Lithium Americas Announce FID for Thacker Pass Phase 1 and Closes

Strategic Investment from Orion Resource Partners

(All amounts in US$ unless otherwise indicated)

VANCOUVER, British Columbia--(BUSINESS WIRE)--April 1, 2025--Lithium Americas

Corp. (TSX: LAC) (NYSE: LAC) (“Lithium Americas” or the “Company”) today announced

the closing of the previously announced $250 million investment from fund entities managed by

Orion Resource Partners LP (collectively, “Orion”), for the development and construction of

Phase 11 of the Thacker Pass lithium project in Humboldt County, Nevada (“Thacker Pass” or

the “Project”). Contemporaneously, Lithium Americas and General Motors Holdings LLC

(“GM”) (together, the Thacker Pass joint venture (“JV”) partners (“JV Partners”)) announced

the final investment decision (“FID”) for Thacker Pass Phase 1.

HIGHLIGHTS

 As part of closing, Orion has purchased senior unsecured convertible notes in the

aggregate principal amount of $195 million, has paid Lithium Americas $25 million in

exchange for payments corresponding to the minerals produced and gross revenue

generated by Thacker Pass and committed an additional $30 million in aggregate

principal amount of senior unsecured convertible notes available through a delayed draw

facility, subject to the satisfaction of certain conditions (the “Investment”).

 The Investment satisfies all remaining requirements from both the U.S. Department of

Energy (“DOE”) and GM to satisfy all remaining equity capital fundraising requirements

under the previously announced $2.26 billion loan from the DOE (the “DOE Loan”).

 With the Investment, Lithium Americas has achieved fully funded status for the

development of Phase 1 of Thacker Pass at the project and corporate level for the

duration of construction.

 The JV Partners announced FID for construction of Phase 1 of Thacker Pass. Completion

of Phase 1 of Thacker Pass is targeted for late 2027.

 Contemporaneously with FID, GM and Lithium Americas contributed $100 million and

$192 million in cash to the JV, respectively.

Jonathan Evans, Lithium Americas’ President and CEO said, “Today marks another important

milestone in our journey to bring Thacker Pass to production. With our JV Partner, GM, we

announced FID for Phase 1 alongside our other exceptional partners – the U.S. DOE and Orion.

Together, we will develop a U.S.-produced lithium supply chain to reduce American dependence

on foreign suppliers for critical minerals.”

ADVISORS

Evercore Group L.L.C. and Goldman Sachs & Co. LLC are acting as joint lead placement agents

for Lithium Americas, and Vinson & Elkins LLP and Cassels Brock & Blackwell LLP are acting

as legal counsel to Lithium Americas. Torys LLP and Davis Graham & Stubbs LLP are acting as

legal counsel to Orion Resource Partners.

ABOUT LITHIUM AMERICAS

Lithium Americas is committed to responsibly developing the Thacker Pass project located in

Humboldt County in northern Nevada, which hosts the largest known measured lithium resource

(Measured and Indicated) and reserve (Proven and Probable) in the world. Thacker Pass is

owned by a JV between Lithium Americas (holding a 62% interest and is the manager of the

Project) and GM (holding a 38% interest). The Company is focused on advancing Thacker Pass

Phase 1 toward production, targeting nominal design capacity of 40,000 t/y of battery-quality

lithium carbonate. The Company and its engineering, procurement and construction management

contractor, Bechtel, entered into a National Construction Agreement (Project Labor Agreement)

with North America’s Building Trades Unions for construction of Thacker Pass. The three-year

construction build is expected to create nearly 2,000 direct jobs, including 1,800 skilled

contractors. Lithium Americas’ shares are listed on the Toronto Stock Exchange and New York

Stock Exchange under the symbol LAC. To learn more, visit www.lithiumamericas.com or

follow @LithiumAmericas on social media.

QUALIFIED PERSON

The scientific and technical information contained in this news release has been derived from the

technical report entitled “NI 43-101 Technical Report on the Thacker Pass Project Humboldt

County, Nevada, USA,” dated effective December 31, 2024. The disclosure herein has been

reviewed and approved by Dr. Rene LeBlanc, RM-SME, Vice President, Growth and Product

Strategy of the Company, a Qualified Person as defined under National Instrument 43-101. The

technical report is available under the Company’s profile on SEDAR+, in the S-K 1300

Technical Report which is available under the Company’s profile on EDGAR at www.sec.gov

and both reports are available on the Company’s website.

FORWARD-LOOKING INFORMATION

This news release contains “forward-looking information” within the meaning of applicable

Canadian securities legislation, and “forward-looking statements” within the meaning of Section

27A of the Securities Act and Section 21E of the Securities Exchange Act of 1934, as amended

(collectively referred to as “forward-looking information” (“FLI”)). All statements, other than

statements of historical fact, are FLI and can be identified by the use of statements that include,

but are not limited to, words, such as “anticipate,” “plan,” “continues,” “estimate,” “expect,”

“may,” “will,” “projects,” “predict,” “proposes,” “potential,” “target,” “implement,”

“scheduled,” “forecast,” “intend,” “would,” “could,” “might,” “should,” “believe” and similar

terminology, or statements that certain actions, events or results “may,” “could,” “would,”

“might” or “will” be taken, occur or be achieved. FLI in this news release includes, but is not

limited to, expectations regarding satisfaction of draw-down conditions for the DOE Loan; the

timing of first draw on the DOE Loan; expectation about the extent that the JV, DOE Loan, the

Investment and cash on hand would fund the development and construction of Thacker Pass;

expectations and timing on the commencement of major construction and first production;

project de-risking initiatives; expectations related to the construction build, job creation and

nameplate capacity of the Project as well as other statements with respect to the Company’s

future objectives and strategies to achieve these objectives, and management’s beliefs, plans,

estimates and intentions, and similar statements concerning anticipated future events, results,

circumstances, performance or expectations that are not historical facts.

FLI involves known and unknown risks, assumptions and other factors that may cause actual

results or performance to differ materially. FLI reflects the Company’s current views about

future events, and while considered reasonable by the Company as of the date of this news

release, are inherently subject to significant uncertainties and contingencies. Accordingly, there

can be no certainty that they will accurately reflect actual results. Assumptions upon which such

FLI is based include, without limitation, the absence of material adverse events affecting the

Company during the construction of the Project; the ability of the Company to satisfy all draw-

down conditions under the DOE Loan; expectations regarding the Company's financial resources

and future prospects; the ability to meet future objectives and priorities; a cordial business

relationship between the Company and third party strategic and contractual partners; general

business and economic uncertainties and adverse market conditions; the availability of

equipment and facilities necessary to complete development and construction at the Project;

unforeseen technological and engineering problems; political factors, including the impact of the

results of the 2024 U.S. presidential election on, among other things, the extractive resource

industry, the green energy transition and the electric vehicle market; uncertainties inherent to

feasibility studies and mineral resource and mineral reserve estimates; uncertainties relating to

receiving and maintaining mining, exploration, environmental and other permits or approvals in

Nevada; demand for lithium, including that such demand is supported by growth in the electric

vehicle market; current technological trends; the impact of increasing competition in the lithium

business, and the Company’s competitive position in the industry; compliance by joint venture

partners with terms of agreements; the regulation of the mining industry by various

governmental agencies; as well as assumptions concerning general economic and industry

growth rates, commodity prices, resource estimates, currency exchange and interest rates and

competitive conditions. Although the Company believes that the assumptions and expectations

reflected in such FLI are reasonable, the Company can give no assurance that these assumptions

and expectations will prove to be correct.

Readers are cautioned that the foregoing lists of factors are not exhaustive. There can be no

assurance that FLI will prove to be accurate, as actual results and future events could differ

materially from those anticipated in such information. As such, readers are cautioned not to place

undue reliance on this information, and that this information may not be appropriate for any

other purpose, including investment purposes. The Company’s actual results could differ

materially from those anticipated in any FLI as a result of the risk factors set out herein and in

the Company’s filings with securities regulators.

The FLI contained in this news release is expressly qualified by these cautionary statements. All

FLI in this news release speaks as of the date of this news release. The Company does not

undertake any obligation to update or revise any FLI, whether as a result of new information,

future events or otherwise, except as required by law. Additional information about these

assumptions and risks and uncertainties is contained in the Company’s filings with securities

regulators, including the Company’s most recent Annual Report on Form 10-K and most recent

management’s discussion and analysis for our most recently completed financial year and, if

applicable, interim financial period, which are available on EDGAR at www.sec.gov and

SEDAR+ at www.sedarplus.ca. All FLI contained in this news release is expressly qualified by

the risk factors set out in the aforementioned documents.

The Company is relying upon the exemption set forth in Section 602.1 of the Toronto Stock

Exchange (“TSX”) Company Manual, which provides that the TSX will not apply its standards

to certain transactions involving eligible interlisted issuers on a recognized exchange.

____________________

1 Phase 1 is the initial phase of production at Thacker Pass, targeting 40,000 tonnes per year (“ t/y”) of battery-grade

lithium carbonate.