Lithium Americas Provides an Update on the Cauchari-Olaroz Lithium Project
February 28, 2017
Lithium Americas Provides an Update on the Cauchari-Olaroz Lithium Project
Vancouver, Canada: Lithium Americas Corp. (TSX: LAC) (OTCQX: LACDF) ("Lithium Americas" or the
"Company") is pleased to provide an update for the Cauchari-Olaroz lithium project ("Cauchari-Olaroz") in
Jujuy province, Argentina.
Minera Exar S.A. (“Minera Exar”), a 50/50 joint venture company (“JV”) between Lithium Americas and
Sociedad Quimica y Minera de Chile S.A. (“SQM”), continues to advance the Cauchari-Olaroz project as
planned. As previously announced, Minera Exar is pursuing a development plan at Cauchari-Olaroz that
targets 50,000 tonnes per annum ("tpa") of lithium carbonate production capacity in two stages, with each
stage consisting of 25,000 tpa of lithium carbonate. A feasibility study (“Stage 1 DFS”) on the first stage
of 25,000 tpa of lithium carbonate production capacity (“Stage 1”) is nearing completion.
The qualified persons (“QPs”) responsible for preparing the Stage 1 DFS have completed substantially all
capital cost development analysis for Stage 1, with remaining work related primarily to confirming SQM’s
operating cost estimates to a NI 43-101 compliant feasibility study standard. The Company and the QPs
can confirm at this time the following:
• The project capital cost estimate for the construction of Stage 1 is expected to be US$420 – US$430
million before value-added and other applicable taxes (“Taxes”) and working capital;
• The operating cost estimate will be at the low end of the cost curve compared to producing lithium
operations;
• The parties expect to be in a position to commence construction in the first half of 2017;
• The current construction schedule is estimated at two years with production forecast to start in 2019;
and
• During the construction period, Minera Exar’s direct employment in the province of Jujuy is estimated
to be at least 800 people; once in operation, Minera Exar is expected to employ approximately 300
people in permanent positions.
Lithium Americas will be responsible for contributing 50% of capital expenditures for the construction of
Stage 1, amounting to approximately US$210 – US$215 million before Taxes and working capital.
Technical Information
Ernie Burga, a qualified person under NI 43-101, has reviewed and approved the scientific and technical
information in this press release. Further information about the scientific and technical information on
Cauchari-Olaroz in this press release, including a summary of data verification measures, and a
description of the assumptions, parameters and risks associated with this information, will be available in
a NI 43-101 Technical Report that will be filed by Lithium Americas in connection with its disclosure of the
results of the Stage 1 DFS.
About Lithium Americas
Lithium Americas, together with its joint venture partner SQM, is developing the Cauchari-Olaroz lithium
project, located in Jujuy, Argentina, through its 50% interest in Minera Exar S.A. In addition, Lithium
Americas owns 100% of the Lithium Nevada project (formerly Kings Valley project), and RheoMinerals
Inc., a supplier of rheology modifiers for oil-based drilling fluids, coatings, and specialty chemicals.
For further information contact:
Lithium Americas Corp.
Investor Relations
Suite 1100 – 355 Burrard Street
Vancouver, BC, V6C 2G8
Telephone: 778-656-5820
Email: [email protected]
Website: www.lithiumamericas.com
Forward-looking statements
Statements in this release that are forward-looking information are subject to various risks and
uncertainties concerning the specific factors disclosed here and elsewhere in the Company's periodic
filings with Canadian securities regulators. Forward-looking information in this news release includes: (i)
the timing and completion of the Stage1 DFS; (ii) the results of the capital cost estimates, operating cost
estimates and other key inputs in the Stage 1 DFS; (iii) the results of analysis to increase the production
rate at the Cauchari-Olaroz project to 50,000 tpa; (v) the timing for commencement of construction and
production at the Cauchari-Olaroz project. When used in this document, the words such as “intent”,
“target”, “expect”, “estimated” and “scheduled” and similar expressions represent forward-looking
information. Information provided in this document is necessarily summarized and may not contain all
available material information.
All such forward-looking information and statements are based on certain assumptions and analyses
made by Lithium Americas management in light of their experience and perception of historical trends,
current conditions and expected future developments, as well as other factors management believes are
appropriate in the circumstances. These statements, however, are subject to a variety of risks and
uncertainties and other factors that could cause actual events or results to differ materially from those
projected in the forward-looking information or statements. Important factors that could cause actual
results to differ from these forward-looking statements include those described under the heading "Risks
Factors" in the Lithium Americas’ most recently filed MD&A, Annual Information Form and other
continuous disclosure filings, as well as the timing and completion of the investment transactions with
Ganfeng Lithium and Bangchak Petroleum, including settling definitive agreements and other conditions
to completion. The Company does not intend, and expressly disclaims any obligation to, update or revise
the forward-looking information contained in this news release, except as required by law. Readers are
cautioned not to place undue reliance on forward-looking information or statements.