA ANNOUNCES Q1 2023 RESULTS; UNDERGROUND EXPANSION CONTINUES
VANCOUVER, May 11, 2023 /CNW/ (LUC – TSX, LUC – BSE, LUC – Nasdaq Stockholm)
Lucara Diamond Corp. (“Lucara” or the “Company”) today reports its results for the quarter ended March 31, 2023.
Q1 2023 HIGHLIGHTS:
Guidance maintained.
All key operational metrics were on plan, with 0.5 million tonnes of ore and 0.8 million tonnes of waste mined,
0.7 million tonnes of ore processed, and 89,640 carats recovered.
The Q1 2023 operating cash cost of $26.65 per tonne of ore processed (1) was well below the expected annual
operating cash cost range of $32.50 to $35.50 per tonne of ore processed.
Revenue for the quarter ended March 31, 2023 totalled $42.8 million, including $5.3 million through Clara.
Cash flow generated from operating activities was $20.4 million.
$30.5 million invested in the Karowe underground expansion project (“UGP”) in Q1 2023 focused on:
o Main shaft sinking activities in both the ventilation shaft, currently at 213 metres below collar, and the
production shaft, currently at 187 metres below collar.
o The successful completion of the first grout programs in each shaft during the first quarter of 2023.
o Completion and energization of the 11kV transmission line from the new Karowe substation to the
UGP.
o Stage two of the bulk power supply upgrade to connect all mine power requirements to the new
Karowe Substation and 132kV power line. Both the existing operations and the UGP are now fully
powered through the upgraded grid-supplied electricity.
Eira Thomas, President & CEO commented: “As anticipated, Q1 delivered lower revenues than in the comparative
period, owing to the change in ore mix processed and diamond pricing weakness resulting from continued
geopolitical and economic uncertainty. Lucara’s outlook for the year remains unchanged as the largest influence
on our revenue in Q1, ore mix, returns to higher contributions of south lobe ore in subsequent quarters. Sinking
continued in both the production and ventilation shafts with material improvement to planned sinking rates
achieved for the production shaft and mitigations underway in the ventilation shaft to achieve the same. Water
management remains a key focus area. An update to the schedule and budget for the underground project has been
initiated in response to slower than planned ramp up to expected sinking rates, and, to account for time incurred
and anticipated for future grouting programs. We remain on-track to complete the results of this analysis before
the end of Q2, 2023.”
(1) See “Non-IFRS Financial Performance Measures”
2
REVIEW FOR THE QUARTER ENDED MARCH 31, 2023
Operational highlights from the Karowe Mine for Q1 2023 included:
o Ore and waste mined of 0.5 million tonnes (Q1 2022: 0.8) and 0.8 million tonnes (Q1 2022: 0.5),
respectively.
o 0.7 million tonnes (Q1 2022: 0.7) of ore processed.
o A total of 89,640 carats recovered (Q1 2022: 83,917) at a recovered grade of 12.8 carats per hundred
tonnes of direct milled ore (Q1 2022: 12.6).
A total of 98 Specials were recovered, with two diamonds greater than 100 carats including one
diamond greater than 300 carats in weight.
Recovered Specials equated to 4% of the weight percentage of total recovered carats from ore
processed during Q1 2023 (Q1 2022 – 6.9%).
o The twelve-month Total Recordable Injury Frequency Rate of 0.36 (Q1 2022: 0.23) trended downwards
following a three-month period with no recordable injuries.
o The Karowe Mine has operated for over two years without a lost time injury.
Financial highlights for the three months ended March 31, 2023 included:
o Revenues of $42.8 million (Q1 2022: $68.2 million) reflected a planned change in product mix
beginning in early 2023 combined with the continuation of weaker diamond prices when compared to
the strong diamond pricing observed in Q1 2022. During Q1 2023, 64% of the carats processed were
recovered from the Centre and North Lobes and 36% were recovered from South Lobe material (Q1
2022: 100% South Lobe ore).
o Karowe’s +10.8 production, sold through HB, accounted for 57% (Q1 2022: 66%) of total revenues
recognized in Q1 2023.
o Sales of non-Karowe diamonds through Clara were $1.5 million in Q1 2023 (Q1 2022: $1.0 million).
o Adjusted EBITDA(1) was $15.3 million (Q1 2022: $36.0 million), with the change directly attributed to a
decrease in revenues.
o Cash flow of $20.4 million (Q1 2022: $30.8 million) from operating activities.
Cash position and liquidity at March 31, 2023:
o Cash and cash equivalents of $31.2 million.
o Funded $18.0 million into a Cost Overrun Facility in the first quarter of 2023.
o Drew $25.0 million from the $170.0 million project finance facility for the Karowe UGP resulting in
$90.0 million drawn at quarter-end.
o The outstanding balance on the working capital facility increased from $15.0 million to $23.0 million
through Q1 2023, resulting in available liquidity of $27.0 million.
DIAMOND MARKET
Despite a positive, longer-term outlook for natural diamonds, anchored on improving fundamentals around supply
and demand, softer diamond prices observed in the latter half of 2022 have continued into 2023 as global economic
concerns combined with geopolitical uncertainty, including the ongoing conflict in Ukraine continue to play out in
the market, particularly in North America. Prices are beginning to show signs of stabilization as China begins to
open-up post-Covid, a trend which is anticipated to continue towards the end of the year. Though sales of lab-grown
diamonds increased during the period, intense competition combined with improvements in technology continue
(1) See “Non-IFRS Financial Performance Measures”
3
to drive prices of lab grown diamonds down. This further differentiates this market segment from the natural
diamond market and highlights the unique nature and inherent rarity of natural diamonds. The longer-term market
fundamentals remain unchanged and positive, pointing to strong price growth over the next few years as demand is
expected to outstrip future supply.
2023 OUTLOOK
This section of the press release provides management's production and cost estimates for 2023. These are
“forward-looking statements” and subject to the cautionary note regarding the risks associated with forward-looking
statements. Diamond revenue guidance does not include revenue related to the sale of exceptional stones (an
individual rough diamond which sells for more than $10 million), or the Sethunya.
No changes were made to the Company’s 2023 Guidance (released in December 2022).
Karowe Diamond Mine Full Year – 2023
In millions of U.S. dollars unless otherwise noted
Diamond revenue (millions) $200 to $230
Diamond sales (thousands of carats) 385 to 415
Diamonds recovered (thousands of carats) 395 to 425
Ore tonnes mined (millions) 1.9 to 2.3
Waste tonnes mined (millions) 2.2 to 2.8
Ore tonnes processed (millions) 2.6 to 2.9
Total operating cash costs (1) including waste mined(2) (per tonne processed) $32.50 to $35.50
Botswana general & administrative expenses including marketing costs (per tonne
processed)
$3.50 to $4.50
Tax rate(3) 0%
Average exchange rate – USD/Pula 12.0
(1) Operating cash costs are a non-IFRS measure. See “Non-IFRS Financial Performance Measures”.
(2) Includes ore and waste mined cash costs of $7.00 to $8.00 (per tonne mined) and processing cash costs of $12.00 to $13.00 (per tonne
processed).
(3) The Company is subject to a variable tax rate in Botswana based on a profit and revenue ratio which increases as profit as a percentage of
revenue increases. The lowest variable tax rate is 22% while the highest variable tax rate is 55% (only if taxable income were equal to
revenue). Capital expenditures are deductible when incurred. With planned capital expenditures of up to $105 million for the UGP, a tax
rate of 0% is forecast for 2023. Should capital expenditures vary from plan, the Company could be subject to current tax.
DIAMOND SALES
Karowe diamonds are sold through three separate and distinct sales channels: through the HB sales agreement, on
the Clara digital sales platform and through quarterly tenders.
HB SALES AGREEMENT FOR +10.8 CARAT DIAMOND PRODUCTION FROM KAROWE
For the three months ended March 31, 2023, the Company recorded revenue of $24.5 million from the HB
agreement (inclusive of top-up payments of $6.6 million), as compared to revenue of $45.2 million (inclusive of top-
up payments of $11.7 million). The revenue achieved in Q1 2023 is comparable to the $24.1 million earned from the
HB agreement (inclusive of top-up payments of $3.6 million) in Q4 2022.
The decrease in revenue in Q1 2023 versus the comparative quarter can be attributed primarily to the number of
high value diamonds delivered to HB in 2022 and the value of diamonds delivered earlier in 2021 for which top-up
revenue was received in the period. Top-up values will typically increase as the more valuable stones move through
production and become available for sale. Adjusting for the sale of Sewelô, a lower number of carats from production
were delivered to HB in Q1 2023 compared to Q1 2022. The lower initial value of the shipments was reflective of the
4
value in the stones delivered consistent with the change in product mix. This result is consistent with the resource
model and expected.
At March 31, 2023, a number of higher value and more technically complex stones that take longer to manufacture
had not fully completed the manufacturing and sales process. As these stones finish the manufacturing process, the
Company may record additional revenue in the form of “top-up” payments when these diamonds are sold.
Despite the overall decrease in revenue recognized in Q1 2023, diamond market fundamentals continued to support
healthy prices as the number of polished stones sold by HB has improved from Q4 2022. Natural variability in the
quality profile of the +10.8ct production in any production period or fiscal quarter results in fluctuations in recorded
revenue and associated top-ups. During Q1 2023, 4% weight percentage of Specials of total carats recovered was
consistent with the Karowe resource model.
CLARA SALES PLATFORM
As Clara grows, to complement goods from the Karowe mine, additional supply is being made available through
diamonds purchased by the Company and re-sold through Clara and secondary market suppliers. Total volume
transacted on the platform was $5.3 million in Q1 2023, with Karowe goods representing 63% of the total sales
volume transacted. Sales of third-party diamonds increased to $1.5 million in Q1 2023 (Q1 2022: $1.0 million). The
Company is focused on growing Clara through building additional supply in 2023, both from third-party producers
and the secondary market. The number of buyers on the platform continues to grow with 99 buyers on the platform
at March 31, 2023.
During Q1 2023, the sales volume transacted was $5.3 million (Q1 2022: $7.0 million), as lower volumes were placed
for sale (due to a shift in product mix from the Karowe Mine). A softening in market prices was observed between
Q1 2023 and Q1 2022.
QUARTERLY TENDER
The Q1 2023 tender of $12.9 million (Q1 2022: $16.1 million) reflected a good performance in rough diamond pricing
with strength in the small stones. Rough diamond prices had reached a multi-year high point at the time of the Q1
2022 tender. Pricing achieved through the tender remained at or above price levels in 2019. A total of 77,750 carats
were sold in the March 2023 tender, generating revenues of $12.9 million (Q1 2023 tender: $16.1 million from the
sale of 74,638 carats).
KAROWE UNDERGROUND EXPANSION UPDATE
The Karowe UGP is expected to extend the mine life to at least 2040, with initial underground carat production
predominantly from the highest value EM/PK(S) unit and is forecast to contribute approximately $4 billion in
additional revenues, using conservative diamond prices.
During 2022, the Company updated the estimated capital cost for the Karowe UGP to $547 million (including
contingency). As a result of sinking delays and grouting events beginning in mid-2022 and which are ongoing, the
Company is evaluating the impact of the incurred delays against the overall project schedule and budget. Several
operational adjustments were implemented beginning in Q4 2022 to address the challenges encountered. An
update to the project schedule and budget to take into account these developments is expected to be completed
before the end of Q2, 2023.
5
During the three months ended March 31, 2023, a total of $30.5 million was spent on the Karowe UGP development,
primarily in relation to ongoing construction activities, including:
Main sinking in the production and ventilation shafts:
o In response to water inflows from the sandstones, one cover grouting event in the ventilation shaft
and two events in the production shaft were successfully completed during February and March 2023.
Experiences gained from these first grouting events will inform future anticipated cover grouting
events as the shafts progress to depth.
o Planned sinking rates achieved in the production shaft in Q1 following active interventions and
mitigations implemented in Q4 2022. Further investments made in Q4 2022 are expected to similarly
improve sinking cycle times to planned rates in the ventilation shaft and progress is being closely
monitored. Cycle time is the period it takes to complete a series of activities within the sinking process
to achieve the next planned vertical advance.
o The ventilation shaft is currently at 213 metres below collar, with a planned final depth of 731 metres.
The production shaft is currently at 187 metres below collar, with a planned final depth of 765 metres.
The 11kV transmission line to the project site was commissioned in mid-January 2023. This represents a
significant milestone for the Karowe UGP as it is now fully powered through grid-supplied electricity.
Transition of the temporary power supply to a back-up power configuration. Back-up power will continue to be
provided by diesel generators.
Stage two of the bulk power supply upgrade to connect all mine power requirements to the new Karowe
Substation and 132kV power line. This upgrade is expected to deliver stable and dedicated power to the Karowe
Mine operations.
The roll out of a behavioural-based safety training program in Q4 2022 has continued in the first quarter of 2023.
The UGP achieved a three-month period with no reportable incidents delivering a three-month rolling Total
Recordable Injury Frequency Rate of zero.
Activities for the Karowe UGP in Q2 2023 are expected to include the following:
Sinking and grouting within both the ventilation and production shafts.
Procurement of underground equipment, including dewatering pumps, underground crush and convey systems
and the permanent stage winder.
Initiation of construction on the bulk air cooler system.
Development of a request for proposal for the underground lateral development work; and,
Continuation of detailed design and engineering of the underground mine infrastructure and layout.
The capital cost estimate for the underground expansion in 2023 is $105 million – see “2023 Outlook”. The program
will focus predominantly on shaft sinking and grouting activities in both shafts, along with construction of the bulk
air cooler, tendering of the underground development contract and underground equipment purchases. Ramp-up
to planned sinking rates for the ventilation shaft continues and additional cover grouting events are expected for
both shafts in 2023 and 2024.
6
FINANCIAL HIGHLIGHTS – Q1 2023
Three months ended
March 31,
In millions of U.S. dollars, except carats or otherwise
noted
2023 2022
Revenues $ 42.8 68.2
Operating expenses (18.3) (18.0)
Net income for the period 1.0 19.0
Earnings per share (basic and diluted) 0.00 0.04
Operating cash flow per share (1) 0.03 0.08
Cash on hand 31.2 39.1
Amounts drawn on working capital facility (2) 23.0 12.0
Amounts drawn on project finance facility 90.0 45.0
Karowe Revenue 41.2 67.2
Carats sold 83,374 80,295
QUARTERLY RESULTS OF OPERATIONS – KAROWE MINE, BOTSWANA
UNIT Q1-23 Q4-22 Q3-22 Q2-22 Q1-22
Sales
Revenues from the sale of Karowe diamonds US$M 41.3 40.1 46.5 50.0 67.2
Karowe carats sold Carats 83,374 81,264 99,301 66,167 80,295
Production
Tonnes mined (ore) Tonnes 541,400 484,705 920,410 1,091,192 811,947
Tonnes mined (waste) Tonnes 761,295 199,385 453,860 357,764 482,104
Tonnes processed Tonnes 700,678 690,946 693,398 719,207 666,488
Average grade processed(1) cpht (*) 12.8 12.5 11.4 12.0 12.6
Carats recovered Carats 89,640 86,655 78,879 86,317 83,917
Costs
Operating cost per tonne of ore processed(2) US$ 26.65 26.20 29.33 28.78 27.80
Capital Expenditures
Sustaining capital expenditures US$M 0.8 9.9 4.0 4.1 0.8
Underground expansion project(3) US$M 30.5 22.3 23.9 29.1 31.1
(*) carats per hundred tonnes
(1) Average grade processed is from direct milling carats and excludes carats recovered from re-processing historic recovery
tailings from previous milling.
(2) Operating cost per tonne of ore processed is a non-IFRS measure. See “Use of Non-IFRS Performance Measures” below.
(3) Excludes qualifying borrowing cost capitalized in each quarter.
(1) Operating cash flow per share before working capital adjustments is a non-IFRS measure. See “Use of Non-IFRS Performance Measures”
below.
(2) Excludes amounts drawn from the Clara revolving credit facility.
7
CONFERENCE CALL
The Company will host a conference call and webcast to discuss the results on Friday, May 12, 2023 at 5:00am
Pacific, 8:00am Eastern, 1:00pm UK, 2:00pm CET.
To join the conference call please use the following link https://emportal.ink/3MK80nT or the phone numbers listed
below.
Conference ID:
33643944 / Lucara Diamond
Dial-In Numbers:
Toll-Free Participant Dial-In North America (+1) 888 390 0605
UK Toll free 0800 652 2435
Local Vancouver (+1) 416 764 8609
Webcast:
To view the live webcast presentation, please log on using this direct link: https://app.webinar.net/8rMY2nz2Z7p
The presentation slideshow will also be available in PDF format for download from the Lucara website ( Link to
presentation).
Conference Replay:
A replay will be available until May 19, 2023. The pass code for the replay is: 643944#.
Replay number (Toll Free North America) (+1) 888 390 0541
Replay number (Local) (+1) 416 764 8677
On behalf of the Board,
Eira Thomas
President and Chief Executive Officer
Follow Lucara Diamond on Facebook, Twitter, Instagram, and LinkedIn
For further information, please contact:
Hannah Reynish Investor Relations & Communications
+1 604 674 0272| [email protected]
Sweden Robert Eriksson, Investor Relations & Public Relations
+46 701 112615 | [email protected]
UK Public Relations Charles Vivian / Jos Simson, Tavistock
+44 778 855 4035 | [email protected]
ABOUT LUCARA
Lucara is a leading independent producer of large exceptional quality Type IIa diamonds from its 100% owned
Karowe Diamond Mine in Botswana. The Karowe Mine has been in production since 2012 and is the focus of the
Company’s operations and development activities. Clara Diamond Solutions Limited Partnership (“Clara”), a wholly-
owned subsidiary of Lucara, has developed a secure, digital sales platform that uses proprietary analytics together
with cloud and blockchain technologies to modernize the existing diamond supply chain, driving efficiencies,
unlocking value and ensuring diamond provenance from mine to finger. Lucara has an experienced board and
management team with extensive diamond development and operations expertise. Lucara and its subsidiaries
operate transparently and in accordance with international best practices in the areas of sustainability, health and
8
safety, environment, and community relations. Lucara has adopted the IFC Performance Standards and the World
Bank Group’s Environmental, Health and Safety Guidelines for Mining (2007). Accordingly, the development of the
Karowe underground expansion project (“UGP”) adheres to the Equator Principles. Lucara is committed to upholding
high standards while striving to deliver long-term economic benefits to Botswana and the communities in which the
Company operates.
The information is information that Lucara is obliged to make public pursuant to the EU Market Abuse Regulation
and the Swedish Securities Markets Act. This information was submitted for publication, through the agency of the
contact person set out above, on May 11, 2023 at 5:00pm Pacific Time.
NON-IFRS FINANCIAL PERFORMANCE MEASURES
This news release refers to certain financial measures, such as adjusted EBITDA, adjusted operating earnings,
operating cash flow per share, operating margin per carat sold and operating cost per tonne of ore processed, which
are not measures recognized under IFRS and do not have a standardized meaning prescribed by IFRS. These
measures may differ from those made by other corporations and accordingly may not be comparable to such
measures as reported by other corporations. These measures have been derived from the Company’s financial
statements, and applied on a consistent basis, because the Company believes they are of assistance in the
understanding of the results of operations and financial position. Please refer to the Company’s MD&A for the
quarter ended March 31, 2023 for an explanation of non-IFRS measures used.
CAUTIONARY NOTE REGARDING FORWARD LOOKING STATEMENTS
Certain of the statements made and contained herein and elsewhere constitute forward-looking statements as
defined in applicable securities laws. Generally, these forward-looking statements can be identified by the use of
forward-looking terminology such as "expects", "anticipates", "believes", "intends", "estimates", "potential",
"possible" and similar expressions, or statements that events, conditions or results "will", "may", "could" or "should"
occur or be achieved.
Forward-looking statements are based on the opinions and estimates of management as of the date such statements
are made, and they are subject to a number of known and unknown risks, uncertainties and other factors which may
cause the actual results, performance or achievements of the Company to be materially different from any future
results, performance or achievement expressed or implied by such forward-looking statements. The Company
believes that expectations reflected in this forward-looking information are reasonable, but no assurance can be
given that these expectations will prove to be accurate and such forward-looking information included herein should
not be unduly relied upon.
In particular, forward-looking information and forward-looking statements in this news release may include, but are
not limited to, information or statements of projected capital costs associated with the Karowe UGP,, the Company’s
ability to comply with the terms of the facilities which are required to construct the Karowe UGP, that expected cash
flow from operations, combined with external financing will be sufficient to complete construction of the Karowe
UGP, the potential impacts of COVID-19, economic and geopolitical risks, including potential impacts from the
Russian military invasion of Ukraine, expectations regarding longer-term market fundamentals and price growth, the
disclosure under “2023 Outlook”, expectations regarding top-up payments, processing expectations, expectations
that the Karowe UGP will extend mine life, forecasts of additional revenues, estimated capital costs, production and
cost estimates, tax rates, expectations regarding the scheduling of activities for the Karowe UGP in 2023 and in
future, that the estimated timelines to achieve mine ramp up and full production from the Karowe UGP can be
achieved, the economic potential of a mineralized area, the size and tonnage of a mineralized area, anticipated
sample grades or bulk sample diamond content, future production activity, the future price and demand for, and
supply of, diamonds, future forecasts of revenue and variable consideration in determining revenue, estimation of
mineral resources, exploration and development plans, cost and timing of the development of deposits and
estimated future production, currency exchange rates, success of exploration, requirements for and availability of
additional capital, capital expenditures, operating costs, the completion of transactions the profitability of Clara and