Laurion Files the NI43‐101 Technical Report for its 100% Owned Bell Mountain Project

Resource Estimates Technical Reports (NI 43-101) Exploration Programs

TORONTO – May 4, 2011 – Laurion Mineral Exploration Inc. (TSX.V: LME; OTCQX: LMEFF) (“Laurion”) advised that the Technical Report supporting the recently released initial Mineral Resource Estimate completed on its Bell Mountain Project  l o c a t e d in  Churchill County, Nevada (Press Release April 6, 2011), has been filed with SEDAR.

The report details an initial Measured and Indicated Mineral Resource estimate at Bell Mountain’s Varga, Spurr and  Sphinx  Zones  of  9,761,000  tonnes  at  an  average  grade  of  0.526  g/t  gold  and  17.63  g/t  silver  hosting 165,018  ounces  gold  and  5,533,907  ounces  silver  and  and  initial  Inferred  Mineral  Resource  estimate  of 2,046,000 tonnes of material at an average grade of 0.449 g/t gold and 13.26 g/t silver hosting 29,550 ounces gold and 872,411 ounces silver. This Mineral Resource Estimate assumed a gold price of $1,149.89 per ounce and a silver price of $20.92 per ounce. Preliminary estimates for operating costs were $11.43 per ton (mining, processing and G&A) and for recoveries were 80% for gold and 51% for silver.

The NI 43‐101 Mineral Resource estimate was completed by Telesto Nevada Inc. (“Telesto”). It incorporates data obtained from 54,692 feet (16,671 meters) of 244 reverse circulation (”RC”) drill holes completed on the Varga, Spurr and Sphinx zones.

Highlights of the Bell Mountain Property:

  • The estimated equivalent ounces of gold contained in the Measured and Indicated Mineral Resource is 265,635 ounces, and estimated Inferred Mineral Resource is 45,412 ounces. The resource estimate is comprised of mineralization found on the Varga, Spurr and Sphinx zones.
  • The mineralized zones remain open to depth and laterally.
  • The gold‐silver mineralized structurally controlled Spurr‐Varga fault can be traced for more than 1.8 kilometers (6,000 feet) on surface. On the fault, approximately 1.5 kilometers on strike to the east of the Varga zone, a further mineralized zone, the East Ridge CC zone, has excellent potential for resource addition.  The  zone  had  a  total  of  481  meters  in  13  RC  drill  holes  spaced  over  a  strike  length  of approximately 300 meters, completed in 2003 by NDT ventures, which confirmed mineralization. The Mike  Zone,  located  between  the  Varga  the  East  Ridge  CC  Zone,  displays  similar  widths  and characteristics, and appears open to adding to the Bell Mountain Resources by further drill programs.
  • The Sphinx Vein system can be traced for more than 900 metres along strike by prospect pits, vein quartz float and trenching and is available to resource expansion in further drill programs.
  • A  Preliminary  Feasibility  study  contemplating  a  conventional  open  pit  heap  leach  configuration  and assessment for potential production is in progress.
  • Environmental permitting requirements to include development of baseline needs and mine plan of operations is in progress.

Table 1 – Global Bell Mountain Resource Estimate

MetricTonnage ('000 Tonnes)Average Gold Grade (g/Tonne)Gold (grams)Gold (ozs)Average Silver Grade (g/Tonne)Silver (grams)Silver (ozs)Total Equivalent Ounces Of Gold
Measured5,9520.5313,158,063101,53416.6298,913,0803,180,127159,355
Indicated3,8100.5181,974,57563,48419.2273,210,7962,353,780106,280
Total Measured and Indicated9,7610.5265,132,638165,01817.63172,123,8765,533,907265,635
Inferred2,0460.449919,10829,55013.2627,135,036872,41145,412

Notes:  

1. Rounding of tons as required by Form 43‐101F1 reporting guidelines (Item 19) results in apparent differences between tons, grade and contained ounces in the mineral resource.

2. Mineral Resources are estimated at a pit discard cutoff Grade at 0.192 g/t AuEq

3. The assumed parameters used for Bell Mountain used establishing a cut‐off grade is identified as follows:

  • Gold Price ‐ $1,149.89/oz (US) ‐ 60% 3‐year previous average/40% 2‐year forward (Dec. 31, 2010)
  • Silver Price ‐ $20.92/oz US ‐ 60% 3‐year previous average/40% 2‐year forward (Dec. 31, 2010)
  • Recovery ‐ Gold 80%, Silver 51%
  • Total Operating Costs ‐ $11.43/ton (mining, processing and G&A)
  • Gold Equivalent Ratio ‐ 55 to 1

Parameters  used  to  estimate  the  in‐situ  resource  are  based  on  information  supplied  by  Bell  Mountain  Group. Assumptions  were  made  for  items  like  strip  ratio,  mining  costs,  processing  costs  and  recovery  percentages.    These assumptions  were  based  on  published  and  previously  calculated  rates  for  other  mining  operations  having  similar parameters, and on testwork performed on Bell Mountain samples.  The operation parameters assume open pit mining and cyanide heap leaching.  A  conceptual  open  pit  mining  method was  used  for  the  purpose  of  delineating  the mineralization  with  a  reasonable  prospect  of  economic  extraction.  Tonnage  estimates  were  based  on  a  2.6 grams/cubic  centimeter  density  factor.    Inverse  distance  square  method  was  used  to  interpolate  grade  in  the resource model (geostatistical methods of calculating resources) using the database based on the RC and core drilling.

About Laurion Minerals Exploration Inc. 

The Corporation's focus is to make the transition from explorer to near‐term producer and envisages the realization of shareholder  value  and  wealth  through  monetization  of  its  discoveries  and  assets.    Laurion's  exploration  horizons  are focused primarily on gold with a secondary interest in base metals and PGEs with key interests in prospective mining properties located in Ontario, Canada and Nevada USA.

The  Corporation  has  an  option  to  acquire  a  100%  interest  in  the  Bell  Mountain  Gold  Project  with  Globex  Mining Enterprises Inc. (TSE: GMX, (G1M‐Frankfurt)) ("Globex") of Rouyn‐Noranda, Quebec.

Laurion envisages the realization of shareholder value and wealth through monetization of its discoveries and assets.

QUALIFIED PERSON 

This news release has been reviewed and approved by Jonathan M. Brown,  Telesto Nevada, Inc. and Dana Durgin,  Laurion's  Bell  Mountain  consulting  geologist  (“Bell  Mountain  Group”)  who  are  Qualified  Persons  as defined  by  NI  43‐101,  with  the  ability  and  authority  to  verify  the  authenticity  and  validity  of  the  data comprising  this  resource estimate.

FOR FURTHER INFORMATION, CONTACT:

Laurion Mineral Exploration Inc. 

Cynthia Le Sueur‐Aquin ‐‐ President

Karen Doxsee – Vice President, Corporate Communications

Tel: 1‐888‐212‐4070 Tel: 1‐705‐788‐9186 Fax: 1‐705‐788‐9187 Website: www.laurion.ca

Neither  TSX  Venture  Exchange  nor  its  Regulation  Services  Provider  (as  that  term  is  defined  in  the  policies  of  the  TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

This news release includes certain forward‐looking statements concerning the future performance of Laurion's business, operations  and  financial  performance  and  condition,  as  well  as  management's  objectives,  strategies,  beliefs  and intentions.  Such statements include, but are not limited to, statements concerning the approval of Laurion's application to trade its common shares over the facilities of the OTCQX and the commencement of such trading.  Forward‐looking statements are frequently identified by such words as "may", "will", "plan", "expect", "anticipate", "estimate", "intend" and similar words referring to future events and results.  Forward‐looking statements are based on the current opinions and  expectations  of  management.    All  forward‐looking  information  is  inherently  uncertain  and  subject  to  a  variety  of assumptions, risks and uncertainties, including the speculative nature of mineral exploration and development, fluctuating commodity prices, competitive risks and the availability of financing, as described in more detail in our recent securities filings available at www.sedar.com.  Actual events or results may differ materially from those projected in the forward‐ looking statements and Laurion cautions against placing undue reliance thereon.  Laurion and its management assume no obligation to revise or update these forward looking statements