Lithium Ionic drills 1.59% Li2O over 15m and 1.58% Li2O over 9m at Salinas Project, Minas Gerais, Brazil; NI 43-101 Mineral Resource Estimate Underway

Drill Results Resource Estimates

Lithium Ionic drills 1.59% Li2O over 15m and 1.58% Li2O over 9m at Salinas

Project, Minas Gerais, Brazil; NI 43-101 Mineral Resource Estimate Underway

TORONTO, ON, January 9, 2024 – Lithium Ionic Corp. (TSXV: LTH; OTCQX: LTHCF; FSE: H3N)

(“Lithium Ionic” or the “C ompany”) reports assay results from the Salinas Lithium Project

(“Salinas”), located approximately 100 kilometres north of its Itinga group of properties which

hosts the Feasibility-stage Bandeira lithium project and the Outro Lado lithium deposit (see press

releases dated October 19, 2023 and June 27, 2023 ) (See location map and drill highlights in

Figure 1).

With properties covering 1 4,182 hectares, the Company is the second largest landholder in

Brazil’s “Lithium Valley”, in northern Minas Gerais State, Brazil, where two lithium producers

currently operate.

Salinas Drill Intercept Highlights:

▪ 1.59% Li2O over 15.0m, directly at surface from 42 metres (hole BGDD-23-095)

▪ 1.58% Li2O over 9.0m (hole BGDD-23-098)

▪ 1.13% Li2O over 9.1m, including 1.61% Li2O over 4.0m (hole BGDD-23-100)

▪ 0.96% Li2O over 11.0m, including 1.21% Li2O over 5.0m (hole BGDD-23-102)

Blake Hylands, P.Geo., Chief Executive Officer of Lithium Ionic, commented, “Our drilling efforts

at Salinas have proved very successful , with assay results that continue to demonstrate high

grades over significant widths that reinforce this target’s potential. We look forward to seeing the

results from the last 9 months of drilling at Salinas materialize into an initial mineral resource ,

which we expect to deliver in the coming months. While our focus remains on getting Bandeira to

production, the advancement of our other regional targets, including Salinas underscores the

scalability of our projects in this prolific lithium district.”

The Company is actively drilling at Salinas, one of its main targets of the 50,000-metre drill

program planned for 2024, where it is testing and delineating multiple outcropping spodumene-

rich pegmatite bodies. Approximately 25,000 metres (105 holes) have been completed at Salinas

since the Company began drilling in May 2023.

Lithium Ionic acquired the Salinas group of properties in early 2023 from Neolit Minerals

Participações Ltda. (“Neolit”; see press release dated March 13, 2023 ) and began selectively

drilling the area in May 2023, following up on a 4,000-metre, 24-hole, drill program completed by

the previous owner in 2022, which yielded excellent results, including highlights of 1.53% Li2O

over 11.4m, 1.22% Li2O over 13.8m, 1.71% Li2O over 9.8m and 1.19% Li2O over 13.4m. On

July 25, 2023, the Company reported initial results from its drilling program at Salinas, including

highlights of 1.38% Li2O over 16m, 1.60% Li2O over 12m, 1.55% Li2O over 9m, 1.26% Li2O

over 11m and 1.34% Li2O over 10m. On December 7, 2023, the Company reported the widest

and highest -grade lithium intercept to date at this target , including 1.13% Li2O over 27.6m,

including 1.34% Li2O over 9m.

Figure 1. Salinas Lithium Project Location & Drill Intercept Highlights

Table 1. Salinas Drill Results

Hole ID Az Dip From To Metres Li2O (%)

BGDD-23-094

310 -79

206.50 208.50 2.00 0.58

and 223.17 226.40 3.23 0.48

and 279.34 282.39 3.05 1.41

BGDD-23-095 310 -70 42.16 57.16 15.00 1.59

BGDD-23-098 260 -75 199.70 208.70 9.00 1.58

BGDD-23-099

0 -90

63.06 66.10 3.04 0.95

and 109.22 114.22 5.00 0.93

including 109.22 112.22 3.00 1.24

BGDD-23-100 310 -60 120.18 129.25 9.07 1.13

including 120.18 124.18 4.00 1.61

BGDD-23-101 310 -60 nsv

BGDD-23-102

310 -60

65.94 70.98 5.04 1.29

and 75.43 86.40 10.97 0.96

including 76.43 81.43 5.00 1.21

*No significant results/values (nsv) for holes BGDD-23-101

**Assays pending for holes: BGDD-23-096 and BGDD-23-103 to BGDD-23-107

***Hole BGDD-23-097 reported on December 7, 2023.

About Lithium Ionic Corp.

Lithium Ionic is a Canadian mining company exploring and developing its lithium properties in

Brazil. Its Itinga and Salinas group of properties cover 14,182 hectares in the northeastern part of

Minas Gerais state, a mining-friendly jurisdiction that is quickly emerging as a world -class hard-

rock lithium district. Its Feasibility-stage Bandeira Project is situated in the same region as CBL’s

Cachoeira lithium mine, which has produced lithium for +30 years, as well as Sigma Lithium

Corp.’s Grota do Cirilo project, which hosts the largest hard-rock lithium deposit in the Americas.

Quality Assurance and Control

During the drill program, assay samples were taken from NQ core and sawed in half. One -half

was sent for assaying at SGS Laboratory, a certified independent commercial laboratory, and the

other half was retained for results, cross checks, and future reference. A strict QA/QC program

was applied to all samples. Every sample was processed with Drying, crushing from 75% to 3

mm, homogenization, quartering in Jones, spraying 250 to 300 g of sample in steel mill 95% to

150. SGS laboratory carried out multi-element analysis for ICP90A analysis.

Qualified Persons

The technical information in this news release has been reviewed and approved by Carlos Costa,

Vice President Exploration of Lithium Ionic and Blake Hylands, CEO and director of Lithium Ionic,

who are both “qualified persons” as defined in NI 43-101.

The technical information relating to the historical exploration conducted by Neolit is historical in

nature and has not been independently verified by Lithium Ionic. A qualified person, as defined in

National Instrument 43-101, has not done sufficient work on behalf of Lithium Ionic to classify the

historical drilling reported above as c urrent mineral resources or mineral reserves and Lithium

Ionic is not treating the historical drill results as current mineral resources or mineral reserves.

Investor and Media Inquiries:

+1 647.316.2500

[email protected]

Cautionary Note Regarding Forward-Looking Statements

This press release contains statements that constitute “forward -statements.” Such forward

looking statements involve known and unknown risks, uncertainties and other factors that may

cause the Company’s actual results, performance or achievements, or devel opments to differ

materially from the anticipated results, performance or achievements expressed or implied by

such forward-looking statements. Although the Company believes, in light of the experience of its

officers and directors, current conditions and expected future developments and other factors that

have been considered appropriate that the expectations reflected in this forward -looking

information are reasonable, undue reliance should not be placed on them because the Company

can give no assurance t hat they will prove to be correct. When used in this press release, the

words “estimate”, “project”, “belief”, “anticipate”, “intend”, “expect”, “plan”, “predict”, “may” or

“should” and the negative of these words or such variations thereon or comparable t erminology

are intended to identify forward -looking statements and information. The forward -looking

statements and information in this press release include information relating to the prospectivity

of Salinas and the Company’s other mineral properties, the economic viability of the Bandeira,

the mineralization and development of the Company’s mineral properties, the Company’s

exploration program and other mining projects and prospects thereof , the Company’s ability to

complete a Feasibility Study, the Company’s ability to complete a NI 43 -101 mineral resource

estimate for Salinas, the Company’s ability to complete an environmental impact assessment and

obtain the requisite permitting and approvals and the Company’s future plans . Such statements

and information reflect the current view of the Company. Risks and uncertainties that may cause

actual results to differ materially from those contemplated in those forward -looking statements

and information. By their nature, forward -looking statements involve known and unknown risks,

uncertainties and other factors which may cause our actual results, performance or achievements,

or other future events, to be mater ially different from any future results, performance or

achievements expressed or implied by such forward -looking statements. The forward -looking

information contained in this news release represents the expectations of the Company as of the

date of this news release and, accordingly, is subject to change after such date. Readers should

not place undue importance on forward -looking information and should not rely upon this

information as of any other date. The Company undertakes no obligation to update these forward-

looking statements in the event that management’s beliefs, estimates or opinions, or other factors,

should change.

Information and links in this press release relating to other mineral resource companies are from

their sources believed to be reliable, but that have not been independently verified by the

Company.

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this press

release.