VANCOUVER, BRITISH COLUMBIA, September 16, 2026 – American Lithium Corp. (“American Lithium” or

the “Company”) (TSX-V:LI | OTCQX:AMLIF | Frankfurt:5LA1) is pleased to report that the Falchani Lithium

Project pilot-plant has all systems installed and operating. Recent laboratory testing has demonstrated an

improvement in lithium recoveries. The pilot-plant, being advanced by TECMMINE in Lima, Peru, marks a

key milestone toward derisking the Falchani project by validating the flowsheet at scale.

Highlights:

• The pilot -plant is fully installed with the various components presently being tested with

operating systems performing as expected.

• Latest laboratory bench test work run using pilot plant equipment in a semi-continuous process

achieved average lithium extraction of 88.7% (range: 88.0% –89.9%), well above the 80.0%

recovery utilized in the February 2024 PEA. (1)

• With all flow sheet equipment now installed and tested, the Company is advancing toward full

end-to-end flowsheet validation - at scale in a continuous mode, to validate the bench -scale

results.

• The pilot-plant is expected to run continuously at target rates for 3+ months, processing 6 –10

tonnes of Falchani mineralization.

• Pilot plant results will feed into the future project feasibility work.

Dr. Laurence Stefan, President and COO, commented: "The results from the key core processing stages

have been very encouraging. The consistency we are seeing gives us strong confidence as we move rapidly

toward full pilot plant operations. Every stage we bring online has added to our understanding of how this

deposit will perform at scale, optimizing to build on the promising recent results.”

The Company initially prioritized commissioning the plant's core systems and are all operational and per-

forming as expected. The key core systems are — impurity removal, controlled cooling, pre-neutralization,

neutralization, crystallization, centrifugal separation, and consumables' reaction management — all now

individually validated. Recent laboratory bench test work that used individual components of the pilot -

plant in a semi-continuous flow sheet (mainly crystallizers and evaporator) delivered very consistent re-

sults. Lithium losses across the alum crystallization, pre-neutralization, neutralization, mechanical evapo-

ration, and precipitation stages were reduced to fractions of a percent per phase, driving the 88.7% overall

lithium recovery, which is above the PEA recovery rate noted above. (1)

Falchani's volcanic-hosted lithium mineralization has naturally low impurities, supporting a simple flow-

sheet capable of producing battery-grade lithium carbonate exceeding 99.5% purity.

Figure 1: Partial View of the Pilot Plant. More Images Here

Qualified Person

Mr. Ted O'Connor, P.Geo., a Director of American Lithium, and a Qualified Person as defined by National

Instrument 43-101 Standards of Disclosure for Mineral Projects, has reviewed and approved the scientific

and technical information contained in this news release.

About TECMMINE

TECMMINE E.I.R.L. is a Peruvian metallurgical consulting company based in Lima, Peru with mineral

processing and metallurgical testing laboratory facilities and experienced metallurgical personnel led by

Eng. Jose Malqui.

About American Lithium

American Lithium is developing two of the world’s largest, advanced -stage lithium projects, along with

the largest undeveloped uranium project in Latin America. They include the TLC claystone lithium project

in Nevada and the Falchani hard -rock lithium pro ject in southern Peru, which also hosts a globally

significant cesium resource, as well as the Macusani uranium project located in the same region. All three

projects have completed robust preliminary economic assessments, exhibit significant expansion

potential and enjoy strong community support.

For more information, please contact the Company at [email protected] or visit our website

at www.americanlithiumcorp.com.

Follow us on Facebook, Twitter and LinkedIn.

On behalf of the Board of Directors of American Lithium Corp.

“Alex Tsakumis”

Chief Executive Officer

Tel: 604 428 6128

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press

release.

(1)Cautionary Note Regarding PEA

Certain technical information in this News Release refers to the results of the PEA prepared for the Project.

PEAs are preliminary in nature and include inferred mineral resources that are considered too speculative

geologically to have the economic considerations applied to them that would enable them to be catego-

rized as mineral reserves. There is no certainty the results of the PEA’s will be realized. Mineral resources

are not mineral reserves and do not have demonstrated economic viability. Additional work is required to

upgrade the mineral resources to mineral reserves. In addition, t he mineral resource estimates could be

materially affected by environmental, geotechnical, permitting, legal, title, taxation, socio -political, mar-

keting, or other relevant factors.

Cautionary Statement Regarding Forward Looking Information

This news release contains certain forward -looking information and forward -looking statements

(collectively “forward -looking statements”) within the meaning of applicable securities legislation. All

statements, other than statements of historical fact, are forward-looking statements. Forward -looking

statements in this news release include, but are not limited to, statements regarding the business plans,

expectations and objectives of American Lithium. Forward-looking statements are frequently identified by

such words as "may", "will", "plan", "expect", "anticipate", "estimate", "intend", “indicate”, “scheduled”,

“target”, “goal”, “potential”, “subject”, “efforts”, “option” and similar words, or the negative connotations

thereof, referring to future events an d results. Forward -looking statements are based on the current

opinions and expectations of management and are not, and cannot be, a guarantee of future results or

events. Although American Lithium believes that the current opinions and expectations reflec ted in such

forward-looking statements are reasonable based on information available at the time, undue reliance

should not be placed on forward-looking statements since American Lithium can provide no assurance that

such opinions and expectations will pro ve to be correct. All forward -looking statements are inherently

uncertain and subject to a variety of assumptions, risks and uncertainties, including risks, uncertainties

and assumptions related to: American Lithium’s ability to achieve its stated goals;, which could have a

material adverse impact on many aspects of American Lithium’s businesses including but not limited to:

the ability to access mineral properties for indeterminate amounts of time, the health of the employees or

consultants resulting in de lays or diminished capacity, social or political instability in Peru which in turn

could impact American Lithium’s ability to maintain the continuity of its business operating requirements,

may result in the reduced availability or failures of various local administration and critical infrastructure,

reduced demand for the American Lithium’s potential products, availability of materials, global travel

restrictions, and the availability of insurance and the associated costs; the ongoing ability to work

cooperatively with stakeholders, including but not limited to local communities and all levels of

government; the potential for delays in exploration or development activities; the interpretation of drill

results, the geology, grade and continuity of mineral deposits; the possibility that any future exploration,

development or mining results will not be consistent with our expectations; risks that permits will not be

obtained as planned or delays in obtaining permits; mining and development risks, including risks related

to accidents, equipment breakdowns, labour disputes (including work stoppages, strikes and loss of

personnel) or other unanticipated difficulties with or interruptions in exploration and development; risks

related to commodity price and foreign exchange rate fluctuations; risks related to foreign operations; the

cyclical nature of the industry in which American Lithium operates; risks related to failure to obtain

adequate financing on a timely basis and on acceptable terms or delays in obtaining governmental

approvals; risks related to environmental regulation and liability; political and regulatory risks associated

with mining and exploration; risks related to the uncertain global economic environment and the effects

upon the global market generally, any of which could continue to negatively affect global financia l

markets, including the trading price of American Lithium’s shares and could negatively affect American

Lithium’s ability to raise capital and may also result in additional and unknown risks or liabilities to

American Lithium. Other risks and uncertainties related to prospects, properties and business strategy of

American Lithium are identified in the “Risk Factors” section of American Lithium’s Management’s

Discussion and Analysis filed on July 30, 2026, and in recent securities filings available at

www.sedarplus.ca. Actual events or results may differ materially from those projected in the forward -

looking statements. American Lithium undertakes no obligation to update forward -looking statements

except as required by applicable securities laws. Investors s hould not place undue reliance on forward -

looking statements.