Lion One Reports Engineering and Development Progress at the Tuvatu Alkaline Gold Project in Fiji

Corporate Updates

Lion One Reports Engineering and

Development Progress at the Tuvatu Alkaline

Gold Project in Fiji

North Vancouver, British Columbia--(Newsfile Corp. - February 8, 2022) - Lion One Metals

Limited

(TSXV: LIO) (OTCQX: LOMLF) (ASX: LLO)

("Lion One" or the "Company")

is pleased to

provide the following progress report for the engineering and development of the Company's fully

permitted high grade Tuvatu Alkaline Gold Project located on the island of Viti Levu in Fiji.

Highlights

Production permits are in place for underground gold mining operations

Engineering and procurement of gold recovery plant is underway

Development of second underground access portal is underway

Mobile crushing unit has been ordered, built, and is now being shipped to mine site

Majority of required mining equipment has been shipped and delivered to mine site

Contracts for water, power, tailings, explosives, and communications secured or in progress

ERP implementation underway for accounting, supply chain, cost control, and inventory

Mill Design & Construction

Lion One has designed a scalable milling facility with installation anticipated by Q3 2023, for initial gold

production by the end of Q4 2023. The mill has been designed with a scalable capacity to be

expandable from the initial planned production rate of 300 tonnes per day (tpd) for approximately 24,000

ounces of gold per year, ramping up to potentially 1,200 tpd.

For more information read the

Metallurgical Overview

and

Process Description

below.

Underground Development & Mining

Lion One has commenced development of the portal for underground access #2 and expects to

commence underground development at a projected rate of 2m per day during the current quarterly

period.

Several recent news releases have highlighted a number of high-grade intercepts (See

Recent Infill

Drilling Results

below) that occur in very close proximity to planned underground infrastructure,

indicating that a number of high-grade lodes are immediately accessible and can be included in the

initial mine plan. Lion One anticipates to be driving through these lodes as early as Q2 2022.

Dual-Track Advancement Strategy

Concomitant with the mine development plan being undertaken, Lion One continues to pursue

aggressive exploration drilling of newly defined feeder targets in proximity to the Tuvatu resource,

including the prolific 500 Zone, as well as regional targets within the ~6 km Navilawa caldera.

Lion One has an exceptional team to lead this effort led by Wally Berukoff, CEO, Patrick Hickey, COO

and Sergio Cattalani, SVP Exploration.

Lion One's Chief Operating Officer Patrick Hickey commented, "Lion One is committed to building a

mine at Tuvatu and we are progressing with design of the processing facilities and development of

Tuvatu decline #2, with the objective of initiating production by late 2023. At its current resource grade of

over 8 g/t Au, Tuvatu has the potential to become one of highest grade gold mines in the world, while

ongoing exploration demonstrates significant potential for identifying a large alkaline gold system within

the Navilawa Caldera".

Metallurgical Overview

Lion One has conducted and reviewed extensive metallurgical test work at numerous accredited

laboratories between 1997 and 2020, including mineralogy studies, comminution tests, gold recovery

tests and cyanide detoxification tests.

The results of this work have defined the optimum recovery

process to achieve an average gold recovery of 87.5% as reported in the September 25, 2020,

Preliminary Economic Assessment Update.

Recent metallurgical test work conducted by Met-Solve

Laboratories has indicated potential recoveries in excess of 90% are possible using the proposed

process.

The metallurgical test results indicate that the Tuvatu mineralization is amenable to a combined

process of gravity concentration with intensive cyanidation and carbon in pulp ("CIP") cyanidation.

Further refinements to the plant will be made once the detail engineering and procurement commences.

Figure 1:

conceptual process plant design and site layout

To view an enhanced version of Figure 1, please visit:

https://orders.newsfilecorp.com/files/2178/113121_5ec8ce11a40af828_001full.jpg

Process Description

Run-of-Mine ("ROM") material will be trucked from underground and onto the mill feed surge stockpiles

or directly into the crushing plant feed pocket.

The crushing plant will consist of two stages of crushing

including an open circuit primary jaw crusher and a closed-circuit secondary cone crusher.

The feed

pocket will have a 350mm-by-350mm stationary grizzly to protect the jaw crusher from oversized feed.

The cone crusher will be fed by one of two double deck screens.

One screen will be dedicated to sizing

ore and the second screen will be used to produce aggregate.

The double-deck screen undersize, with a

particle size of 80% passing approximately 8 to 10mm, will be conveyed to the mill feed surge bin, which

will provide a live capacity of 300t of the mill feed, or the equivalent of 24 hours of mill operation.

Two

vibrating feeders, together with the primary ball mill feed conveyor, will be installed underneath the surge

bin. Each of the feeders can provide the full feed rate if one of the feeders requires unplanned

maintenance.

All the feeders will be equipped with variable frequency drive ("VFD") control to adjust the

reclaim rate.

Normally only one feeding system will be in operation.

The integrated comminution circuits, including the two-stage grinding circuit, will grind the 8 to 10mm

feed to a grind size of 80% passing (P

80

) 60 to 65μm. Both mills will discharge the ground ore into a

common pump box and sent to a vibrating screen.

The 2 mm plus oversized particles will report back to

the secondary ball mill for further grinding. Undersized particles from the vibrating screen will be treated

by a primary gravity concentrator.

The gold concentrate from the primary gravity concentrator will be

treated by an intensive cyanide leaching reactor.

The pregnant gold solution from reactor will be pumped

to the on-site absorption-desorption-recovery ("ADR") plant with a dedicated electrowinning ("EW") cell

to produce a gold rich sludge to be fed into an electric furnace to produce gold doré.

The tailings from the primary gravity concentrator will be further separated by a hydrocyclone.

The

oversize from the hydrocyclone will report back to the secondary grinding mill.

The overflow containing

fines will be treated by a continuous gravity concentrator.

The approximately 1.0 to 1.8t/h gravity

concentrate from the continuous gravity concentrator will pumped to the CIP cyanide leach tanks while

the tailings will be thickened from 35% w/w solids to 45% w/w solids.

The thickener underflow will be

pumped to an aerated pre-treatment tank prior to entering the CIP circuit.

This process utilizes gravity

separation for 100% of the ore instead of the conventional 33%.

Since the Tuvatu mineralization contains

variable quantities of large and very small free gold, this process optimizes overall gold recovery.

The standard CIP cyanide circuit will operate at 45% w/w solids with the carbon being loaded

countercurrent to the flow of the pulp.

The gold loaded carbon will be transferred to the ADR plant for

desorption and recovery.

The leaching tanks, buffer tank and associated pumps will be located in a

concrete tank farm.

The reagent storage and mixing facilities will be located adjacent to the CIP circuit.

The Project will employ an alkaline, non-cyanide stripping and EW process.

The pressurized elution

vessel for the CIP circuit will operate at approximately 0.5MPa at 150˚C and have dedicated EW cell

located adjacent to the dedicated intensive leach EW cell.

After the ADR system is shut down and the

system pressure is reduced to atmospheric pressure, the gold rich sludge will be washed from the steel

cathodes and collected. The gold sludge will be dried and mixed with gold flux prior to melting in an

electric furnace at approximately 1,200 to 1,300°C to produce gold doré. The gold doré will be stored in

a secure vault within a secure and supervised area.

The leach residue from the carbon safety screen in the CIP circuit will flow by gravity to a residual

cyanide detoxification system where Weak Acid Dissociable ("WAD") cyanide will be destroyed using

the SO2/air process. The circuit will consist of two mechanically agitated tanks, each with a capacity to

handle the full slurry flow for a retention time of approximately 75 minutes. The arrangement will provide

sufficient detoxification capacity if one of the two tanks require unplanned maintenance. The reagents

used will include hydrated lime, sodium metabisulphite, and copper sulphate. After detoxification, the

tailings slurry will be pumped to high-rate thickener.

The residue will be thickened to approximately 50 to

55% w/w solids.

Diluted flocculant solution will be added to the thickener to assist the thickening

process.

The thickener underflow will be pumped to two filter presses for dewatering to approximately 10

to 12% w/w solids. The filtered tailings cake will be loaded into lined dump trucks for transporting to the

Tailings Storage Facilities ("TSF") approximately 3.5km from the plant site.

Engineering of the TSF has

been completed for the first year of operation with subsequent TSF construction planned the following

year after start-up.

It is necessary for Lion One to provide all electrical power to the mine site.

The proposed new main

power plant is five 800kW diesel powered generators with 4 in operation and 1 on standby.

The 2

existing 900kVA diesel generators for underground development will be relocated to the main power

plant.

The combined power output will be 4,660kW (with one 800kW standby) to run both the

underground mining operation and the process plant.

The Company is also investigating the installation

of a hybrid power plant consisting of a combination of solar and diesel generation to maintain a constant

and stable supply of 4,660kW at any time within 24 hours a day.

Photo 1:

design for portal of underground access no. 2

To view an enhanced version of Photo 1, please visit:

https://orders.newsfilecorp.com/files/2178/113121_5ec8ce11a40af828_002full.jpg

Photo 2:

blasting for development of underground access no.2

To view an enhanced version of Photo 2, please visit:

https://orders.newsfilecorp.com/files/2178/113121_5ec8ce11a40af828_003full.jpg

Recent Infill Drilling Results

Reported Jan. 25, 2022:

359.8 g/t Au over 1.8m, including 1,616 g/t Au over 0.4m

Reported Nov. 30, 2021:

33.52 g/t Au over 2.4m from 173.4m

inc. 185.6 g/t Au over 0.4m

20.61 g/t Au over 7.5m from 126.6m

inc. 89.03 g/t Au over 1.5m, and 227.3 g/t Au over 0.3m

21.34 g/t Au over 2.5m from 120.85m

inc. 38.25 g/t Au over 1.3m, and 52.27 g/t Au over 0.3m

Reported Sept. 7, 2021:

10.24 g/t Au over 8.48m inc. 33.26 g/t Au over 2.44m from 111.2m, and

13.49 g/t Au over 3.3m from 115.4m

The current mineral resource estimate for the Tuvatu project comprises 1,007,000 tonnes Indicated at

8.48 g/t Au (274,600 oz. Au) and 1,325,000 tonnes inferred at 9.0 g/t Au (384,000 oz. Au) at a cut-off

grade of 3.0 g/t Au.

The Company advises that it has not based its current mine development plan on a feasibility study of

mineral reserves, demonstrating economic and technical viability, and, as a result, there may be an

increased uncertainty of achieving any particular level of recovery of minerals or the cost of such

recovery, including increased risks associated with developing a commercially mineable deposit.

Qualified Person

The scientific and technical content of this news release has been reviewed, prepared, and approved by

Mr. Bill Witte, P. Eng, who is a Qualified Person pursuant to National Instrument 43-101 - Standards of

Disclosure for Mineral Projects ("NI-43-101).

About Tuvatu

The Tuvatu gold deposit is located on the island of Viti Levu in the South Pacific island nation of Fiji. The

mineral resource for Tuvatu as disclosed in the technical report "Tuvatu Gold Project PEA", dated June

1, 2015, and prepared by Mining Associates Pty Ltd of Brisbane Qld, and subsequently updated in

January 2018 as disclosed in the technical report and PEA by Tetra Tech "Technical Report and

Preliminary Economic Assessment Update for the Tuvatu Gold Project, The Republic of Fiji"

dated

September 2020, comprises 1,007,000 tonnes Indicated at 8.48 g/t Au (274,600 oz. Au) and 1,325,000

tonnes inferred at 9.0 g/t Au (384,000 oz. Au) at a cut-off grade of 3.0 g/t Au.

The technical report is

available on the Lion One website at

www.liononemetals.com

and on the SEDAR website at

www.sedar.com

.

About Lion One Metals Limited

Lion One's flagship asset is 100% owned, fully permitted high grade Tuvatu Alkaline Gold Project,

located on the island of Viti Levu in Fiji. Lion One envisions a low-cost high-grade underground gold

mining operation at Tuvatu coupled with exciting exploration upside inside its tenements covering the

entire Navilawa caldera, an underexplored yet highly prospective 7km diameter volcanic edifice of

alkaline affinity. Lion One's CEO Walter Berukoff leads an experienced team of explorers and mine

builders and has owned or operated over 20 mines in 7 countries.

As the founder and former CEO of

Miramar Mines, Northern Orion, and La Mancha Resources, Walter is credited with building over $3

billion of value for shareholders.

On behalf of the Board of Directors of

Lion One Metals Limited

"

Walter Berukoff

"

Chairman and CEO

For further information

Contact Investor Relations

Toll Free (North America) Tel: 1-855-805-1250

Email:

[email protected]

Website:

www.liononemetals.com

Neither the TSX Venture Exchange nor its Regulation Service Provider

accepts responsibility for the adequacy or accuracy of this release.

This press release may contain statements that may be deemed to be "forward-looking statements"

within the meaning of applicable Canadian securities legislation. All statements, other than

statements of historical fact, included herein are forward looking information. Generally, forward-

looking information may be identified by the use of forward-looking terminology such as "plans",

"expects" or "does not expect", "proposed", "is expected", "budget", "scheduled", "estimates",

"forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words

and phrases, or by the use of words or phrases which state that certain actions, events or results may,

could, would, or might occur or be achieved. This forward-looking information reflects Lion One Metals

Limited's current beliefs and is based on information currently available to Lion One Metals Limited

and on assumptions Lion One Metals Limited believes are reasonable. These assumptions include,

but are not limited to, the actual results of exploration projects being equivalent to or better than

estimated results in technical reports, assessment reports, and other geological reports or prior

exploration results. Forward-looking information is subject to known and unknown risks, uncertainties

and other factors that may cause the actual results, level of activity, performance or achievements of

Lion One Metals Limited or its subsidiaries to be materially different from those expressed or implied

by such forward-looking information. Such risks and other factors may include, but are not limited to:

the stage development of Lion One Metals Limited, general business, economic, competitive,

political and social uncertainties; the actual results of current research and development or

operational activities; competition; uncertainty as to patent applications and intellectual property

rights; product liability and lack of insurance; delay or failure to receive board or regulatory approvals;

changes in legislation, including environmental legislation, affecting mining, timing and availability of

external financing on acceptable terms; not realizing on the potential benefits of technology;

conclusions of economic evaluations; and lack of qualified, skilled labour or loss of key individuals.

Although Lion One Metals Limited has attempted to identify important factors that could cause actual

results to differ materially from those contained in forward-looking information, there may be other

factors that cause results not to be as anticipated, estimated or intended. Accordingly, readers should

not place undue reliance on forward-looking information. Lion One Metals Limited does not undertake

to update any forward-looking information, except in accordance with applicable securities laws.

To view the source version of this press release, please visit