Lithium Americas Receives Notice of Intent for the Thacker Pass Lithium Project

Permits & Approvals

Lithium Americas Receives Notice of Intent for the Thacker Pass Lithium

Project

VANCOUVER, British Columbia, Jan. 21, 2020 -- Lithium Americas Corp. (TSX: LAC) (NYSE: LAC) ("Lithium Americas"

or the "Company") is pleased to announce the publication of the Notice of Intent (“ NOI”) to prepare an Environmental Impact

Statement (“EIS”) for the Thacker Pass lithium claystone project (“ Thacker Pass” or the “Project”) located in northwestern

Nevada.  Thacker Pass is 100% owned by Lithium Nevada Corp. (“Lithium Nevada ”), a Nevada corporation that is a wholly-

owned subsidiary of Lithium Americas. The NOI formally commences the National Environmental Policy Act (“ NEPA”) EIS

preparation and public engagement process by the U.S. Department of the Interior Bureau of Land Management (“BLM”).

The NEPA process is designed to help public officials complete permitting decisions that are protective of the environment and

includes a public engagement process.  The 12-month NEPA period is scheduled to include the BLM’s Record of Decision

(“ROD”), representing the BLM’s final decision on Lithium Nevada’s application for an approved Plan of Operations.  In October

2019, the BLM engaged ICF Jones & Stokes, Inc. (“ ICF”), an experienced NEPA consultant, to prepare the EIS.  The BLM,

Lithium Nevada and ICF have entered into Memorandums of Understanding that define the timeline and support the overall

management of the EIS-development process.

“The initiation of the EIS process by the BLM is a major accomplishment and milestone toward developing Thacker Pass as a

low-cost and environmentally responsible source of lithium chemicals in the US,” commented Jonathan Evans, Lithium

Americas’ President and CEO. “This achievement, which commences a mandated 12-month process to complete the EIS,

was a team effort that required the coordination and commitment from the Bureau of Land Management, local and state

government agencies, our partners and the team at Lithium Nevada.”

“The Thacker Pass Project is being engineered to produce low-cost, battery-quality lithium products reliably and at scale,

however, the environmental design is a point of pride for the project team.  Our goal is to produce the first carbon neutral

lithium products, representing an innovative benchmark in the industry,” commented Alexi Zawadzki, CEO of Lithium Nevada. 

“Our vision is for a more sustainable battery supply chain in the US, with cathode and cell manufacturing located in close

proximity to the proposed Thacker Pass mine site.”

The publication of the NOI on January 21, 2020, follows the final Plan of Operations which was accepted by the BLM in

September 2019. The Plan of Operations includes production of battery-grade lithium hydroxide and lithium carbonate, lithium

metal (up to 60,000 tons per annum (“tpa”) of lithium carbonate equivalent (“LCE”)), and battery manufacturing. The Company

is targeting an initial phase (“Phase 1”) production capacity of approximately 20,000 tpa of battery-quality lithium hydroxide, in

addition to approximately 2,000 tpa of battery-quality lithium carbonate. The anticipated timing of key permitting milestones to

begin construction in early 2021 are highlighted in Figure 1.

A photo accompanying this announcement is available at

https://www.globenewswire.com/NewsRoom/AttachmentNg/52fcc9bb-f6b5-409b-894a-64ae45696b4a

The Company’s engagement with government, the Fort McDermitt Tribe and local stakeholders is planned to continue over the

next year in anticipation of the ROD being issued by early 2021. The ROD will include the agency’s decision, alternatives

considered and the plans for mitigation and monitoring, if required.

Environmental & Social Responsibility

Carbon Accounting

The proposed Thacker Pass mining and metallurgical process is being designed to achieve or exceed carbon-neutral scope 1

emissions status as defined by the Greenhouse Gas Protocol (“ Scope 1 ”). The low carbon footprint is expected due to 1) the

unique nature of the ore, which requires low energy to extract, beneficiate and process, and; 2) heat from the exothermic

process which is designed to be captured to generate carbon-free electricity and steam. The cogeneration facility is expected

to provide enough electricity to operate the plant and mine with the potential for excess electricity to be sold to the grid.

Carbon-free steam is expected to be used in the plant (no natural gas or other fuel is required to make steam). Furthermore,

solar power generation and electric trucks are also being evaluated to further reduce carbon emissions beyond Scope 1.

Through innovative design, Thacker Pass is being developed as a potential model of sustainability in the extraction and

processing of critical minerals required for a low-carbon economy. Many years of environmental monitoring data was collected

and used to locate project infrastructure in areas of lowest environmental impact. The sound and air emissions control

systems have been engineered to use the best available technology, resulting in a design that exceeds regulatory

requirements. Within the proposed processing facility, water recycling is expected to be employed throughout the facility to

minimize consumption (Phase 1 requires approximately the same amount of water as 2-3 alfalfa irrigation pivots).

Lithium Americas made the decision in 2018 to move the Project south of the Montana Mountains in order to avoid disturbance

in sensitive ecological areas located within the mountains. The Company has collected baseline environmental data over a

seven-year period and has provided a full set of baseline reports to the BLM. The data and related modeling indicate that there

will not be any adverse impact to local streams or related wildlife habitat, either directly or indirectly, and these data are being

used to draft the EIS. 

Community Engagement

Lithium Americas engaged with local stakeholders throughout the project definition and design process in a transparent

consultation process.  Several open houses have been held since 2017, with more scheduled in 2020.  A Project Engagement

Agreement with the local Fort McDermitt Tribe continues to be in place to ensure that tribal members are fully engaged and

informed of the project, including employment and training opportunities prior to proposed construction and operations. 

Great Basin Sagebrush Restoration Fund

The Great Basin Sagebrush Restoration Fund founded by Lithium Americas and the University of Nevada, Reno Foundation is

now the largest research fund of its kind in the US. Progress continues in 2020 on developing innovative sagebrush restoration

technologies in including coated seeds, genetics and restoration modeling. 

Winnemucca Office

In anticipation of construction commencing, pending permits and financing, a project office in Winnemucca was established in

December 2019. The office is staffed full time to respond to public questions about the project, including employment and

contracting opportunities. 

Employment

During the proposed two-year construction and commissioning period, it is anticipated that approximately 1,000 jobs would be

created. Approximately 350 high-paying jobs are anticipated during Phase 1 operations. Northern Nevada has limited career

opportunities, which emphasizes the potential for the Project to provide a positive impact on the local economy.

Scalability

The lithium deposit hosted in the McDermitt Caldera has been drilled extensively by Lithium Americas and heritage owners of

the claims. 

However, the full extent of the deposit has not been defined. To this end, Lithium Americas has also submitted a Plan of

Operations for exploration in parallel to mine Plan of Operations. Approval of this plan would allow Lithium Americas to explore

other areas within Thacker Pass that have potential for lithium enriched sediments, including areas south of Highway 293 and

areas east of the proposed pit (Figure 2).

A photo accompanying this announcement is available at

https://www.globenewswire.com/NewsRoom/AttachmentNg/0264d8a3-c499-4bb6-81d8-98e2aa25e3ac

Process Research Facility

Lithium Americas has successfully produced over 5,000 kg of high-quality lithium sulphate, the precursor for lithium hydroxide

and lithium carbonate, at the Company’s process testing facility in Reno, Nevada.  Lithium sulphate has been sent to

crystallization vendors to make battery quality lithium hydroxide samples and provide the process flow sheet and cost

estimates. 

Additional mineralized material from the Thacker Pass deposit was collected in 2019 from numerous areas of the proposed pit.

These samples, totaling approximately 60 tonnes of material, represent the various ore types predicted to be encountered

across the proposed pit area. The samples continue to be processed at the facility to optimize and further increase confidence

in the flow sheet.

Feasibility Study 

Building on the results of the National Instrument 43-101 (“ NI 43-101”) Technical Report on the Pre-Feasibility Study for the

Thacker Pass Project, dated August 1, 2018, Lithium Americas is currently working with Sawtooth Mining LLC (exclusive

mining contractor for Thacker Pass), TIC-The Industrial Company, a division of Kiewit Corporation, and professional services

firms to produce a feasibility study. The Company is targeting a Phase 1 production capacity of approximately 20,000 tonnes

per annum of battery-quality lithium hydroxide, in addition to approximately 2,000 tonnes per annum of battery-quality lithium

carbonate. Lithium Americas expects to release a NI 43-101 feasibility study on Thacker Pass by mid-2020.

Financing Strategy  

Lithium Americas continues to evaluate a variety of strategic financing options, including the possibility of a joint venture

partner for the development of Phase 1 of Thacker Pass. The Company expects to begin a formal financing process in 2020,

which will include the shipment of samples of lithium hydroxide to potential customers and partners. 

Qualified Persons

The scientific and technical information in this news release has been reviewed and approved by Dr. Rene LeBlanc and Randal

Burns, Qualified Persons for purposes of NI 43-101. Dr. LeBlanc is the Chief Technical Officer for the Company and Mr. Burns

is a VP Exploration at Lithium Nevada Corp., a wholly-owned subsidiary of the Company.

Further information about the Project, including a description of the key assumptions, parameters, description of sampling

methods, data verification and QA/QC programs, methods relating to resources and factors that may affect those estimates

are contained in the technical report entitled “Technical Report on the Pre-Feasibility Study for the Thacker Pass Project,

Humboldt County, Nevada, USA” with an effective date of August 1, 2018, which is available on SEDAR and on the Company’s

website.

About Lithium Americas: 

Lithium Americas owns a 50% interest in the Caucharí-Olaroz lithium project under construction in Jujuy, Argentina. Lithium

Americas through a wholly owned subsidiary, Lithium Nevada, owns 100% of the Thacker Pass lithium project located in

Nevada and the largest known lithium deposit in the United States. The Company trades on both the Toronto Stock Exchange

and on the New York Stock Exchange, under the ticker symbol “LAC”.

For further information contact: 

Lithium Americas Corp.  

Investor Relations 

Suite 300 – 900 West Hastings Street 

Vancouver, BC, V6C 1E5

Telephone: 778-656-5820 

Email: [email protected]

Website: www.lithiumamericas.com

Forward-Looking Statements & Information  

This news release contains “forward-looking information” and “forward-looking statements” (which we refer to collectively as

forward-looking information) under the provisions of applicable securities legislation. Forward-looking information can be

identified by the use of words such as “seek”, “anticipate”, “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”,

“predict”, “propose”, “potential”, “target”, “intend”, “could”, “might”, “should”, “believe”, “scheduled”, “implement” and similar

words or expressions. All statements, other than statements of historical fact, are forward-looking information. Examples of

forward-looking information in this news release include, without limitation, the expected outcome and timing of EIS and permit

applications and other environmental, timing and results of community engagement and other social matters; the timing and

results of the proposed feasibility study on the Thacker Pass project; timing, cost, quantity, capacity and product quality of

production at the Thacker Pass Project; addition of a joint venture partner or other financing options; sufficiency of water rights

and regulatory approvals in connection therewith; estimates of mineral resources and underlying assumptions related thereto,

future exploration activities and results thereof; development of mineral resources and mineral reserves; processing and

engineering technology; and patent applications.

Forward-looking information may involve known and unknown risks, assumptions and uncertainties which may cause the

Company’s actual results or performance to differ materially. This information reflects the Company’s current views with

respect to future events and is necessarily based upon a number of assumptions that, while considered reasonable by the

Company today, are inherently subject to significant uncertainties and contingencies, and accordingly, the Company can give

no assurance that these assumptions and expectations will prove to be correct. With respect to forward-looking information

included in this news release, the Company has made assumptions regarding, among other things: reliability of government

permitting processes and stated deadlines, current technological trends; ability to fund, advance and develop the Project; the

ability to operate in a safe and effective manner; uncertainties relating to receiving and maintaining mining, exploration,

environmental and other permits or approvals; demand for lithium; impact of increasing competition in the lithium business,

including the Company’s competitive position in the industry; general economic conditions; stability and support of legislative,

regulatory and community environment in the jurisdiction where it operates; estimates of and changes to market prices for

lithium and commodities; exploration, development and construction plans and costs for the Project; estimates of mineral

resources and mineral reserves, including whether mineral resources will ever be developed into mineral reserves; reliability of

technical data; anticipated timing and results of exploration, development and construction activities; the ability to achieve

commercial production; and accuracy of budget and construction estimates.

Forward-looking information also involve known and unknown risks that may cause actual results to differ materially, these

risks include, among others: the Project may not be developed as planned, and there is uncertainty as to whether there will

ever be production at the Project; cost overruns; market prices affecting development of the Project; risks with ability to

successfully secure adequate financing or addition of a joint venture partner; risks to the growth of the lithium markets; lithium

prices; inability to obtain required governmental permits and that operations may be limited by government-imposed

limitations; technology risk; inability to achieve and manage expected growth; political risk associated with foreign operations;

risks associated with not having production experience; operational risks; changes in government regulations; changes in

environmental requirements; failure to obtain or maintain necessary licenses, permits or approvals; insurance risk; receipt and

security of mineral property titles and mineral tenure risk; changes in project parameters; uncertainties associated with

estimating mineral resources and mineral reserves, including uncertainties regarding assumptions underlying such estimates;

whether mineral resources will ever be converted into mineral reserves; opposition to development of the Project; surface

access risk; geological, technical, drilling or processing problems; liabilities and risks; health and safety risks; unanticipated

results; unpredictable weather; unanticipated delays; reduction in demand for lithium; inability to generate profitable

operations; intellectual property risks; dependency on key personnel; currency and interest rate fluctuations; and volatility in

general market and industry conditions. Additional risks, assumptions and other factors are set out in the Company’s

management discussion analysis and most recent annual information form, copies of which are available on SEDAR at

www.sedar.com.  

Although the Company has attempted to identify important risks and assumptions, given the inherent uncertainties in such

forward-looking information, there may be other factors that cause results to differ materially. Forward-looking information is

made as of the date hereof and the Company does not intend, and expressly disclaims any obligation to, update or revise the

forward-looking information contained in this news release, except as required by law. Accordingly, readers are cautioned not

to place undue reliance on forward-looking information.