Cypress Development Delivers Solution from Pilot Plant FOR Testing Production of Lithium Carbonate and Lithium Hydroxide
NEWS RELEASE TSXV: CYP | OTCQX: CYDVF
CYPRESS DEVELOPMENT DELIVERS SOLUTION FROM PILOT PLANT FOR TESTING
PRODUCTION OF LITHIUM CARBONATE AND LITHIUM HYDROXIDE
June 13, 2022 – Vancouver, Canada – Cypress Development Corp. (TSXV: CYP) (OTCQX: CYDVF)
(Frankfurt: C1Z1) (“Cypress” or “the Company”) is pleased to report that the Company’s Lithium
Extraction Facility (“Pilot Plant”) in Amargosa Valley, Nevada continues to operate successfully, reaching
a milestone in the delivery of concentrated lithium solution to two laboratories in Canada for further
testing in the production of lithium products.
“The Company is very pleased to have reached this significant milestone. About 4,000 liters of
concentrated lithium chloride solution have been delivered from the Pilot Plant to two Canadian
laboratories. Each laboratory is now working to further treat the solutions, one to produce lithium
carbonate, and the other, lithium hydroxide, as the final end product,” commented Bill Willoughby,
President and CEO of Cypress Development. “These results will then be used to determine what additional
steps are needed, if any, to attain battery-grade standards and evaluate the alternatives for producing
these products in the ongoing Feasibility Study.”
Pilot Plant
Cypress’ Lithium Extraction Facility in Amargosa Valley, Nevada marked its sixth month of operation with
the completion of 11 separate continuous tests conducted on a 24-hour per day basis, over periods
ranging from 3 to 14 days. Processing conditions and equipment arrangements in the areas of leaching,
filtration, impurity removal, and the Direct Lithium Extraction (DLE) system during the testing periods have
been varied to determine the effect of changes. The Pilot Plant will continue to operate during the summer
with a work schedule of 7-days on, 5-days off.
“The Pilot Plant operates very well and requires minimal time for start-up,” stated Todd Fayram, President
of Continental Metallurgical Services and Qualified Person who oversees process engineering and
operations at the Pilot Plant. “For the most part we are using standard equipment with well-established
methods in mineral processing. This allows us to efficiently examine changes and reconfigure the process
as required.”
The Company is pleased with the progress and results to-date. Recoveries in the Pilot Plant remain as
expected, with lithium extraction from claystone in the 80 to 85% range. Tailings testing has preliminarily
2
identified characteristics that will allow for dry stacking with minimal water entrainment. The Pilot Plant
is also focused on minimizing water usage and has operated successfully with an emphasis on 100%
recycling of all process water streams within the facility.
Qualified Person
Todd Fayram, MMSA-QP is a Qualified Person as defined by National Instrument 43-101 and has approved
of the technical information in this release.
About Cypress Development Corp
Cypress Development Corp. is a Canadian based advanced stage lithium company, focused on developing
its 100%-owned Clayton Valley Lithium Project in Nevada, USA. Cypress is in the pilot stage of testing on
material from its lithium-bearing claystone deposit and progressing towards completing a feasibility study
and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle
and battery storage market.
ON BEHALF OF CYPRESS DEVELOPMENT CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer
For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851 | Toll Free: 1 800 567 8181 | Email [email protected]
www.cypressdevelopmentcorp.com
NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS
RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.
Cautionary Note Regarding Forward-Looking Statements
This release includes certain statements that may be deemed to be "forward-looking statements". Forward-looking
statements are subject to risks, uncertainties and assumptions and are identified by words such as “expects,”
“estimates,” “projects,” “anticipates,” “believes,” “could,” “scheduled,” and other similar words. All statements in
this release, other than statements of historical facts, that address events or developments that management of the
Company expects, are forward-looking statements. Although management believes the expectations expressed in
such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of
future performance, and actual results or developments may differ materially from those in the forward-looking
statements. The Company undertakes no obligation to update these forward-looking statements if management's
beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ
materially from those in forward-looking statements, include market prices, exploration, and development successes,
continued availability of capital and financing, and general economic, market or business conditions. Please see the
public filings of the Company at www.sedar.com for further information.