Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LGD.TO ·

Liberty Gold Announces Positive Preliminary Economic Assessment for the Goldstrike Oxide Gold Deposit, Great Basin, USA Post-tax NPV5% of US$129.5 million, IRR of 29.4%, and Initial Capex of US$113.2 million

Economic Studies

Page 1 of 10

NEWS RELEASE 18-12 July 10, 2018

Liberty Gold Announces Positive Preliminary Economic Assessment for the

Goldstrike Oxide Gold Deposit, Great Basin, USA

Post-tax NPV5% of US$129.5 million, IRR of 29.4%, and Initial Capex of US$113.2 million

VANCOUVER, B.C. – Liberty Gold Corp. (LGD - TSX) ("Liberty Gold" or the "Company") is pleased to

announce the results of a Preliminary Economic Assessment (“PEA”) at its Goldstrike oxide gold

property, Utah. The PEA utilizes the maiden resource estimate completed in February 2018 (see

news release dated February 8, 2018), and provides a strong, base-case economic scenario upon

which to expand the scope and scale of the project with ongoing drilling. The PEA confirms a low

capital intensity, low operating cost, open-pit, run-of-mine, heap-leach operation, with a 7.5 year mine

life and highly attractive economics.

“This positive PEA marks a solid milestone for the Goldstrike project and for Liberty Gold,” stated Cal

Everett, President and CEO of Liberty Gold. “Importantly, it is based on a high degree of confidence in

the deposit geometry because it is backed up by over 1,700 drill holes with 75% of the resource in the

indicated category. There is a high level of certainty in the metallurgical assumptions, as they are

consistent with historical recoveries obtained from 209,000 ounces of historical production between

1988 and 1994. The PEA does not include any potential benefits from by-product silver production or

from processing residual gold remaining in the historical heap leach pads, which are currently being

drill-tested. A gold cut-off grade of 0.20 grams per tonne (“g/t”) was selected for this study, in contrast

to 0.25 g/t used in the original resource estimate. The lower cut-off improves the economics of the

project, delivers a lower strip ratio, produces more ounces, and extends the mine life. We see this

project as scalable in terms of both size and throughput through future additions to the resource base,

moving us closer to our goal of becoming a 100,000+ ounce per year producer.”

PEA Highlights

The base case assumes a gold price of US$1,300/ounce (“oz”). All figures are stated in U.S. Dollars

(“$”) unless otherwise noted. The Technical Report pursuant to National Instrument (“NI”) 43-101

guidelines for the Preliminary Economic Assessment will be filed on SEDAR within 45 days.

• After-tax Net Present Value at a 5% discount rate (“NPV5%”) and Internal Rate of Return (“IRR”)

of $129.5 million and 29.4% respectively with a 2.3 year payback of initial capital (pre-tax

NPV5% and IRR of $176.2 million and 34.8% respectively)

• Mine life of 7.5 years with a 2 year pre-production period

• Life of mine (“LOM”) head grade of 0.48 g/t gold

• Low LOM Strip Ratio of 1.2:1

• Total amount of gold recovered is estimated at 713,000 oz

• Average annual gold production of approximately 95,000 oz

Page 2 of 10

• Peak annual gold production of approximately 117,000 oz

• LOM direct operating cash cost1 is estimated at $642/oz of gold recovered

• All-in sustaining cost or AISC2 is estimated at $793/oz of gold recovered

• Pre-production capital cost estimated at $113.2 million, using an owner-operator approach

• LOM sustaining capital costs estimated at $61.6 million, plus $20.0 million for closure costs

1 Cash cost includes mining cost, mine-level G&A, leaching and refining cost

2 All-in sustaining cost (AISC) includes adjusted cash cost per ounce, sustaining capital and closure costs. This is a non-GAAP

performance measure; please see “Non-GAAP Measures and Other Financial Measures” below.

The PEA was prepared by SRK Consulting (Canada) Inc., of Vancouver, British Columbia (“SRK”),

Golder Associates Inc. of Reno, Nevada (“Golder”), Kappes Cassiday and Associates of Reno,

Nevada (“Kappes”), Advantage Geoservices of Osoyoos, British Columbia and GL Simmons

Consulting LLC of Larkspur, Colorado.

The PEA is preliminary in nature and includes inferred mineral resources that are too speculative

geologically to have economic considerations applied to them that would enable them to be

categorized as mineral reserves. There is no certainty that PEA results will be realized. Mineral

resources are not mineral reserves and do not have demonstrated economic viability.

PEA Overview

Goldstrike hosts disseminated gold mineralization similar to deposits on the Carlin Trend, with strong

oxidation in most areas.

The PEA envisions recovery of gold and silver from the Goldstrike mineralized material using a run of

mine (“ROM”) heap-leach circuit. The ROM material will be leached with a dilute cyanide solution, and

the leached gold will be recovered from solution using a carbon adsorption circuit followed by

electrowinning and refining in a furnace to produce doré bars.

Important project metrics are presented in the following tables.

Assumptions

Gold Price $1300/oz

Production Profile

Total Tonnes of Mineralized Material Mined and Processed 59.3 million tonnes

Total Tonnes Waste Mined 70.6 million tonnes

Head Grade 0.48 g/t

Mine Life 7.5 years

Page 3 of 10

Tonnes per Day Mineralized Material Mined 22,500 tonnes per day

Strip Ratio (Waste:Mineralized Material) 1.2:1

Average Gold Recovery 78%

Total Gold Ounces Mined 915,516 oz

Total Gold Ounces Recovered 713,000 oz

Average Annual Gold Production 95,000 oz

Peak Annual Gold Production 117,855 oz

Unit Operating Costs

LOM Average Cash Cost1 $642/oz

LOM Average Adjusted Cash Cost2 $675/oz

LOM Cash Cost plus Sustaining Cost (AISC)3 $793/oz

Project Economics

Royalties (estimate; royalties differ slightly by location and gold price) 2.50%

Pre-tax NPV5%/ After-Tax NPV5% $176.2 million/$129.5 million

Pre-tax IRR/ After-Tax IRR 34.8%/29.4%

Undiscounted Operating Pre-Tax Cash Flow/After-Tax Cash Flow $259.3 million/$195.5 million

After-Tax Payback Period 2.3 years

1Includes mining cost, mine-level G&A, leaching and refining cost

2Includes the above plus royalties

3Includes the above plus sustaining and closure costs

Capital Requirements Units Initial LOM

Mining Capital $ million $23.50 $61.30

Total Infrastructure Capital $ million $31.40 $35.10

Total Processing Capital $ million $48.30 $68.40

Closure Costs $ million $0.00 $20.00

Owners Costs $ million $10.00 $10.00

Total Capital Costs $ million $113.20 $194.80

Page 4 of 10

Mining

The PEA Study utilizes open pit mining with mine planning based on economic pit shells generated by

mine planning software. Mine production is planned at 22,500 tonnes per day or 8.2 million tonnes per

year of leach feed (mineralized) material. With an average waste to leach feed material strip ratio of

1.2 to 1, the average mining rate is approximately 50,000 tonnes per day of leach feed and waste

material. The open pit mining at Goldstrike was designed utilizing an owner-operated, conventional

mine fleet of front end loaders and trucks.

1million tonnes

2numbers may not add due to rounding

Processing

The PEA Study assumes processing of run-of-mine (without crushing) leach feed material by truck

stacking onto a single heap leach pad in nine metre vertical lifts. Gold and silver will be extracted via

conventional heap leaching and will be recovered from the pregnant solution using a carbon

adsorption circuit. The gold and silver will then be stripped from carbon using a desorption process

followed by electrowinning to produce a precipitate sludge. The sludge is then roughly refined on site

in a furnace to produce doré bars, which are shipped to a refinery.

Operating Costs

Operating costs are based on the mining and processing scenario outlined above. Mining costs are

relatively well known in the Great Basin, where a large number of similar operations are in existence.

Parameter Units LOM2 1 2 3 4 5 6 7 8 9

Total Leach

Material Mt1 59.3 6.9 8.2 8.2 8.2 8.2 8.2 8.2 3.1 0.0

Gold Grade g/t 0.48 0.60 0.57 0.45 0.43 0.46 0.48 0.44 0.35 0.00

Contained Gold oz 915,516 132,899 151,769 120,079 114,051 120,316 125,926 115,976 34,499 0

Total Waste Mt 70.5 8.0 11.4 11.5 13.0 12.0 11.5 2.5 0.7 0.0

Total Material

Moved Mt 129.9 14.9 19.7 19.7 21.2 20.2 19.7 10.7 3.8 0.0

Gold Produced oz 713,004 87,876 117,855 97,463 88,650 92,447 97,234 90,742 36,427 4,309

Operating Costs LOM ($million) $/oz $/tonne

Mine Operating Cost1 $272.1 $392.16 $4.59

Leach Operating Costs $117.5 $169.37 $1.98

Water Supply $3.5 $5.01 $0.06

Road and Infrastructure Maintenance $17.0 $24.50 $0.29

Page 5 of 10

1Includes extraction of both mineralized material and waste rock

PEA Sensitivities

The PEA examines the effect on NPV5% of up to a 40% increase or decrease in capital (Capex) and

operating (Opex) expenditures. NPV5% is strongly influenced by the price of gold.

The following tables show the change in NPV5% over a range of Opex, Capex and gold prices. The

base case is shaded grey.

NPV5% in $M Operating Cost

-40.0% -20.0% 0.0% 20.0% 40.0%

Capital Cost -40.0% $288.2 $236.0 $183.7 $131.4 $79.1

-20.0% $261.3 $209.0 $156.6 $104.3 $51.9

0.0% $234.2 $181.9 $129.5 $77.1 $24.5

20.0% $207.1 $154.7 $102.3 $49.6 ($3.5)

40.0% $180.0 $127.4 $74.8 $21.9 ($32.0)

NPV5% in $M Gold Price/oz

$900 $1,100 $1,300 $1,500 $1,700

Capital Cost -40.0% $21.4 $102.6 $183.7 $264.7 $344.8

-20.0% ($6.5) $75.5 $156.6 $237.7 $318.7

0.0% ($35.2) $48.1 $129.5 $210.6 $291.7

20.0% ($67.7) $20.4 $102.3 $183.5 $264.6

40.0% ($101.4) ($7.8) $74.8 $156.4 $237.5

NPV5% in $M Gold Price/oz

$900 $1,100 $1,300 $1,500 $1,700

Operating Cost

-40.0% $71.7 $153.1 $234.2 $315.3 $396.3

-20.0% $18.9 $100.7 $181.9 $262.9 $344.0

0.0% ($35.2) $48.1 $129.5 $210.6 $291.7

20.0% ($101.8) ($5.0) $77.1 $158.3 $239.4

40.0% ($169.8) ($64.2) $24.5 $106.0 $187.1

The following tables show the effect of Capex, Opex and Gold Price on IRR

Post-tax IRR in % Operating Cost

-40.0% -20.0% 0.0% 20.0% 40.0%

Capital Cost -40.0% 74.5% 65.0% 54.7% 43.2% 30.3%

-20.0% 56.7% 48.4% 39.5% 29.8% 18.6%

0.0% 44.5% 37.3% 29.4% 20.7% 10.5%

20.0% 35.8% 29.2% 22.0% 13.9% 4.3%

40.0% 29.1% 22.9% 16.2% 8.5% -0.6%

Site G&A $35.2 $50.73 $0.59

Total $445.3 $641.77 $7.51

Page 6 of 10

Post-tax IRR in % Gold Price/oz

$900 $1,100 $1,300 $1,500 $1,700

Capital Cost -40.0% 12.9% 36.1% 54.7% 70.6% 85.0%

-20.0% 3.1% 23.8% 39.5% 53.3% 65.6%

0.0% -3.7% 15.2% 29.4% 41.5% 52.4%

20.0% -10.1% 8.8% 22.0% 33.0% 42.8%

40.0% -16.6% 3.7% 16.2% 26.5% 35.4%

Post-tax IRR in % Gold Price/oz

$900 $1,100 $1,300 $1,500 $1,700

Operating Cost

-40.0% 19.5% 32.9% 44.5% 55.2% 64.9%

-20.0% 9.2% 24.6% 37.3% 48.5% 58.9%

0.0% -3.7% 15.2% 29.4% 41.5% 52.4%

20.0% N/A 3.8% 20.7% 34.0% 45.6%

40.0% N/A -13.3% 10.5% 25.8% 38.3%

The following table illustrates the effect of gold price and discount rate on NPV.

NPV in $M Discount Rate

0.0% 5.0% 6.0% 7.0% 8.0%

Gold Prices -20.0% $56.8 $23.5 $18.3 $13.4 $8.9

-10.0% $126.2 $76.7 $68.8 $61.5 $54.7

0.0% $195.5 $129.5 $119.0 $109.3 $100.2

10.0% $264.7 $182.2 $169.1 $156.9 $145.5

20.0% $333.9 $235.0 $219.2 $204.5 $190.7

Project Enhancement Opportunities

The PEA demonstrates the potential economic viability of the Goldstrike Project. The PEA also

outlines a number of opportunities for Project Enhancement.

• Potential additions to the bedrock resource base: drilling is ongoing at Goldstrike, and a

large number of areas, both peripheral to the current resource and in satellite targets, are

undrilled, insufficiently drilled or are currently undergoing drill testing. An updated resource

estimate is targeted for the first half of 2019.

• Potential additions to the resource through testing of surficial areas: Historic heap leach

pads, stockpiles and waste dumps are currently undergoing drill testing. While these areas

were considered sub-economic in the late 1990s, they may prove to be of greater interest today.

Much of this material, currently classified as waste, falls within the high walls of the PEA pits.

• Potential upgrade of inferred mineral resources to measured and indicated mineral

resources: Infill drilling for this purpose is ongoing.

• Silver credits: The Goldstrike Mine operated from 1988 through 1994 and, based on historical

records from operators Tenneco Minerals Co. and USMX, produced 209,000 oz of gold and

197,000 oz of silver, or approximately 0.95 oz of silver for every oz of gold recovered. Based on

Page 7 of 10

this, silver assays from approximately 550 Liberty Gold drill holes, and Liberty Gold

metallurgical testing carried out to date, the Company believes there is potential for significant

silver revenues from a future operation at Goldstrike. Liberty Gold intends to pursue a silver

resource study to quantify a silver resource, as well as a review of metallurgical test data to

estimate silver recoveries that could be expected at the Goldstrike Project.

• Optimization of the mine plan: The PEA represents the first step toward addressing the

viability of a mining operation at Goldstrike. Further work may identify opportunities for cost-

saving, such as waste haul optimization and improved pit sequencing through pit phasing.

Contract mining or a leased mine fleet will also be assessed.

• Further metallurgical test work: Metallurgical test work is currently underway in areas not

previously tested. This work may lead to changes in the recovery curves used for this study,

and more advanced studies may identify other ways to enhance recovery.

Jim Lincoln, Chief Operating Officer for Pilot Goldstrike, a subsidiary of Liberty Gold, stated, “In our

team’s operating history, we have consistently adopted a mine development approach that

emphasizes project de-risking through concurrent engineering, metallurgy, social license

considerations, procurement of process water and addressing what is necessary to a develop a mine

from advanced exploration projects. This has proven to add value to mining projects which I have

worked on such as Long Canyon, Nevada and Karma, Burkina Faso, West Africa. Liberty Gold’s

Goldstrike project continues to progress with this development philosophy.”

Further details of the PEA will be available in a NI 43-101 technical report to be filed on SEDAR within

45 days. For an illustrative graphic of the PEA highlights, as-mined resource blocks and mine site

layout, please click here:

https://libertygold.ca/images/sites/default/files/GS_PEA_Highlights.pdf

Future Plans

Liberty Gold is committed to a program of continuing to address key development requirements and

advance the project while further demonstrating economic viability in the most efficient way possible

through:

• Continued drilling to address potential resource conversion, possible additions to the resource

through drilling adjacent to the existing resource and drilling of superjacent surficial deposits,

and testing of new targets (in progress)

• Metallurgical testing (in progress)

• Geochemical characterization of waste rock

• Baseline studies (meteorology, hydrology, etc.)

• Procurement of process water (in progress)

• Expanded permitting for drilling (in progress)

Page 8 of 10

• Earning our social license (ongoing).

Restated Mineral Resource Estimate

The Company’s February 2018 mineral resource estimate formed the original basis for the PEA. This

resource estimate, and the Technical Report within which it is reported, was prepared by SRK, and

entitled “Independent Technical Report and Resource Estimate for the Goldstrike Project, Washington

County, Utah, USA” effective February 8, 2018 and signed March 21, 2018. (the “Technical Report”).

The Technical Report was authored by Independent Qualified Persons David Rowe, CPG, of SRK

Consulting (Canada) Inc., James N. Gray, P.Geo, of Advantage Geoservices and Gary Simmons,

MMSA of GL Simmons Consulting LLC. The report is available under the Company’s profile at

www.sedar.com and on the Company’s website at www.libertygold.ca.

In the course of preparing the PEA, a lower cut-off grade of 0.20 g/t gold (compared to 0.25 g/t gold in

the original resource) was determined to be more suitable for the economic assessment. Accordingly,

the mineral resource was restated to reflect this change (the mineral endowment at the 0.20 g/t gold

cut off was previously released in a sensitivity table in the Technical Report).The effective date for the

data used in the resource estimate remains February 8, 2018, and all other parameters remain the

same.

Restated Mineral Resource Statement for Goldstrike Project – Effective February 8, 2018*

Indicated Inferred

Tonnes

(1,000s)

Grade Au

(g/t)

Ounces

Au

(1,000s)

Tonnes

(1,000s)

Grade Au

(g/t)

Ounces Au

(1,000s)

Resource 57,846 0.50 925 19,603 0.47 296

* Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

There is no certainty that all or any part of the Mineral Resources estimated will be converted into

Mineral Reserves. The estimate of Mineral Resources may be materially affected by changes in

environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues that

may arise subsequent to the effective date. The CIM definitions were followed for the classification of

Indicated and Inferred Mineral Resources. The quantity and grade of reported Inferred Mineral

Resources in this estimation are uncertain in nature and there has been insufficient exploration to

define these Inferred Mineral Resources as an Indicated Mineral Resource and it is uncertain if further

exploration will result in upgrading them to an Indicated Mineral Resource category. All figures have

been rounded to reflect the relative precision of the estimates. Mineral Resources are reported at a

cut-off grade of 0.20 g/t gold based on $1,500 per troy ounce gold and gold metallurgical recoveries on

a sliding scale by grade.

Qualified Persons

The following persons are the Company's designated Qualified Persons for this news release within

the meaning of National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101")

and have reviewed and approved the information contained in this news release and verified all data