Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

LCE.V ·

Cypress Development Announces Positive Preliminary Economic Assessment (PEA) for Clayton Valley Lithium Project, Nevada

Economic Studies

Suite 1610 - 777 Dunsmuir Street, Vancouver, BC, Canada, V7Y 1K4

www.cypressdevelopmentcorp.com

TSX Venture Exchange Symbol: CYP

Email: [email protected]

Telephone: (604) 687-3376

Facsimile: (604) 687-3119

NEWS RELEASE

September 6, 2018

Cypress Development Announces Positive Preliminary Economic Assessment

(PEA) for Clayton Valley Lithium Project, Nevada

Vancouver, BC - Cypress Development Corp. (TSX-V: CYP) (OTCQB: CYDVF)

(Frankfurt: C1Z1) (“Cypress” or the “Company”) is pleased to announce positive

results from a Preliminary Economic Assessment (PEA) of the Company’s Clayton

Valley Lithium Project in Nevada, U.S.A. The PEA was prepared by Global Resource

Engineering (GRE) of Denver, Colorado , an independent engineering services firm

with extensive experience in mining and mineral processing . All dollar values are in

US dollars.

Highlights:

 Net present value of $1.45 billion at 8% discount rate and 32.7% internal rate

of return on after-tax cash flow.

 Lithium carbonate price of $13,000 per tonne based on Benchmark Research

market study.

 Average annual production rate of 24,042 tonnes of lithium carbonate over

40-year life.

 Capital cost estimate of $4 82 million, pre-production and o perating cost

estimate averaging $3,983 per tonne of lithium carbonate.

 Updated Resources from May 1, 2018 estimate:

o Indicated Resource of 831 million tonnes at 8 67 ppm Li, or 3. 835

million tonnes lithium carbonate equivalent (LCE).

o Inferred Resource of 1.12 billion tonnes at 860 ppm Li, or 5.126

million tonnes LCE.

2

Cypress CEO Dr. Bill Willoughby commented "This is a nother important milestone

for the project and Cypress. The PEA outlines the steps necessary for a mine and

mill at Clayton Valley, including a sulfuric acid plant which is the main driver in the

costs. GRE uses a conventional approach in processing and developed a production

schedule that utilizes only a small fraction of the total reso urces on the property. The

end result is a project that has strong economics and the potential to generate

significant cash flow.”

PEA Summary

After tax cash flow analysis (US Dollars)

Internal rate of return (IRR) 32.7%

Net present value (NPV-8%) $1.45 billion

Cumulative cash flow, undiscounted $6.171 billion

Payback period 2.7 years

Operating rate 15,000 tpd for 40 years

Capital cost estimate $482 million over 2 years

Net lithium recovery 81.5%

Base case price for lithium carbonate $13,000/tonne

Average production lithium carbonate 24,042 tonnes

Operating cost for lithium carbonate $3,983/tonne

Sensitivity of Base Case to Lithium Price

Price for lithium carbonate NPV-8%

($ Million) IRR

$4,800/tonne - break-even --- 0

$8,000/tonne (-38%) 433 16.4

$10,500/tonne (-19%) 947 25.0

$13,000/tonne – base-case 1,454 32.7

$15,500/tonne (+19%) 1,960 40.0

$18,000/tonne (+38%) 2,467 46.8

3

Resources:

The PEA includes an updated Mineral Resource Estimate, which followed upon

changes in the resou rce model and property boundaries since the May 1, 2018

Resource Estimate. For the PEA, GRE created an ultimate pit shell for the property -

wide resources, and an initial pit shell that focused on the higher -grade clay units in

the eastern part of the prope rty. Estimation methods follow those in the previous

report.

Resources – Property-Wide Pit Shell

Cut-off

grade

Li ppm

Indicated Inferred

Tonnes

(million)

Li

ppm

Tonnes

LCE

(million)

Tonnes

(million)

Li

ppm

Tonnes

LCE

(million)

300 831.0 867 3.834 1,120.3 860 5.125

600 768.5 892 3.649 1,022.2 888 4.831

900 319.7 1,091 1.857 430.3 1,082 2.478

Resources- Initial Pit Shell

Cut-off

grade

Li ppm

Indicated Inferred

Tonnes

(million)

Li

ppm

Tonnes

LCE

(million)

Tonnes

(million)

Li

ppm

Tonnes

LCE

(million)

300 365.3 942 1.832 160.5 992 0.847

600 361.3 946 1.820 158.5 997 0.841

900 198.0 1,105 1.164 106.8 1,119 0.626

CIM definitions were followed for Mineral Resources.

The mineral resources are reported using a cut -off grade of 300 ppm Li and are

constrained to a pit shell reflecting a $1 7.50/tonne operating cost, $ 13,000/tonne of

LCE price, and 81.5% net recovery to LCE. Both property-wide and initial pit shells

use a 30-degree pit slope.

Mining and production schedule:

A 15,000 tonne per day n ominal production rate was selected based upon the

projected output for the operation, with the goal of producing 20,000 tonnes per year

of lithium carbonate. The nominal production rate equates to 5.475 million tonnes per

year of mill feed at an average g rade of 1,012 ppm Li. Further improvement in the

4

production schedule is possible given the resources in the initial pit alone far exceed

the 219 million tonnes of production needed to support a 40-year mine life.

GRE evaluated four options for mine equip ment and mill feed transportation and

selected an in-pit feeder-breaker with slurry pumping for the base case. No drilling or

blasting is required, and the only major piece of mobile equipment is a front -end

loader to fee d the in -pit feeder -breaker. Waste mining is minimal, amounting to a

total of 6 million tonnes over the 40-year mine life.

Processing:

The plant design by GRE includes agitated tank leaching, and a multi-stage thermal-

mechanical evaporation system for concentrating leach solution . Slurried feed is

transported to the mill where l ithium extraction is achieved through leaching at

elevated temperatures with dilute sulfuric acid. The sulfuric acid concentration is

targeted at 5%, with the addition of concentrated acid delivered from the on-site acid

plant.

The estimated acid plant capacity is 2,000 tonnes per day of sulfuric acid , generated

from the combustion of elemental sulfur trucked to the site in the molten state. The

acid plant has the potential to produce up to 25 MW of electricity, bu t at additional

capital expense. For this study, only enough electricity will be generated to run the

acid plant . Steam from the plant will be used for heating in the leaching and

evaporation stages of processing.

Leaching will take place in a primary leach vessel followed by a series of thickeners.

Retention time in the leach circuit is estimated at 4 to 6 hours with acid consumption

estimated at 125 kg per tonne of feed. Overflow from the final leach thickener is

pumped to a primary impurity removal circ uit where calcium hydroxide is added to

precipitate iron and aluminum, and the thickened underflow filtered and conveyed to

a dry -stack tailings facility. The p urified solution is reduced in volume via a multi-

stage thermal-mechanical evaporation system where evaporate is collected and

recycled as process water , and the condensate is treated by stage -wise addition of

sodium hydroxide and soda ash to precipitate calcium, manganese and magnesium

before advancing to final product production. Precipitation of the final product occurs

with the addition of soda ash , producing a lithium carbonate product targeted at

99.5% purity. Net recovery of lithium throughout processing is estimated at 81.5%.

Process water for the operation will be obtained by recycling barren leach solution

after treating in a reverse osmosis plant, and by introducing fresh make -up water,

estimated at 345 m3/hour and delivered via pipeline from a well field located off-site.

Capital Costs:

The total initial capital cost estimate is $482 million distributed over two years of pre-

production. An overall factor of 2.86 on equipment costs is used to allow for the

necessary installation labor, construction materials, spares , first fill, buildings, and

engineering and construction management. Infrastructure and G&A capital includes

allowances for feasibility study, permitting, bonding, off-site electrical, and acquisition

of process water.

Capital Cost (USD Millions)

5

Mine development and equipment 35

Plant feed prep, leaching, purification and lithium recovery 163

Acid plant 105

Tailings 25

Site utilities 17

Infrastructure and G&A capital 38

Direct Capital Costs 383

Working capital 24

Contingency (20% of Direct Costs) 76

Indirect Capital Costs 99

TOTAL CAPEX 482

Operating Cost Estimate:

Estimated operating costs are $17.50 per tonne of mill feed, or $96 million per year,

including 10% contingency. Acid plant operations are the major component in the

operating costs and account for more than half of the total. Project labor is estimated

at 136 on-site employees. Connected power is estimated at 12 MW, with a n all-in

cost of $0.066 per KWH.

Operating Cost $ per tonne

of mill feed

$ per tonne

of LCE

Mining 1.73 395

Plant labor 1.45 330

Reagents & supplies 12.70 2,893

Power 0.94 210

G & A 0.68 155

TOTAL OPEX 17.50 3,983

Project Advancement:

GRE recommends further work , including bench scale testing , to demonstrate the

recovery of lithium product. Cypress intends to proceed with this recommendation as

soon as possible, beginning with the collection of representative sample material with

respect to the production schedule. The Company will continue to work on permitting

and other areas to advance the project.

Global Resource Engineering of Denver, Colorado, prepared the Technical R eport

which carries an Effective Date of September 5 , 2018. Terre A. Lane, J. Todd

Harvey, Hamid Samari, and J. J. Brown of GRE , and Todd Fayram of Continental

Metallurgical Services are the Qualified Persons for the report.

The PEA is preliminary in natu re and includes inferred mineral resources that are

considered too speculative geologically to have the economic considerations applied

to them that would enable them to be categorized as mineral reserves, and there is

6

no certainty that the PEA will be realized. Mineral resources are not mineral reserves

and do not have demonstrated economic viability.

The NI 43 -101 technical report detailing the PEA will be filed on SEDAR within 45

days.

The information contained in this news release relating to the PE A has been

reviewed and approved by Terre Lane of GRE, who is a "Qualified Person" as the

term is defined in National Instrument 43 -101 and is independent of Cypress. GRE

has reviewed and approved the presentation of the PEA information in this news

release.

About Cypress Development Corp.:

Cypress Development Corp. is a publicly traded exploration company focused on

developing the Company's 100% -held Clayton Valley Lithium Project, located

immediately east of Albemarle's Silver Peak mine, North America' s only lithium brine

operation. Recent exploration by Cypress has discovered an extensive deposit of

lithium-bearing claystone adjacent to the brine field.

Cypress Development Corp. has approx. 62.0 million shares issued and outstanding.

To find out more about Cypress Development Corp. (TSX-V: CYP), visit our website

at www.cypressdevelopmentcorp.com.

CYPRESS DEVELOPMENT CORP.

“Dr. Bill Willoughby”

WILLIAM WILLOUGHBY, PhD., PE

Chief Executive Officer

For further information contact myself or:

Don Myers

Cypress Development Corp.

Director, Corporate Communications

Telephone: 604-639-3851

Toll Free: 800-567-8181

Facsimile: 604-687-3119

Email: [email protected]

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES

PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE

CONTENT OF THIS NEWS RELEASE.

This release includes certain statements that may be deemed to be "forward -looking

statements". All statements in this release, other than statements of historical facts, that

address events or developments that management of the Company expects, a re forward -

looking statements. Although management believes the expectations expressed in such

forward-looking statements are based on reasonable assumptions, such statements are not

guarantees of future performance, and actual results or developments may differ materially

from those in the forward -looking statements. The Company undertakes no obligation to

update these forward -looking statements if management's beliefs, estimates or opinions, or

other factors, should change. Factors that could cause actual results to differ materially from

those in forward -looking statements, include market prices, exploration and development

7

successes, continued availability of capital and financing, and general economic, market or

business conditions. Please see the publi c filings of the Company at www.sedar.com for

further information.