Cypress Test Program at NORAM Engineering Completed for Clayton Valley Lithium Project in Nevada

Corporate Updates

Suite 1610 - 777 Dunsmuir Street, Vancouver, BC, Canada, V7Y 1K4

www.cypressdevelopmentcorp.com

TSX Venture Exchange Symbol: CYP

Email: [email protected]

Telephone: (604) 687-3376

Facsimile: (604) 687-3119

NEWS RELEASE

February 27, 2020

Cypress Test Program at NORAM Engineering Completed for

Clayton Valley Lithium Project in Nevada

Vancouver, BC - Cypress Development Corp. (TSX-V: CYP) (OTCQB: CYDVF)

(Frankfurt: C1Z1) (“Cypress” or “the Company”) is pleased to report the test program

at NORAM Engineering and Constructors Ltd. (“NORAM”) is complete and initial

results are positive. As reported in a November 14, 2019 press release, NORAM was

contracted to examine the downstream portion of the revised extraction flowsheet for

Cypress’ Clayton Valley Lithium Project in Nevada. Testing was conducted at BC

Research Inc., a member of the NORAM Group of companies in Richmond, British

Columbia.

The program utilized both synthetic and actual solutions generated from Cypress’

large leach tests conducted at Continental Metallurgical Services (“CMS”) in Butte,

Montana. The tests simulated the purification solution and concentration steps within

a portion of the NORAM-Cypress developed flowsheet. Initial results are positive and

indicate the target levels of lithium concentration and rejection of impurities in solution

were achieved. The pending, final report will be used to update the mass balance in

the process flowsheet and complete the remining step in the Company’s ongoing

Prefeasibility Study (“PFS”) on the project.

NORAM Test Results

Step Li

(ppm)

Mg

(ppm)

Ca

(ppm)

Fe

(ppm)

Al

(ppm)

Feed 380 3340 339 2270 1395

Purified 360 54 15 40 10

With respect to the PFS, the Company and its consultants are actively working to

complete the study. The resource model, pit design, production schedule, and site

selection and infrastructure studies for the processing plant are completed.

The design is based on mining 15,000 tonnes per day of material in an effort to produce

25,000 tonnes per year of lithium carbonate equivalent (“LCE”). The mine area is

designed to initially target the upper portions of the intercepts encountered in 2019

2

drilling (see table below). This area of drilling represents a small portion of the overall

lithium resource on the property and is expected to support the design basis of

production for the first 18 years of the project. The large leach tests at CMS show

lithium extractions of 84 -86% and confirmed values for acid consumption from the

2018 Preliminary Economic Assessment (“PEA”). Sulfuric acid remains a major

consumable for the project. Quotations for an on-site sulfuric acid plant, sulfur supply

and transportation were obtained. Issues related to leaching and filtration were

resolved and the N ORAM test program completes the rem aining critical design

element required for the PFS process flowsheet.

2019 Drill Intercepts

Hole Top (m) Bottom (m) Interval (m) Grade Li (ppm)

GCH-07 3 91 88 1,189

GCH-08 3 87 85 1,226

GCH-09 2 75 74 1,115

GCH-10 3 54 51 1,130

GCH-11 5 87 82 1,115

GCH-12 2 81 80 1,252

The project’s PFS is limited to the Dean and Glory mining claim-blocks totaling 4,780

acres. An additional 1,280-acre claim-block was part of the Company’s 2019 lawsuit

against Centrestone Resources, LLC, and was excluded from the PFS. This

contiguous claim block is located south and east of the project’s initial proposed mine

area. These mining claims include the lands on which Centrestone Resources drilled

two exploration holes. On December 16, 2019, the District Court entered an oral order

granting summary judgment in favor of the Company on its claims against Centrestone

Resources LLC. On February 6, 2020, the District Court entered its written order for

summary judgment. The District Co urt set a hearing on April 21, 2020 in Goldfield,

Nevada, to hear the Company’s damage claim.

Todd Fayram, QP, of Continental Metallurgical Services, LLC., is the qualified person

as defined by National Instrument 43-101 and has approved the technical information

in this release.

About Cypress Development Corp.:

Cypress Development Corp. is a publicly traded exploration company focused on

developing the Company's 100% -owned Clayton Valley Lithium Project in Nevada.

Exploration and development by Cypre ss has discovered a world -class resource of

lithium-bearing claystone adjacent to Albemarle's Silver Peak mine, North America's

only lithium brine operation. The size of the resource makes the Clayton Valley Project

a premier target with the potential to impact the future supply of lithium for the fast -

growing global lithium-ion battery market.

Cypress Development Corp. has approx. 90.1 million shares issued and outstanding.

To find out more about Cypress Development Corp. (TSX -V: CYP), visit our website

at www.cypressdevelopmentcorp.com.

3

CYPRESS DEVELOPMENT CORP.

“Dr. Bill Willoughby”

WILLIAM WILLOUGHBY, PhD., PE

Chief Executive Officer

For further information contact myself or:

Don Myers

Cypress Development Corp.

Director, Corporate Communications

Telephone: 604-639-3851

Toll Free: 800-567-8181

Facsimile: 604-687-3119

Email: [email protected]

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES

PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCUR ACY OF THE

CONTENT OF THIS NEWS RELEASE.

This release includes certain statements that may be deemed to be "forward -looking

statements". All statements in this release, other than statements of historical facts, that

address events or developments that ma nagement of the Company expects, are forward -

looking statements. Although management believes the expectations expressed in such

forward-looking statements are based on reasonable assumptions, such statements are not

guarantees of future performance, and a ctual results or developments may differ materially

from those in the forward-looking statements. The Company undertakes no obligation to update

these forward -looking statements if management's beliefs, estimates or opinions, or other

factors, should change. Factors that could cause actual results to differ materially from those

in forward-looking statements, include market prices, exploration and development successes,

continued availability of capital and financing, and general economic, market or busines s

conditions. Please see the public filings of the Company at www.sedar.com for further

information.