Lithium Ionic Advances Environmental & Social Permitting Process with Submission of LAC License Application for the Construction and Development of the Bandeira Lithium Project, Minas Gerais, Brazil

Mine Development & Operations Permits & Approvals

Lithium Ionic Advances Environmental & Social Permitting Process with

Submission of LAC License Application for the Construction and Development of

the Bandeira Lithium Project, Minas Gerais, Brazil

TORONTO, ON, November 21, 2023 – Lithium Ionic Corp. (TSXV: LTH; OTCQX: LTHCF; FSE:

H3N) (“Lithium Ionic” or the “Company”), a lithium exploration and development company focused

on becoming Brazil’s next significant lithium producer, is pleased to report a major milestone with

the application of a Concomitant Environmental and Installation License (“LAC”, or Licença

Ambiental Concomitante in Portuguese ) submitted to the State of Minas Gerais for the

construction and development of its Bandeira lithium Project (“Bandeira”).

The Preliminary Economic Assessment (“PEA”) for Bandeira announced last month defined an

underground mining operation which provides a reduced environmental footprint relative to other

development options. This development approach qualifies the Bandeira project as a candidate

for the accelerated LAC license that would result in the environmental and social license, together

with an authorization to begin construction.

As part of the application, the Company submitted both an RCA (Environmental Control Report)

and PCA (Environmental Control Plan) which have been underway since March 2023 by local

environmental consultancy group, NEO Agroambiental Ltda., with assistance from Lithium Ionic’s

technical team.

All of the Company’s properties and projects, including Bandeira, have been recognized as

“priority projects” within the state of Minas Gerais government, which is expected to accelerate

the licensing review process for project construction and operations (see press release dated

July 19, 2023).

Blake Hylands, P.Geo., C EO of Lithium Ionic, commented, “ The submission of the LAC permit

application marks a major milestone on our development path towards becoming a near -term

producer of high -quality lithium concentrate. We are pleased that Minas Gerais state officials

recognize the importance of supporting the development of the battery materials sector in the

region and we are confident that having our project on their priority business development list will

result in our application being evaluated accordingly, without delay.”

The Bandeira project covers 175 hectares, or approximately 1% of its large 14,182-hectare land

package in the northern part of Minas Gerais State within a region recently coined “Lithium Valley”

by state officials, which is emerging as a globally significant producer of high -quality lithium

concentrate. Two lithium producers currently operate in the region, located between 800 metres

and 4 kilometres from the Bandeira project.

The Company is currently undertaking an independent NI 43 -101 compliant Feasibility Study

(“FS”), including an updated MRE, expected to be completed in early 2024. The FS follows a

Preliminary Economic Assessment (“PEA”) , which showcased a viable and highly economic

mining project. The PEA, which had a drill data cut -off of August 30, 2023 with respect to the

MRE, supported 20 -years of low-cost spodumene concentrate production with a post-tax Net

Present Value (“NPV”)8% of US$1.6 billion (~C$2.2 billion) and an Internal Rate of Return (“IRR”)

of 121% (see details of the PEA in the press release dated October 19, 2023).

About Lithium Ionic Corp.

Lithium Ionic is a Canadian mining company exploring and developing its lithium properties in

Brazil. Its Itinga and Salinas group of properties cover 14,182 hectares in the northeastern part of

Minas Gerais state, a mining-friendly jurisdiction that is quickly emerging as a world -class hard-

rock lithium district. Its Feasibility-stage Bandeira Project is situated in the same region as CBL’s

Cachoeira lithium mine, which has produced lithium for +30 years, as well as Sigma Lithium

Corp.’s Grota do Cirilo project, which hosts the largest hard-rock lithium deposit in the Americas.

Qualified Persons

The technical information in this news release has been prepared by Carlos Costa, Vice President

Exploration of Lithium Ionic and Blake Hylands, CEO and director of Lithium Ionic, who are both

“qualified person s” as defined in NI 43 -101. Mr. Costa and Mr. Hylands have both read and

approved the content in this news release.

Investor and Media Inquiries:

+1 647.316.2500

[email protected]

Cautionary Note Regarding Forward-Looking Statements

This press release contains statements that constitute “forward -statements.” Such forward

looking statements involve known and unknown risks, uncertainties and other factors that may

cause the Company’s actual results, performance or achievements, or devel opments to differ

materially from the anticipated results, performance or achievements expressed or implied by

such forward-looking statements. Although the Company believes, in light of the experience of its

officers and directors, current conditions and expected future developments and other factors that

have been considered appropriate that the expectations reflected in this forward -looking

information are reasonable, undue reliance should not be placed on them because the Company

can give no assurance t hat they will prove to be correct. When used in this press release, the

words “estimate”, “project”, “belief”, “anticipate”, “intend”, “expect”, “plan”, “predict”, “may” or

“should” and the negative of these words or such variations thereon or comparable t erminology

are intended to identify forward -looking statements and information. The forward -looking

statements and information in this press release include information relating to the prospectivity

of the Company’s mineral properties, the economic viability of the Bandeira, the mineralization

and development of the Company’s mineral properties, the Company’s exploration program and

other mining projects and prospects thereof, the Company’s ability to complete a Feasibility Study,

the Company’s ability to complete an environmental impact assessment and obtain the requisite

permitting and approvals and the Company’s future plans . Such statements and information

reflect the current view of the Company. Risks and uncertainties that may cause actual results to

differ materially from those contemplated in those forward-looking statements and information. By

their nature, forward -looking statements involve known and unknown risks, uncertainties and

other factors which may cause our actual results, performance or ac hievements, or other future

events, to be materially different from any future results, performance or achievements expressed

or implied by such forward-looking statements. The forward-looking information contained in this

news release represents the expectations of the Company as of the date of this news release

and, accordingly, is subject to change after such date. Readers should not place undue

importance on forward -looking information and should not rely upon this information as of any

other date. The Company undertakes no obliga tion to update these forward -looking statements

in the event that management’s beliefs, estimates or opinions, or other factors, should change.

Information and links in this press release relating to other mineral resource companies are from

their sources believed to be reliable, but that have not been independently verified by the

Company.

Neither the TSXV nor its Regulation Services Provider (as that term is defined in the

policies of the TSXV) accepts responsibility for the adequacy or accuracy of this press

release.