Vancouver, British Columbia--(Newsfile Corp. - May 14, 2020) -

Los Andes Copper Ltd.

(TSXV: LA) ("Los Andes" or the

"Company") is pleased to present an update on the work conducted in order to progress the Pre-Feasibility Study ("PFS") on

the Company's Vizcachitas Project ("Vizcachitas" or the "Project").

The Preliminary Economic Assessment (PEA) delivered in June 2019 provided a conceptual plan for developing the

Vizcachitas Project. A PFS is currently underway and areas of work being advanced include, processing, tailings facility,

infrastructure, geology, mine plan, environment and social and community engagement.

The current COVID-19 situation, while delaying some of the metallurgical testwork and field work, has not delayed the progress

of the main engineering study. All employees and subcontractors are working from home where possible and only a small group

of individuals are working to prepare samples in the Company's Santiago core storage area.

Highlights of the main advances in the PFS

Testwork has shown that a HPGR circuit is feasible for the Project and could provide enhanced project economics with

lower energy consumption and increased operating flexibility.

The mineral is amenable to filtering and dry-stack tailings. This change would significantly reduce the Project's water

consumption, footprint and environmental impact.

Due to the reduced footprint required for dry stacked tailings, it is possible to have all project infrastructure in one

operating complex in the Rocin Valley. The PEA outlined infrastructure in both the Rocin Valley and the Chalaco Valley.

Fernando Porcile, Executive Chairman of Los Andes, commented:

"I am delighted that we are continuing to make significant progress with the PFS during these difficult times."

"The results from the testwork carried out to date are encouraging and now with the approval of the environmental declaration

for the PFS drill programme allowing us to carry out further drilling in the coming months, we will be able to complete certain

other aspects of the study, therefore further contributing to the delivery of a robust PFS."

"I look forward to keeping the market up to date with our progress."

Processing

Studies on the feasibility of using a HPGR circuit are progressing and show the potential for enhanced project economics, lower

energy consumption, reduced maintenance and increased operational flexibility. HPGR technology has been identified as the

most attractive grinding alternative, given the data obtained from the preliminary testwork conducted to date.

The flotation optimisation testwork conducted to date has shown revised conditions (when compared to the PEA) which should

increase overall copper and molybdenum recoveries by improving floatability with reduced grinding requirements. Flotation

testing was conducted on the "Upper Zone" composite from the 2018 testwork which had the lowest metallurgical recoveries

from those composite samples.

The mineral characterisation carried out in 2017-2019 on over 80 variability samples showed that the mineralized rock, with

copper head grades between 0.18 - 1.00%, molybdenum head grades between 30 - 500 ppm, had a low presence of clays

(mainly kaolinite), favouring flotation and water recovery performance.

Tailings Facility

The settling and filtering testwork conducted to date is indicating that filtered dry-stacked tailings are a viable alternative to

thickened tailings. The 2019 laboratory settling testwork with four composite samples from the 2018 testwork shows good

settling rates for tailings, even for the worst samples. The Vizcachitas mineralisation has favorable filtration rates suitable for belt

filters. Nevertheless, belt filters are being considered in combination with pressure filters to treat the finer fraction of tailings and

retain excess filtering capacity to reduce operational risks.

Dry-stacked tailings would:

Reduce water consumption by approximately 50%

Reduce the Project's footprint

Be better suited for areas of high seismic activity

Be transported by trucks or conveyors

Eliminate the need for a traditional dam wall

Reduce the environmental risk by avoiding contact with ground water

Infrastructure

All the project infrastructure is located in the Rocin Valley, reducing the Project's footprint and environmental impact.

The PFS layout has the crushing and grinding area built over a mine waste backfill platform close to the mine and the

concentrator is built on the east side of the Rocin Valley. CAPEX related to excavations and earthworks is reduced as pre-

stripping is used as the backfill.

Dry filtered tailings are stacked within the Rocin Valley.

A 220 kV power line would be routed to a substation near the city of Los Andes, reducing its length from a 105 km line in

the PEA to 65 km line.

The concentrate would be loaded into sealed contains (Rotainers) and transported by truck to a transfer station near San

Felipe, where its freighted by railway to the Ventanas, Valparaíso or San Antonio ports.

Ongoing and outstanding tasks

The Company has also been progressing a number of other areas of the PFS.

Drilling

With the environmental approval obtained in April 2020 and the corresponding resolution issued this week, additional drilling can

commence during the third quarter of this year. The information from this drilling programme will be used to update the

geological and domain models and the Company expects to then be able to generate an updated resource estimate.

Mine Plan

Work to date has included operational pit design for the definition of PFS drilling, push-back sequence strategy, waste dump

strategy and preliminary design, and definition of early earth movement and upper level access for the process plant and

infrastructure engineering.

With the results of the upcoming drilling, the Company expects to be able to finalize an operational mine plan and prepare a

reserve statement. As part of this process, the drilling results will also be used to prepare an updated geotechnical assessment.

Processing

A program of additional composite preparation and testing is underway, as well as the definition of further variability samples

which are to be included in the testwork. Pending work also includes selective molybdenum and copper flotation testing, critical

water content testing (Atterberg limits) and environmental characterization of the tailings.

Infrastructure

The main ongoing items include the trade-off studies for water procurement infrastructure and preliminary engineering, and the

design of the Rocín River diversion intake and tunnel.

Environment

Approval of the environmental declaration ("DIA") for PFS drilling has been obtained. The work for the environmental impact

assessment ("EIA") for the construction and operation of the Project is underway, including the identification of environmentally

sensitive areas to be avoided during project design, seasonal environmental baseline work and the implementation of the river

monitoring stations for hydrology and water quality baseline studies. Further impact studies and baseline work (air quality,

paleontological, archeological, etc.) will be required once the Project is further defined.

Social & Community Engagement

Meetings with community organizations and authorities to present the Project have been taking place on an ongoing basis. The

Company has implemented a program of community engagement activities which has included funding educational and other

social programs. The recent environmental approval has included commitments for social programs which are being

implemented.

As the Project is further defined, the social baseline work needs to be updated and expanded. A formal community consultation

process has to be conducted as part of the EIA preparation This process can only be carried out once the key elements of the

Project are determined.

Time Line

Depending on how the COVID-19 situation develops, the Company expects the Pre-Feasibility Study to be completed by the

end of the first quarter in 2021.

A presentation has been prepared with further details on the PFS update and is available on the Company's website:

https://www.losandescopper.com/

.

For more information please contact:

Fernando Porcile, Executive Chairman

Tel: +56 2 2954-0450

Antony J. Amberg, President & CEO

Tel: +56 2 2954-0450

Blytheweigh, Financial PR

Megan Ray

Rachael Brooks

Tel: +44 207 138 3203

E-Mail:

[email protected]

or visit our website at:

www.losandescopper.com

.

Follow us on twitter

@LosAndesCopper

Follow us on LinkedIn

Los Andes Copper Ltd

About Los Andes Copper Ltd.

Los Andes Copper Ltd. is an exploration and development company with an 100% interest in the Vizcachitas Project in Chile.

The Company is focused on progressing the Project, which is located along Chile's most prolific copper belt, into production.

Vizcachitas is one of the largest copper deposits in the Americas not controlled by the majors and the Company believes it will

be Chile's next major copper mine.

The Project is a copper-molybdenum porphyry deposit, located 120 km north of Santiago, in an area of very good infrastructure.

The Company's Preliminary Economic Assessment (the "PEA"), delivered in June 2019, highlights that the Project has a post

tax NPV of $1.8 billion and an IRR of 20.77%, based on a $3 per pound copper price. It also has a Measured Resources of

254.4 million tonnes having a grade of 0.439% copper and Indicated Resource of approximately 1.03 billion tonnes having a

grade of 0.385% copper. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Please

refer to the technical report dated June 13, 2019, with an effective date of May 10, 2019 and titled "Preliminary Economic

Assessment of the Vizcachitas Project", prepared by Tetra Tech.

The PEA is preliminary in nature, it includes inferred mineral resources that are considered too speculative geologically to have

the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no

certainty that the PEA will be realized.

Additionally, there is significant exploration upside at Vizcachitas with potential to increase the resource base beyond the initial

45-year mine life.

Los Andes Copper Ltd. is listed on the TSX-V under the ticker: LA.

Qualified Persons

Antony Amberg CGeol FGS, the Company's President and CEO, and Romke Kuyvenhoven, Member of Chilean Mining

Commission, the Company's Senior Metallurgical Consultant, are the qualified persons who have reviewed and approved the

scientific and technical information contained in this news release.

Certain of the information and statements contained herein that are not historical facts, constitute "forward-looking

information" within the meaning of the Securities Act (British Columbia), Securities Act (Ontario) and the Securities Act

(Alberta) ("Forward-Looking Information").

Forward-Looking Information is often, but not always, identified by the use of words

such as "seek", "anticipate", "believe", "plan", "estimate", "expect" and "intend"; statements that an event or result is "due" on

or "may", "will", "should", "could", or might" occur or be achieved; and, other similar expressions. Forward-looking Information

in this news release includes, without limitation, statements regarding the Vizcachitas Project becoming Chile's next major

copper mine, the ability to use filtering and dry-stacked tailings and the anticipated benefits therefrom, the Company's

expectation that drilling will occur in the third quarter and that it will be able to prepare an updated resource estimate and

reserve statement and finalize its operational mine plan, and the expected timing of completion of the PFS.

Forward-Looking

Information involves known and unknown risks, uncertainties and other factors which may cause the actual results,

performance or achievements of the Company, or industry results, to be materially different from any future results,

performance or achievements expressed or implied by such Forward-Looking Information; including, without limitation, the

achievement and maintenance of planned production rates, the evolving legal and political policies of Chile, the volatility in

the Chilean economy, military unrest or terrorist actions, metal and energy price fluctuations, favourable governmental

relations, the availability of financing for activities when required and on acceptable terms, the estimation of mineral

resources and reserves, current and future environmental and regulatory requirements, the availability and timely receipt of

permits, approvals and licenses, industrial or environmental accidents, equipment breakdowns, availability of and

competition for future acquisition opportunities, availability and cost of insurance, labour disputes, land claims, the inherent

uncertainty of production and cost estimates, currency fluctuations, expectations and beliefs of management and other risks

and uncertainties, including those described in Management's Discussion and Analysis in the Company's financial

statements.

Such Forward-Looking Information is based upon a number of assumptions, including assumptions regarding

the timing and receipt of regulatory approvals; global and Chilean economic, political and market conditions; the ability of the

Company and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions

and programs on reasonable terms acceptable to the Company; the price of metals and energy; and the ability of third

parties service providers to deliver service in a timely manner.

Among the factors that have a direct bearing on the

Company's future results of operations and financial conditions are changes in project parameters as plans continue to be

refined, a change in government policies, competition, currency fluctuations and restrictions and technological changes,

among other things.

Should one or more of any of the aforementioned risks and uncertainties materialize, or should

underlying assumptions prove incorrect, actual results may vary materially from any conclusions, forecasts or projections

described in the Forward-Looking Information.

Accordingly, readers are advised not to place undue reliance on Forward-

Looking Information.

Except as required under applicable securities legislation, the Company undertakes no obligation to

publicly update or revise Forward-Looking Information, whether as a result of new information, future events or otherwise.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture

Exchange) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/55861