LAURION Advances Environmental and Permitting Activities at Ishkōday Gold and Polymetallic Project

Permits & Approvals

1 | Page

LAURION Advances Environmental and Permitting Activities at

Ishkōday Gold and Polymetallic Project

TORONTO ONTARIO, September 18, 2026 — LAURION Mineral Exploration Inc. (TSX-V: LME

| OTC: LMEFF | FSE: 5YD) ("LAURION" or the "Company") is pleased to provide shareholders

with an update on the environmental , technical and regulatory work supporting the

continued advancement of the Company's 100%- owned Ishkōday Gold and

Polymetallic Project in the Onaman -Tashota, Beardmore-Geraldton Greenstone Belt of

Northwestern Ontario.

LAURION is currently advancing two complementary initiatives associated with the

historical Sturgeon River Mine: the recovery and remediation of the historical surface

waste rock stockpile and the Company’s proposed Advanced Exploration Project

focused on dewatering, rehabilitating and evaluating the historical Sturgeon River Mine

shaft and underground workings.

Over the past five years, LAURION has undertaken a comprehensive program of

environmental baseline studies, technical investigations , indigenous and regulatory

consultation to characterize existing site conditions and support project planning and

applicable regulatory approvals.

Background

Surface Stockpile Recovery

LAURION has submitted an application for a Recovery of Minerals Permit to the Ministry

of Energy and Mines, including a Recovery and Remediation Plan, under section 152.1 of

Ontario’s Mining Act and Ontario Regulation 463/24.

The Sturgeon River Mine surface waste rock stockpile is a legacy of historic mining

operations and based on historic and current technical information, contains mineralized

material that LAURION is seeking authorization to recover under Ontario's regulatory

framework for the recovery of minerals. The material currently exists on surface as a result

of decades-old operations and its recovery is not expected to require new infrastructure,

mining or underground development. The proposed work would involve the recovery of

minerals from the historical surface waste rock stockpile through removal and off-site

processing of the material, followed by remediation of the stockpile area in accordance

with applicable provincial standards. These activities take into consideration, and are

2 | Page

supported by, the assessment of potential environmental effects and identif ication of

appropriate environmental protection and remediation measures.

Shaft Dewatering and Advanced Exploration

Separately, LAURION is advancing its plans to rehabilitate the historical Sturgeon River

Mine shaft to facilitate further evaluation and exploration of the historical in-situ resource

potential.

The historical mine workings include a vertical shaft extending approximately 642 metres

below surface and 15 historical underground levels. The mine has remained flooded since

historical operations ceased, with approximately 114,000 cubic metres of static water

previously estimated to be contained within the underground mine workings . The

proposed Advanced Exploration Project would involve removal of the existing shaft cap,

rehabilitation of the shaft collar and installation of a temporary exploration headframe

and hoisting plant to allow for safe access , controlled dewatering of the shaft, and

progressive rehabilitation of the shaft and existing underground levels. Once safe

underground access has been established, LAURION intends to undertake underground

exploration drilling and sampling to further evaluate the deposit and mineralized system.

No commercial mineral production or ore processing is currently proposed as part of the

Advanced Exploration Project.

To facilitate the evaluation and exploration of the historical underground workings ,

LAURION is currently preparing a Permit to Take Water (“PTTW”) application for the

dewatering activities to submit to the Ministry of the Environment, Conservation and Parks

(MECP), with a submission target for Q4 2026. Given the proposed volume of water taking,

a detailed hydrogeological impact assessment will be completed to characterize the

proposed taking and assess potential effects on surrounding groundwater and surface

water resources. The assessment is expected to provide the technical basis for the

proposed dewatering program and associated PTTW application.

In parallel, LAURION is advancing other regulatory requirements necessary to undertake

the proposed Advanced Exploration Project activities, including the preparation of an

Advanced Exploration Closure Plan in accordance with Ontario’s Mining Act. Additional

environmental approvals are also being advanced, as applicable, for project

components, including mine water treatment and discharge, air and noise emissions,

and associated project infrastructure. The applicable Advanced Exploration Closure Plan

and additional environmental approval submissions are targeted for early 2027.

Environmental Baseline Program

Over the past five years, LAURION has commissioned and completed a comprehensive

program of independent environmental baseline studies to support project planning and

compliance with applicable regulatory requirements for the proposed surface stockpile

recovery and Advanced Exploration Project . The program was designed to establish a

detailed understanding of existing environmental conditions, support project design ,

inform the development of appropriate environmental protection, mitigation and

remediation measures, and provide a baseline against which potential p roject-related

environmental effects can be assessed and monitored.

3 | Page

The environmental baseline studies completed to date include:

• Terrestrial ecology, species at risk and bat studies — surveys and assessments to

characterize terrestrial habitat and evaluate the potential presence of protected

species, including bat populations, within and surrounding the project area;

• Aquatic and benthic studies — characterization of aquatic conditions and benthic

communities to establish baseline conditions of surrounding waterbodies and

support the assessment of potential effects associated with water-related activities

at the site;

• Groundwater and surface water studies — multi-year monitoring and

characterization of groundwater and surface water quality and conditions within

and surrounding the project area, providing baseline information against which any

future changes can be assessed;

• Shaft water and hydrogeological studies — characterization of conditions

associated with the flooded historical mine workings to inform planning and

assessment of the proposed dewatering program; and

• Archaeological studies — completion of a Stage 1 A rchaeological Assessment to

identify areas of archaeological potential and inform the need for any subsequent

assessment associated with the proposed project footprint.

Together, these studies provide a foundation for ongoing regulatory review and

permitting activities, and will inform the development of project-specific environmental

management, monitoring, mitigation and remediation measures. Environmental studies

and monitoring programs will continue to be refined, as appropriate, as project planning

and regulatory review activities progress.

Indigenous and Stakeholder Consultation

LAURION has continued to engage with applicable Indigenous communities regarding

the progression of the Ishkōday Project, including the proposed transition to advanced

exploration through dewatering of the historical mine shaft, as well as the recovery and

off-site processing of the existing surface waste rock stockpile.

Project and permitting updates, including discussion s regarding the advanced

exploration permitting pathway, baseline studies, stockpile processing and shaft access,

are being advanced through the Indigenous Joint Steering Committee. Project-specific

consultation and engagement with Animbiigoo Zaagi’igan Anishinaabek First Nation

(AZA), Bingwi Neyaashi Anishinaabek First Nation (BNA), and Biinjitiwaabik Zaaging

Anishinaabek First Nation (BZA) ha s been initiated and will continue to inform project

planning, design and permitting activities.

In addition, as part of the Closure Plan process, LAURION will provide public notice of the

proposed Closure Plan in accordance with the direction of the Ministry of Energy and

Mines (MEM) in Ontario and the requirements of Ontario Regulation 35/24 . The public

consultation process will include public meetings.

4 | Page

Management Commentary

“Five years of rigorous, independent environmental baseline work is not a small

undertaking, and I am proud of the diligence our team and consultants have brought to

this work,” said Cynthia Le Sueur -Aquin, President and CEO of LAURION . “This stockpile

represents decades-old mining waste sitting on surface today . R ecovering potentially

economic residual mineralization within the stockpile, and doing so responsibly, is exactly

the kind of value-additive, environmentally sound project our shareholders should expect

from LAURION. We've taken the time to build a comprehensive picture of site conditions

before asking the Ministry to authorize this work, and we believe that thoroughness will

serve both the project and the communities around it well as the applications move

through review.”

“Beyond the surface stockpile project, the proposed dewatering and rehabilitation of

the historical Sturgeon River shaft is an equally important initiative for LAURION," added

Ms. Le Sueur-Aquin. “Historical records indicate the presence of gold -bearing structures

on multiple underground levels that were not fully explored prior to the cessation of

mining activities in 1942. Subject to regulatory approvals, the proposed dewatering

program is expected to provide safe underground access for geological mapping,

sampling and evaluation, allowing our technical team to better understand the

mineralized system. It is also anticipated that the program will facilitate the rehabilitation

of a long-standing legacy mine hazard under regulatory oversight. This phase of work is

exploratory in nature, and no ore will be mined, processed or sold as part of the proposed

dewatering program.”

Comments from Blue Heron Environmental

“Blue Heron has been pleased to support LAURION with the environmental baseline

studies and permitting work required to advance the Ishkōday Project,” said Linda Byron,

Director at Blue Heron Environmental. “We appreciate the hard work and commitment

demonstrated by the LAURION team throughout this process and are excited to see the

Company take this important next step in moving the project forward.”

Qualified Person

The technical contents of this press release have been reviewed and approved by Dr.

Trevor Boyd, Ph.D., P.Geo., a consultant to LAURION and a Qualified Person as defined

by National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”).

Dr. Boyd is independent of the Company within the meaning of NI 43-101.

About LAURION

LAURION Mineral Exploration Inc. is listed on the TSX Venture Exchange (LME), OTCQB

(LMEFF), and Frankfurt Stock Exchange (5YD), and is a mid -stage Canadian mineral

exploration company, focused on advancing the 100%-owned Ishkōday Gold and Base

Metal Project in Northern Ontario.

5 | Page

The Ishkōday Project covers approximately 57 km² within the prolific Beardmore –

Geraldton and Onaman–Tashota Greenstone Belts and hosts a single 6.0 km by 2.5 km

mineralised corridor. Historical and modern exploration programs have completed over

98,000 metres of drilling, confirming a large and evolving gold -rich base metal mineral

system.

LAURION’s strategy emphasizes disciplined, data -driven exploration, systematic

technical advancement, integrated geological modelling, and responsible capital

allocation. The Company is focused on strengthening geological confidence, expanding

the scale of the mineral system, and positioning the project for a potential future Mineral

Resource Estimate (“ MRE”). LAURION continues to evaluate opportunities that may

enhance project development flexibility, including potential non -dilutive initiatives such

as the evaluation of historical surface stockpile processing. The Company ’s objective is

to build technical clarity, scale, and long -term project value before monetization,

ensuring that future development decisions or strategic opportunities are supported by

strong geological foundations and reduced execution risk.

Cynthia Le Sueur -Aquin, President and CEO of LAURION, is the Company ’s largest

shareholder, holding 17,221,306 common shares, reflecting strong alignment between

management and shareholders.

For Further Information, Contact:

LAURION Mineral Exploration Inc.

Cynthia Le Sueur-Aquin – President and CEO

Tel: 1-705-788-9186 Fax: 1-705-805-9256

Douglas Vass - Investor Relations Consultant

Email: [email protected]

Website: http://www.LAURION.ca

Follow us on: X (@LAURION_LME), Instagram (laurionmineral) and LinkedIn

Caution Regarding Forward-Looking Information

This press release contains forward -looking statements, which reflect the Company ’s current expectations

regarding future events including with respect to LAURION's business, operations and condition,

management’s objectives, strategies, beliefs and intentions, the Company’s ability to advance the Ishkōday

Project and achieve the Company’s strategic and technical objectives (within the above-stated timeframes,

if at all), including with respect to the Company ’s expectations regarding the MRE, the timing and the

Company’s expectation s regarding the permitting applications and submissions described in this press

release, the nature, focus, timing and potential results of the Company's exploration, drilling and prospecting

activities, including the Company ’s planned recovery and remediation activities and the proposed

Advanced Exploration Project , as referenced in this press release, and the statements regarding the

Company’s exploration or consideration of any possible strategic alternatives and transactional

opportunities, as well as the potential outcome(s) of this process, the possible impact of any potential

transactions referenced herein on the Company or any of its sta keholders, and the ability of the Company

to identify and complete any potential acquisitions, mergers, financings or other transactions referenced

herein, and the timing of any such transactions.

The forward-looking statements involve risks and uncertainties. Actual events and future results, performance

or achievements expressed or implied by such forward-looking statements could differ materially from those

6 | Page

projected herein including as a result of a change in the trading price of the common shares of LAURION,

the failure to obtain the consents, permits and/or approvals from applicable governmental bodies, regulators

and Indigenous communities, required in connection with the Company's strategic and technical objectives,

the risk that additional drilling may not support the preparation of an MRE, the TSX Venture Exchange or any

other applicable regulator not providing its approval for any strategic alternatives or transactional

opportunities, the interpretation and actual results of current exploration activities, changes in project

parameters as plans continue to be refined, future prices of gold and/or other metals, possible variations in

grade or recovery rates, failure of equipment or processes to operate as anticipated, the failure of

contracted parties to perform, labor disputes and other risk s of the mining industry, delays in obtaining

governmental approvals or financing or in the completion of exploration, as well as those factors disclosed

in the Company’s publicly filed documents. Investors should consult the Company ’s ongoing quarterly and

annual filings, as well as any other additional documentation comprising the Company ’s public disclosure

record, for additional information on risks and uncertainties relating to these forward-looking statements. The

reader is cautioned not to rely on these forward-looking statements. Subject to applicable law, the Company

disclaims any obligation to update these forward-looking statements.

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICE PROVIDER (AS THAT TERM IS DEFINED IN

THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY

OF THE CONTENT OF THIS NEWS RELEASE.