Lahontan Engages Kappes, Cassiday and Associates FOR Santa Fe Preliminary Economic Assesment

Corporate Updates

217 Queen Street West, Suite 401, Toronto, ON M5V 0R2 www.lahontangoldcorp.com

NEWS RELEASE TSX.V LG, OTCQB LGCXF

LAHONTAN ENGAGES KAPPES, CASSIDAY AND ASSOCIATES FOR SANTA FE

PRELIMINARY ECONOMIC ASSESMENT

Toronto, Ontario, May 6, 2024. Lahontan Gold Corp (TSXV:LG, OTCQB:LGCXF) (the

"Company" or "Lahontan"), is pleased to announce that it has engaged Kappes, Cassiday and

Associates based in Reno, Nevada (“KCA”) to produce an updated NI 43-101 compliant Technical Report

and Preliminary Economic Assessment (“PEA”) for its flagship Santa Fe Mine project, located in Nevada’s

prolific Walker Lane. KCA will lead a team including RESPEC Company LLC (“RESPEC”) also based

in Reno, and Equity Exploration of Vancouver, British Columbia (“Equity”). KCA will coordinate the

PEA, Equity will be responsible for updating the block model and Mineral Resource Estimate, and RESPEC

will provide mine design and planning. KCA will develop metallurgical flow sheets, process facility layout,

and general mine infrastructure along with economic analysis.

Kimberly Ann, Lahontan Founder, CEO, President, and Director commented: “We are very pleased to have

some of the top mining consultancies begin work on the Santa Fe Mine PEA. We believe that Santa Fe is

one of, if not the, premier gold and silver mine development opportunity in the Great Basin of the western

US. We will simultaneously continue preparing our Exploration Plan of Operations for submission to the

Bureau of Land Management this Summer. Utilizing the baseline studies in the Plan, we can modify the

Plan to reflect our proposed mining operation being defined by our team of consultants”.

Scope of Work – Santa Fe Mine PEA

The PEA will evaluate open-pit mining from multiple sites at the Santa Fe Mine, three-stage crushing, drum

agglomeration with cement, heap leaching, and a carbon ADR plant producing gold/silver doré bars:

• Plant production rate will be from 10,000 to 15,000 dry tons per day, to be optimized during the

PEA process;

• Three-stage crushing with agglomeration including conveyor stacking;

• Process feed will be open pit sourced gold and silver mineralization mined by a contractor;

• Water sources will be developed from nearby well fields, electric power will be supplied from the

local grid;

• The mining portions of the PEA study, including capital and operating costs, will be completed

by RESPEC which KCA will review and incorporate this information into the overall PEA study;

• The heap leach pad/pond designs and associated facilities, including capital and operating costs

will be developed by KCA.

The work for the PEA is expected to begin immediately, a detailed timeline will be established once all

existing data has been thoroughly reviewed by the PEA team.

About Lahontan Gold Corp.

Lahontan Gold Corp. is a Canadian mine development and mineral exploration company that holds,

through its US subsidiaries, four top-tier gold and silver exploration properties in the Walker Lane of

mining friendly Nevada. Lahontan’s flagship property, the 26.4 km2 Santa Fe Mine, had past production

217 Queen Street West, Suite 401, Toronto, ON M5V 0R2 www.lahontangoldcorp.com

of 345,000 ounces of gold and 711,000 ounces of silver between 1988 and 1995 from open pit mines

utilizing heap-leach processing (Nevada Bureau of Mines and Geology, 1995). The Santa Fe Mine has

Canadian National Instrument 43-101 compliant Indicated Mineral Resource of 1,112,000 oz Au Eq

(grading 1.14 g/t Au Eq) and an Inferred Mineral Resource of 544,000 oz Au Eq (grading 1.00 g/t Au Eq),

all pit constrained (Au Eq is inclusive of recovery, please see Santa Fe Project Technical Report*). The

Company will continue to aggressively explore Santa Fe during 2023 and begin the process of evaluating

development scenarios to bring the Santa Fe Mine back into production. Quentin J. Browne, P.Geo.,

Consulting Geologist to Lahontan Gold Corp., is the Qualified Person for the Company and approved the

technical content of this news release. For more information, please visit our website:

www.lahontangoldcorp.com

* Please see the Santa Fe Project Technical Report, Authors: Trevor Rabb and Darcy Baker, P. Geos. Effective Date: December

7, 2022, Report Date: March 2, 2023. The Technical Report is available on the Company’s website and SEDAR.

On behalf of the Board of Directors

Kimberly Ann

Founder, CEO, President, and Director

FOR FURTHER INFORMATION, PLEASE CONTACT:

Lahontan Gold Corp.

Kimberly Ann

Founder, Chief Executive Officer, President, Director

Phone: 1-530-414-4400

Email:

[email protected]

Website: www.lahontangoldcorp.com

Cautionary Note Regarding Forward-Looking Statements:

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release. Except for statements of historical fact,

this news release contains certain "forward-looking information" within the meaning of applicable securities law.

Forward-looking information is frequently characterized by words such as "plan", "expect", "project", "intend",

"believe", "anticipate", "estimate" and other similar words, or statements that certain events or conditions "may" or

"will" occur. Forward-looking statements are based on the opinions and estimates at the date the statements are made

and are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ

materially from those anticipated in the forward-looking statements including, but not limited to delays or uncertainties

with regulatory approvals, including that of the TSXV. There are uncertainties inherent in forward-looking information,

including factors beyond the Company’s control. The Company undertakes no obligation to update forward-looking

information if circumstances or management's estimates or opinions should change except as required by law. The reader

is cautioned not to place undue reliance on forward-looking statements. Additional information identifying risks and

uncertainties that could affect financial results is contained in the Company’s filings with Canadian securities regulators,

which filings are available at www.sedar.com