Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LPK.V ·

Lupaka Provides Development Update; Commercial Production Expected in Q3/18

Production Results Mine Development & Operations

Lupaka Provides Development Update; Commercial Production

Expected in Q3/18

VANCOUVER, BRITISH COLUMBIA, April 17, 2018 -- Lupaka Gold Corp. (" Lupaka

Gold" or the “Company") (TSX-V: LPK, FRA: LQP) is pleased to provide a development

update on the Company’s 100% owned Invicta Gold Development Project (“Invicta

Project” or “Invicta”).

Highlights:

• Main access road construction is 65% advanced, completion expected in

May 2018

• Operations team substantially in place, rehabilitation of the 3400 Level

approximately 50% complete

• 3430 Level cross-cut completed, continuity and consistency of hanging wall

split and footwall zones confirmed between 3400 and 3430 Levels

• 8,000 tonnes of mineralized development material to be toll processed in May

• Project remains o n track and on budget, commercial production at 350

tonnes per day (“tpd”) expected to be reached in the third-quarter of 2018

(“Q3/18”)

• Fully financed for the development of Invicta (refer to February 13, 2018 news

release)

“With our operational team now substantially in place, the development and rehabilitation

of Invicta has rapidly advanced and the Company is well positioned to reach commercial

production, at 350 tonnes per day, during the third quarter of 2018. While continuing to

rehabilitate and develop the Invicta mine, 8,000 tonnes of mineralized development

material will be sent for processing and evaluation at regional toll milling facilities in May,

the proceeds of which will offset development costs. The 3430 Level cross-cut has been

completed and the continuity and consistency of the hanging wall and footwall veins has

been confirmed from the 3400 Level up to the 3430 Level. Sublevel preparation for mining

of the footwall vein between the 3400 and 3430 Levels is progressing well. We are

pleased to report that overall, the project remains on time and on budget.”

Will Ansley, President and CEO of Lupaka Gold

Road Construction Progress

Upgrades to the 28 kilometre main access road, from the paved highway to the Invicta

Project, are approximately 65% advanced. The upgrade work includes widening the road

from four meters to approximately six meters, construction of four by-passes to circumvent

communities and difficult portions of the road where numerous switchbacks occurred, the

development of borrow pits to obtain road surfacing materials, improving the road surface

to allow 30 tonne haulage trucks and heavy machinery to travel, and the installation of

berms and drainage ditches. Along with the reduction of traffic within the communities and

increasing the efficiency of hauling, one of the main and most important benefits of these

improvements is increasing safety conditions.

Heavy rainfall, thick fog, and a delay in obtaining the explosives licence initially impeded

road upgrade productivity; approximately 20% of the length of the road requires blasting

prior to removal with excavators. During December and January the advance rate of road

construction was approximately 150 meters per day , however, the current rate is in the

range of 300 meters per day. Depending on precipitation levels, the Company is targeting

completion of the road project in May 2018.

Invicta Development and Rehabilitation Update

Development and rehabilitation work at Invicta is progressing well and the Company

anticipates it will commence production from the 3400 Level at a rate of 350 tpd in Q3/18.

Recruitment of the key operations team personnel was completed in Q1/18 which included

the Director of Operations, Mine Manager, Chief Geologist, Superintendent of Production

& Mine Planning, and other related technical personnel. The operations team is

overseeing and directing the mining and road contractors, as well as preparing the mine

development and production plans. During the second quarter of 2018, the Invicta camp

facilities will be expanded from 65 people to allow for up to 130 persons.

Figure 1 – Invicta Development Plan (3D – Oblique Long Section)

Several enhancements have been made to the initial mine plan as outlined in the March

2018 Preliminary Economic Assessment (“PEA”). As illustrated in Figure 1 above, two

vertical material transport raises originally contemplated in the PEA have been eliminated,

resulting in a savings of approximately US$ 250,000, through the use of draw points on

the 3400 Level. The 3400 Level will be the main haulage level for mineralized material

and a decision has been made to increase the dimension of 120 metres of the 3400 Level

Material

storage

from 3.5 metres (‘m’) wide x 3.0 m high to 4.5 m wide x 4.0 m high in order to allow access

of 30 tonne haulage trucks, which can then haul directly to the processing plant . Small

mineralized material storage chambers will be constructed underground to ensure a

continuous flow of mineralized material from the mine to the plant. Mineralized material

will be loaded into the waiting truck s from the underground stations on 3400 Level and

travel directly to the process plant, thereby eliminating the need to construct and operate

a reloading platform 26 kilometres from the mine . The investment in widening the 3400

Level is budgeted to be approximately US$500,000, however, direct haulage (avoiding the

use of a reload station) will lower future operating costs and payback on the investment is

estimated to be approximately one year . Furthermore, increasing the dimensions and

haulage capacity of the 3400 Level allows Lupaka to m ore easily increase the mines

output in future years above the current plan of 350 tpd.

Other efforts on the 3400 Level includes replacing and enhancing the existing ground

support systems, installation of services, refuge and vehicle bypasses, and a ventilation

system that includes two raises (2.0 m x 2.0 m) which will provide a continuous flow of

fresh air to the 3400, 3430 and future sublevels, as well as providing secondary egress

points. Approximately 90 meters of the required 180 metres has been rehabilitated on the

3400 Level, and development of the first ventilation raise has commenced.

The 3430 Level cross-cut was completed advancing a total of 149 m, intersecting the

hanging wall split at 133 m and the footwall zone at 142 m. Mineralization in both zones

is visually consistent containing coarse grains of chalcopyrite, sphalerite, and galena, with

the mineralization 30 metres below on the 3400 Level.

Evaluation of Toll Milling Facilities

Approximately 8,000 tonnes of mineralized development material will be sent to regional

toll milling facilities for processing in May, at different throughput levels, in order to assess

the suitability and optimal recoveries available from the plant s. Approximately 2,000

tonnes of mineralized development material is currently stockpiled on surface.

Josnitoro Project

The Josnitoro joint venture agreement (“JV”) with Hochschild Mining plc required the

Company to obtain a community agreement for exploration by March 2018. Lupaka was

unable to obtain a community agreement and requests for an extension with Hochschild

were unsuccessful, resulting in termination of the JV . As the focus for the Company

continues to be the advancement of Invicta into production, no significant activities were

performed on the JV, and there were no carrying costs associated with the property.

Neither the TSX Venture Exchange nor its Regulation Service Provider (as the term

is defined in the policies of the TSX Venture Exchange) accepts responsibility for

the adequacy of this news release.

About Lupaka Gold

Lupaka is an active Canadian-based company focused on creating shareholder value

through discoveries and strategic development of its assets in some of the most prolific

mining regions of Peru.

Invicta Gold Development Project – 100% owned, the Company’s flagship project is an

advanced stage gold-copper polymetallic underground deposit located approximately 120

kilometres north of Lima. Over $12 million of capital has been spent by previous owners

on development and infrastructure at Invicta , and m anagement expects to commence

potential production in the second half of 2018 by using third-party mining contractors and

utilizing the existing adit and workings. The Invicta project is fully permitted and community

agreements are in place.

The potential underground operation will be focused on underground extraction of

Indicated Mineral Resources and Inferred Mineral Resources from the Atenea vein within

close proximity to the existing 3400 Level adit (up to 130 metres above the 3400 Level).

Invicta’s approved EIA allows for mine production of up to 1,000 tpd, although the current

mining plan is targeting 350 tpd.

Cautionary Note Regarding the Invicta Production Decision

The decision to commence potential production at the Invicta Gold Project and the

Company’s plans for a mining operation as referenced herein (the “Production Decision

and Plans”) are based on economic models prepared by the Company in conjunction with

management’s knowledge of the property and the existing estimate of Indicated and

Inferred Mineral Resources on the property , supplemented by the 2018 PEA . The

Production Decision and Plans were not based on a preliminary economic assessment, a

pre-feasibility study or a feasibility study of mineral reserves demonstrating economic and

technical viability. Accordingly, there is increased uncertainty and economic and technical

risks of failure associated with the Production Decision and Plans, in particular the risk

that mineral grades will be lower than expected, the risk that constructio n or ongoing

mining operations are m ore difficult or m ore expensive than expected, the risk that the

Company will not be able to transport or sell the mineralized material it produces to local

custom toll mills on the terms it expects, or at all; production and economic variables may

vary considerably, due to the absence of a detailed economic and technical analysis

according to and in accordance with NI 43-101.

FOR FURTHER INFORMATION PLEASE CONTACT:

Will Ansley, President & C.E.O.

[email protected]

Tel: (416) 862-5257

or visit the Company’s profile at www.sedar.com or its website at www.lupakagold.com

Qualified Person

The technical information in this document has been reviewed and approved by Dan

Kivari, PEng., Director of Operations of the Company, and a Qualified Person as defined

by National Instrument 43 -101. Mr. Kivari has verified the scientific and technical

information, including sampling, analytical and operational data underlying the information

or opinions contained in this news release.

Cautionary Statements Regarding Forward Looking Information

All statements, trend analysis and other information contained in this press release relative

to anticipated future events or results constitute forward -looking statements. All

statements, other than s tatements of historical fact, included herein, including, without

limitation, statements relating to improvements in the road to the Invicta Project and its

anticipated benefits and the timing of completion of the improvements, the timing of the

commencement of potential production from the Invicta Project and the generation of cash

therefrom, the anticip ated methods of production, the receipt of and anticipated use of

proceeds of the PLI Financing, the Company’s plans and intentions for Invicta, mineral

resource estimates , are forward -looking statements. Forward -looking statements are

based on assumptions, estimates and opinions of management at the date the statements

are made that the Company believes are reasonable, including: that the repayment of the

PLI Financing is consummated on the anticipated terms, that the supplies, equipment,

personnel, permits, and local community approvals required to conduct the Company's

planned pre-production and development activities will be available on reasonable terms,

that the Company will be able to comply with the delivery and other obligations in the PLI

Financing Agreement, that results of exploration activities will be consistent with

management's expectations and that the Company will not experience any material

accident, labour dispute, or failure of equipment and with respect to the planned mining

operations at Invicta; that pre-production mine development can be completed in the time

and for the cost projected; that the Company will be able to obtain funding for planned

production expenses; that mineralization at Invicta will be of the grades and in the

locations expected; that the Company will be able to extract and transport mineralized

rock efficiently and sell the mineralized rock at the prices and in the manner and quantities

expected; that permits will be received on the terms and timeline expected and that other

regulatory or permitting issues will not arise; that mining methods can be employed in the

manner and at the costs expected and that such methods yield the results the Company

expects them to. However, forward -looking information involves known a nd unknown

risks, uncertainties and other factors which may cause the actual results, performance or

achievements of the Company to be materially different from any future results,

performance or achievements expressed or implied by the forward -looking information.

Such risks, uncertainties and other factors include, among others: all of the risks

described in this news release; failure of the PLI Financing to complete on the proposed

terms or at all, including due to the Company’s inability to complete th e conditions

precedent, the risk that actual results of exploration and development activities will be

different than anticipated; that the Company will not be able to comply with the delivery or

other obligations in the PLI Financing Agreement and the ris k that PLI will enforce its

security over the Company’s assets, including its mineral properties; that cost of labour,

equipment or materials will increase more than expected; that the future price of gold will

decline; that the Canadian dollar will streng then against the U.S. dollar; that mineral

resources are not as estimated; unexpected variations in mineral resources, grade or

recovery rates; risks related to shipping mineralized rock; the risk that local mills cannot

or will not buy or process minerali zed rock from the planned production for the prices

expected or at all; risk of accidents, labour disputes and other risks generally associated

with mineral exploration; unanticipated delays in obtaining or failure to obtain community,

governmental or regulatory approvals or financing; and all of the risks generally associated

with the development of mining facilities and the operation of a producing mine, as well as

the risks described in the Company’s annual information form, which is available on

SEDAR at www.sedar.com. Although the Company has attempted to identify important

factors that could cause actual actions, events or results to differ materially from those

described in forward-looking information, there may be other factors that cause actions,

events or results to not be as anticipated, estimated or intended. There can be no

assurance that forward-looking information will prove to be accurate, as actual results and

future events could differ materially from tho se anticipated in such statements. Readers

are cautioned not to place undue reliance on forward -looking information due to the

inherent uncertainty thereof. Lupaka Gold does not undertake any obligation to update

forward-looking statements except as requi red by applicable securities laws. Investors

should not place undue reliance on forward-looking statements.