Lion One Drills Further Wide and High Grade Intersections and Continues to Extend HT Corridor at Tuvatu in Fiji

Drill Results

Lion One Drills Further Wide and High Grade

Intersections and Continues to Extend HT Corridor at

Tuvatu in Fiji

North Vancouver, British Columbia--(Newsfile Corp. - October 16, 2017) -

Lion One Metals Limited

(TSX-V: LIO) (ASX: LLO)

(OTCQX: LOMLF) (FSE: LY1)

(

the

"Company")

is pleased to announce that its ongoing diamond drilling program has returned

further high grade gold intersections at its 100% owned and fully permitted high grade underground Tuvatu Gold Project located

near Nadi on the island of Viti Levu in the Republic of Fiji.

Recent Drill Highlights

1

Drill results continue to

expand the HT Corridor mineralisation with wider

(up to ~8 meters true width) and

high-

grade intersections

11

meters

averaging 9.1g/t gold from 80.8

meters

including:

5.2

meters

averaging 15.3g/t gold

4.8

meters

averaging 20.3g/t gold from 21.5

meters

including:

1.8

meters

averaging 51.8g/t gold

4.5

meters

averaging 7.1g/t gold from 214.5

meters

including:

1.8

meters

averaging 15.0g/t gold

Mineralisation extends from surface

and in close proximity to current decline

with potential to add

to the initial

early

mine-p

lan

Current Drill Program

Drill results have been received from a further three diamond drill holes (TUDDH463, 467 and 469) completed on extensions to

the Tuvatu Gold Project. These drill holes targeted the individual mineralised lodes within the recently recognised and potentially

significant HT Corridor mineralisation. Please refer to Figures 1 and 2, and Tables 1, 2 and 3 for drill hole details.

HT Corridor Mineralisation

: a zone of growing significance

The previous resource estimate for Tuvatu included generally lower grade mineralisation in lodes named T1, T2, H1 and H2 and

as announced in the NI43-101 resource estimate on 4 June 2014.

Prompted by a reinterpretation and the recognition of high-

grade mineralisation at surface, the Company returned to this area for further drilling in 2017. Other results from this current

program have included

2.77

meters

averaging

35.08g

/t

,

3.4

meters

averaging 23.2g/t

gold

and refer to releases dated 22

August 2017 and 15 September 2017 for further details.

Figure 1: Tuvatu Gold

Project

2016/7 Diamond Drilling Program with Current Drilling Target Area

To view an enhanced version of Figure 1, please visit:

http://orders.newsfilecorp.com/files/2178/29696_a1508124335513_8.jpg

The current mine plan derives most of its inventory from the UR lodes which are narrow high-grade structures oriented north-

south and form along cracks in the host monzonite rock. The zone hosting the T and H lodes has been named the HT Corridor.

The HT Corridor mineralization is of a different nature to the UR lodes and includes highly fractured, brecciated and wider zones

of mineralisation striking northwest-southeast and dipping steeply to the northeast. The HT Corridor is characterised by a distinct

biotite and potassium feldspar alteration which has enabled mapping of the corridor for over a kilometers to the northwest and 2

kilometers to the southeast of the existing drilling. The mineralisation identified in the 2017 drilling to date remains open in both

directions along strike and also down dip.

Figure 2: HT Zone of

Mineralization

outlined by Drilling

,

Mapping

and Trenching

To view an enhanced version of Figure 2, please

visit:

http://orders.newsfilecorp.com/files/2178/29696_a1508124335856_15.jpg

Mining significance

The contribution of the T and H lodes to the current mine-plan is minimal due to the 2014 modelled grades in this area,

However,

with the new higher-grade and wider mineralisation intersections, the Company expects that the overall grade and tonnage of the

mineralisation in this area will increase. Furthermore, these mineralized zones extend from surface and crosscut the existing

decline and hence have the potential to be exploited early in the mine-plan.

The Company looks forward to announcing further drill results as and when they are received and compiled from the current drill

program and, in time, a revised mine plan and mining inventory that includes this new discovery.

Table 1: Diamond Drill Results

reported on in this News Release

Drill Hole

From (m)

To

(m)

Interval

(m)

True Width

(m)

Au

(g/t)

Lode

TUDDH 463

3.34

3.70

0.36

0.25

8.01

UR2

80.79

91.80

11.01

7.79

9.08

T1

incl

81.42

86.60

5.18

3.66

15.30

T1

116.70

118.40

1.70

1.20

1.57

T2

127.35

130.02

2.67

1.89

3.12

T2

TUDDH 467

124.60

125.10

0.50

0.33

6.91

H1

133.80

134.05

0.25

0.17

26.36

H1

191.70

199.45

7.75

5.19

1.19

T1

214.45

218.90

4.45

2.98

7.13

T2

incl

216.15

217.90

1.75

1.17

14.96

T2

TUDDH 469

16.05

18.64

2.59

0.89

4.42

T2

incl

16.80

17.80

1.00

0.34

10.40

T2

21.50

26.27

4.77

1.63

20.29

T1

incl

22.95

24.78

1.83

0.63

51.84

T1

50.82

51.05

0.23

0.08

11.53

H1

53.60

55.57

1.97

0.67

3.47

H1

88.90

90.60

1.70

0.58

1.49

H2

88.90

90.60

1.70

0.58

1.49

H2

Notes

:

Intersections reported here are often composite samples.

Results reported here only include those which returned single intervals or composited intervals of

> 2 gram.meters.

T

hose intervals highlighted have returned results of

>15gram.meters

TUDDH prefix denotes diamond drill holes drilled from the surface.

Table 2:

Drill Hole Logistics from the Current Reported Holes

Hole Number

Northing

Easting

Depth

RL

Azimuth

Dip

TUDDH 463

3921005.94

1876503.13

137.60

227.7

234

-65.0

TUDDH 467

3921031.86

1876516.43

230.60

216.31

234

-68.0

TUDDH 469

3921069.33

1876363.29

190.60

184.41

095

-65.0

Notes:

For surface diamond drill holes, up to 26 meters of the poorly consolidated surface material was drilled using PQ3 (83.0mm

core diameter) diamond core with remainder of the hole drilled with HQ3 (61.1mm core diameter) diamond core.

Downhole surveys are carried out using a Ranger Explorer Mark 2 electronic multi-shot camera.

Downhole surveys are taken at least once every 30 m.

Table

3

: Diamond Drill Results

from this mineralized zone reported in Previous News Releases

Drill Hole

From (m)

To

(m)

Interval

(m)

True Width

(m)

Au

(g/t)

Lode

TUDDH 442

42.59

46.25

3.66

3.00

1.74

H1

49.20

51.97

2.77

2.27

35.08

H2

57.13

59.70

2.57

2.11

2.02

T1

62.55

65.77

3.22

2.64

6.83

T2

TUDDH 448

8.60

9.40

0.80

0.27

8.27

H2

13.43

14.20

0.77

0.26

4.08

H2

20.80

21.23

0.43

0.15

6.48

H2

24.95

30.22

5.27

1.80

2.54

H2

41.70

42.30

0.60

0.21

2.32

H2

50.80

53.37

2.57

0.88

2.69

H2

TUDDH 449

15.10

18.60

3.50

2.68

6.00

T1

33.64

34.45

0.81

0.62

2.26

T2

TUDDH 450

70.54

72.00

1.46

1.26

1.41

H2

TUDDH 452

26.96

31.73

4.77

3.65

2.14

T1

incl

31.38

31.73

0.35

0.27

15.40

T1

39.23

44.10

4.87

3.73

1.13

T2

TUDDH 453

63.00

68.80

5.80

1.98

5.93

H1

63.25

65.25

2.00

0.68

13.40

H1

70.30

82.85

12.55

4.29

2.73

H1

incl

80.40

82.85

2.45

0.84

6.02

H1

88.05

90.50

2.45

0.84

5.27

H1

TUDDH 454

62.10

67.90

5.80

5.02

1.39

T2

TUDDH 455

38.80

39.50

0.70

0.24

6.17

T2

TUDDH 458

80.20

82.70

2.50

1.92

1.39

H1

89.70

90.9

1.20

0.92

10.17

H2

TUDDH 459

75.65

79.55

3.90

2.99

9.55

H1

incl

76.70

78.65

1.95

1.49

14.97

H1

TUDDH 461

58.90

62.30

3.40

2.4

23.24

T1

68.60

69.28

0.68

0.48

2.10

T1

78.97

80.30

1.33

0.94

4.37

T2

82.20

82.85

0.65

0.46

2.72

T2

TUDDH 462

67.50

71.10

3.60

2.55

1.95

T1

87.60

93.33

5.73

4.05

3.21

T1

incl

92.50

93.33

0.83

0.59

10.71

T2

95.60

97.00

1.40

0.99

3.42

T2

Notes:

This Table includes results from diamond drill holes reported on in previous Lion One news releases from the same

mineralized zone

.

For these diamond drill holes, up to 26 meters of the poorly consolidated surface material was drilled using

PQ3 (83.0mm core diameter) diamond core with remainder of the hole drilled with HQ3 (61.1mm core diameter) diamond

core. Downhole surveys are carried out using a Ranger Explorer Mark 2 electronic multi-shot camera. Downhole surveys are

taken at least once every 30 m.

About Tuvatu | Lion One |

Fiji Gold

Lion One is advancing its 100% owned Tuvatu Gold Project as a near-term production opportunity in Fiji. Tuvatu is a low-

sulphidation epithermal gold system and has a comparable footprint and geological analogies to other high grade epithermal

gold deposits in the Pacific Ring of Fire such as Porgera and Lihir in PNG, and Vatukoula in Fiji. Tuvatu has been fully permitted

by the Government of Fiji for operations start-up and has a dual-track strategy of production development and resource

expansion inside its 385 hectare mining lease and on its wider extensive land-holdings in the area.

Tuvatu is located 17 km from the international airport in Nadi, on the west coast of Viti Levu in the Republic of Fiji. Lion One's

CEO Walter Berukoff is leading an experienced team of mine builders, and has owned or operated over 20 mines in 7

countries.

As the founder and former CEO of Miramar Mines, Northern Orion, and La Mancha Resources, Mr Berukoff is

credited with building over $3 billion of value for shareholders.

Tuvatu was advanced by previous owners through underground exploration and development from 1997 through to the

completion of a feasibility study in 2000.

Acquired by Lion One in 2011, the project has over 110,000 meters of drilling

completed to date in addition to 1,430 meters of underground development.

In January 2016 the Hon. Prime Minister of Fiji, Mr.

V. Bainimarama, formally presented the previously granted Tuvatu Mining Lease to Lion One.

This concluded the permitting

process for the development of an underground gold mine and processing plant at Tuvatu, demonstrating strong government

support for Fiji's 85 year-old gold mining industry.

As per its independent June 1, 2015 NI 43-101 PEA Technical Report on the Tuvatu Gold Project, the Company envisages a low

cost underground gold mining operation producing an initial estimate of ~353,000 ounces of gold at head grades of 11.3 g/t Au

over an initial 7 year mine life.

Estimated cash cost is US$567 per ounce with all-in sustaining cost of US$779 per ounce. Total

capex of US$48.6 million includes a contingency of US$6.1 million with an 18 month preproduction schedule and 18 month

payback on capital.

At a US$1,200 gold price, the project generates net cash flow of US$112.6 million and an IRR of 52% (after

tax).

The Company is not basing its production decision on a feasibility study of mineral reserves demonstrating economic and

technical viability; as a result there is increased uncertainty and economic and technical risks associated with its production

decision.

Mine engineering and underground development is progressing alongside final detailed engineering for the Tuvatu processing

plant and site infrastructure. The Company has now dewatered the existing Tuvatu exploration decline to 560 meters from the

portal down the decline. The decline was completed in the year 2000 by Emperor Gold Mines, comprising 1,430 meters of

underground development including drives, cross cuts and raises. In conjunction with the dewatering, ventilation fans and lighting

were installed early in 2017 and are running 24 hours per day. The rehabilitation of the decline is ongoing as dewatering

progresses, but in general the stability and ground conditions have been shown to be very good. The areas of rehabilitation and

regularly reviewed and approved by Mine Inspectors from Fiji's Mineral Resource Department.

Competent Persons

and QP

Statement

Information in this announcement relating to exploration drilling at the Tuvatu project is based on data compiled by Lion

One's Managing Director, Mr Stephen Mann, who is a member of The Australasian Institute of Mining and Metallurgy.

Mr.

Mann is the Qualified Person ("QP") responsible for the Tuvatu exploration program and has prepared and approved the

technical information in this news release.

Mr. Mann has sufficient experience which is relevant to the style of mineralization

and type of deposit under consideration and to the activity which they are undertaking to qualify as Competent Persons under

the 2012 Edition of the Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr

Mann consents to the inclusion of the data in the form and context in which it appears.

The Tuvatu Mineral Resources have been estimated by Mining Associates, an external consultancy, and are previously reported

under the 2012 Edition of the Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves (see

LOL -ASX announcement 4

June 2014 titled "Lion One Announces Revised NI 43-101 Resource Estimate: Increased Tonnage

and Grade at the Tuvatu Gold Project, Fiji"). The Company confirms that it is not aware of any new information or data that

materially affects the information included in the original market announcements and, in the case of estimates of Mineral

Resources that all material assumptions and technical parameters underpinning the estimate in the relevant market

announcement continue to apply and have not materially changed. The company confirms that the form and context in which the

Competent Person's findings are presented have not materially modified from the original market announcements.

The Tuvatu historical exploration results have been sourced from data collected by previously listed companies which have

undergone a number of peer reviews by qualified consultants, who conclude that the resources comply with the JORC code and

are suitable for public reporting. This information was prepared and first disclosed under the JORC Code 2004. It has not been

updated since to comply with the JORC Code 2012 on the basis that the information has not materially changed since it was last

reported.

For more information on Lion One including technical reports please visit the Company's website at

www.liononemetals.com

or

the SEDAR website at

www.sedar.com

.

On behalf of Lion One Metals Limited

"Walter H. Berukoff"

Chief Executive Officer

For further information please contact

Stephen Mann, Managing Director (Perth, Australia) Tel: 604-973-3007

Hamish Greig, Vice President (North Vancouver, BC) Tel: 604-973-3008

Joe Gray, Investor Relations (North Vancouver, BC) Tel: 604-973-3004

Toll Free IR Line (North America) Tel: 1-855-805-1250

Email:

[email protected]

Neither the TSX Venture Exchange nor its Regulation Service Provider accepts responsibility for the adequacy or

accuracy of this release.

This press release may contain "forward-looking information" within the meaning of applicable Canadian securities

legislation. All statements, other than statements of historical fact, included herein are forward looking information. Generally,

forward-looking information may be identified by the use of forward-looking terminology such as "plans",

"expects" or "does

not expect", "proposed", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not

anticipate", or "believes", or variations of such words and phrases, or by the use of words or phrases which state that certain

actions, events or results may, could, would, or might occur or be achieved. This forward-looking information reflects Lion

One Metals Limited's current beliefs and is based on information currently available to Lion One Metals Limited and on

assumptions Lion One Metals Limited believes are reasonable. These assumptions include, but are not limited to, the actual

results of exploration projects being equivalent to or better than estimated results in technical reports, assessment reports,

and other geological reports or prior exploration results. Forward-looking information is subject to known and unknown risks,

uncertainties and other factors that may cause the actual results, level of activity, performance or

achievements of Lion One

Metals Limited or its subsidiaries to be materially different from those expressed or implied by such forward-looking

information. Such risks and other factors may include, but are not limited to: the early stage development of Lion One Metals

Limited, general business, economic, competitive, political and social uncertainties; the actual results of current research

and development or operational activities; competition; uncertainty as to patent applications and intellectual property rights;

product liability and lack of insurance; delay or failure to receive board or regulatory approvals; changes in legislation,

including environmental legislation, affecting mining, timing and availability of external financing on acceptable terms; not

realizing on the potential benefits of technology; conclusions of economic evaluations; and lack of qualified, skilled labor or

loss of key individuals. Although Lion One Metals Limited has attempted to identify important factors that could cause actual

results to differ materially from those contained in forward-looking information, there may be other factors that cause results

not to be as anticipated, estimated or intended. Accordingly, readers should not place undue reliance on forward-looking

information. Lion One Metals Limited does not undertake to update any forward-looking information, except in accordance

with applicable securities laws.

1

Intersections rounded to nearest 0.1 meter and 0.1g/t. Refer to Table 1 for full details.