Los Andes Copper Announces Positive PFS for Vizcachitas with a US$2.77 Billion Post-Tax NPV and 24% IRR
Los Andes Copper Announces Positive PFS
for Vizcachitas with a US$2.77 Billion Post-Tax
NPV and 24% IRR
Vancouver, British Columbia--(Newsfile Corp. - February 23, 2023) - Los Andes Copper Ltd. (TSXV:
LA) (OTCQX: LSANF) ("Los Andes" or the "Company") is pleased to announce the results of a positive
Pre-Feasibility Study ("PFS") at its 100% owned Vizcachitas Project ("Vizcachitas" or the "Project"), a
world class porphyry copper project, located 150 km north of Santiago. The PFS has been prepared by
Tetra Tech Sudamérica S.A, a leading international engineering firm. A conference call and webcast to
discuss these results will be held on Friday, February 24, 2023, at 12.00 p.m. Eastern Standard Time.
To register please contact
whereafter the webinar details will be sent to you.
All values in this release are reported in US dollars.
To view a 3D VRIFY presentation of the PFS results, click on the following
link:
https://vrify.com/decks/12765
Vizcachitas PFS Highlights
Robust Economics
A $2.8 billion post-tax net present value ("NPV") using an 8% discount rate and an internal rate of
return ("IRR") of 24% at $3.68/pound ("lb") copper, $12.9/lb molybdenum and $21.79/ounce ("oz")
silver.
Pre-production capital cost of $2.4 billion, with a construction period of 3.25 years.
Payback period of 2.5 years from initial production.
World-Class Resource
Proven & Probable Reserves of 1.22 billion tonnes at 0.36% copper, 136 ppm molybdenum, 1.1
g/t silver, which equates to a copper equivalent ("CuEq") grade of 0.41% (Proven Reserves of 302
million
tonnes at 0.41% copper, 135 ppm molybdenum, 1.2 g/t silver; and Probable Reserves of
917 million
tonnes at 0.34% copper, 136 ppm molybdenum, 1.1 g/t silver).
Measured & Indicated Resources increased by 16% to 14.8 billion lbs CuEq (Measured Resource
of
2.605 billion lbs copper, 84 million lbs molybdenum and 11 million oz silver, and Indicated
Resource
of 10.416 billion lbs of copper, 442 million lbs of molybdenum, and 43 million oz of silver)
and Inferred
Resource increased by 130% to 15.4 billion lbs CuEq (13.747 billion lbs copper, 495
million lb
molybdenum, 55 million oz silver) with respect to the June 2019 Preliminary Economic
Assessment
("PEA").
Long-Scale, Long-Life, High-Margin Production
Average annual production of approximately 183,017 tonnes of copper at a C1 cost of $0.93/lb
copper (net of by-products) for the first 8 years.
Initial Project Life of Mine ("LOM") 26 years producing 8.763 billion lbs copper, 273.3 million lbs
molybdenum, and 32.7 million oz silver.
Realized CuEq metal price (net of smelter return and selling expenses) of $3.50/lb copper sold,
yielding a 44% all-in-sustaining margin.
Low strip ratio (waste:ore) of 1.54:1 for first 8 years, and strip ratio 2.33:1 for LOM.
Favourable metallurgy including low levels of clay, resulting in high copper recoveries (average of
91.1%) and supporting the use of filtered tailings.
Sustainable and Responsible Mining
Signed letter of intent for desalinated water, eliminating the need to draw on continental water.
Reduced water consumption by approximately 50% (from previous design) through use of dry-
stacked filtered tailings.
Reduced power consumption by 25% (from previous design) through use of high pressure grinding
rolls ("HPGR") technology.
CO2 emissions Scope 1 projected at 1.02 h CO2e / t CuEq, and Scope 2 at 0.
Future Opportunities
Potential opportunities to meaningfully improve the Project include: (i) drilling to upgrade inferred
resources and bring them into the mine plan potentially increasing the LOM, reducing operating
expenses, capital expenses and strip ratio; and, (ii) further drilling to define the extent of
mineralization, deposit currently open at depth, east and west.
An independent technical report for the PFS, prepared in accordance with NI 43-101, will be available
under the Company's SEDAR profile within the next 45 days.
Los Andes Copper' CEO, Santiago Montt, commented on the PFS:
"
I am extremely pleased to announce the results of the Pre-Feasibility Study for the proposed
Vizcachitas mine in Chile. It shows that Vizcachitas is clearly a Tier 1 asset that has the potential to
join the ranks as one of the largest and most profitable copper mines in Chile.
The new mine design incorporates a number of optimizations including expanding access works,
allowing for a faster ramp-up of production and minimizing uphill material movement and haulage
distances. This has reduced the OPEX and led to a shorter payback further strengthening the
economics of the Project.
Our new sustainable and responsible design considers the use of HPGR to
reduce energy consumption, dry-stacked filtered tailings to reduce water consumption and footprint,
and desalinated water.
Vizcachitas benefits from being situated in a country with an established mining industry and in close
proximity to existing infrastructure including power, roads and ports. All of these factors have enabled
the Project to meaningfully reduce its initial CAPEX requirement
. There is also
a skilled labor force in
the nearby towns and cities of Putaendo, San Felipe and Los Andes.
The Project is economically robust with the potential for considerable upside through further drilling to
upgrade the Inferred Resource to Measured and Indicated, thereby bringing them into the mine plan
."
Los Andes Copper' Chairman, Eduardo Covarrubias, commented on the PFS:
"The lack of new discoveries of this scale over the last 10 years and the increasing demand for copper
highlights the importance of projects like Vizcachitas. The PFS demonstrates a robust, economically
attractive project with long mine life and potential for significant further upside.
The study focused on ensuring Vizcachitas would lead the way in sustainable mining, and we are
delighted to announce that our three key targets: to reduce water usage, power consumption and the
footprint of the Project have all been met, allowing us to deliver a mine that minimizes its impact on
the environment.
"
Project Description
The Vizcachitas Project is located in the Andes Mountains, in the Province of San Felipe, Fifth Region of
Chile, approximately 150 km northeast of Santiago, Chile, and 46 km northeast of Putaendo, San Felipe
Province. The Project is 100% owned by Los Andes Copper Ltd., a company based in Vancouver and
listed on the TSX Venture Exchange. The Project is located at just 1,950 m.a.s.l., in proximity to other
world-class copper-molybdenum porphyries that belong to the same metallogenic belt.
The Vizcachitas Project is a mineralized copper-molybdenum porphyry system associated with a
complex of hydrothermal breccias and porphyries within Miocene volcanic rocks. The Vizcachitas
Project contains Measured and Indicated Resources of 14.801 billion pounds CuEq (Measured
Resource of 2.605 billion lbs copper, 84 million lbs molybdenum and 11 million oz silver, and Indicated
Resource of 10.416 billion pounds of copper, 442 million lbs of molybdenum, and 43 million oz of silver)
and Inferred Resources of 15.444 billion pounds CuEq (13.747 billion lbs of copper, 495 million lb of
molybdenum, and 55 million oz of silver).
It is one of the largest undeveloped copper projects in South
America not controlled by a major mining company.
The PFS contemplates that Vizcachitas would be mined using conventional open pit methods. From the
open pit the ore would be trucked to a concentrator designed to process 136,000 tonnes per day of ore.
The ore would be fed into a three-stage crushing plant using HPGR technology as the tertiary crusher.
The ore would be crushed to 240 microns, and sent as a slurry to the flotation stage located further down
the valley. The flotation stage would produce a clean copper and silver concentrate and a separate
molybdenum concentrate. The tailings produced in the flotation stage would be thickened and filtered to
15% moisture. The filtered tailings would then be co-mingled with the mine waste rock and deposited in
a combined tailings/waste rock facility.
The Vizcachitas Project is designed to use desalinated water, supplied by a third-party consortium.
Power would be supplied via 60km line connecting to the national grid. Concentrate would be
transported in rotainers (sealed rotating containers) by truck 145km to the Port of Ventanas with the
Ports of Valparaiso and San Antonio as additional options. There are 35km of existing roads that would
require upgrading between Vizcachitas and Putaendo. Rail transportation from San Felipe to any of the
three ports is a further alternative to be evaluated.
Social & Environmental
The PFS was designed to adopt the latest proven sustainable mining technologies. The focus was on
securing a desalinated water supply and reducing water consumption, power consumption and the
footprint
of the Project.
All of these targets have been met. The Company has signed a letter of intent with a desalinated water
consortium to secure a water supply for the Project removing any concerns over the use of continental
water in an area that has been heavily impacted by drought. The plan under discussion with the
consortium also includes providing water at preferential rates to community groups along the pipeline
route in the Putaendo and Petorca valleys.
The use of dry-stacked filtered tailings reduces the water consumption of the Project by approximately
50%, (compared to thickened tailings). It also reduces the footprint of the Project by 500 hectares
compared to the PEA and is now designed to be situated in only one valley.
The introduction of HPGR technology has reduced power consumption by 25% vs a SAG circuit that was
previously considered in the PEA.
The Company has projected low CO2 emissions. Scope 1: 178,389 t CO2e/year, or 1.02 t CO2 per t
CuEq produced; potential to have Scope 2 at zero as long as the power market continues to have
renewable availability for the full energy supply of the Project. The Company will continue to look for
opportunities to further reduce Scope 1 emissions.
Communication with the local communities and public authorities has continued throughout the PFS with
the Community and Corporate Affairs team working closely with all interested parties.
Summary of Vizcachitas PFS Economic Results
Pre-Tax NPV (8%) & IRR
$4.0 billion NPV
29% IRR
Post-Tax NPV (8%) & IRR
$2.8 billion NPV
24%
Undiscounted Post-Tax Cash Flow (LOM)
$9.5 billion
Payback Period from Start of Operations
2.5 years
Economic Assumptions*
$3.68/lb Cu
$12.9/lb Mo
$21.79/oz Ag
Initial CAPEX
$2.441 billion
C-1 Cash Costs (net of by-products)
First 8 years
LOM
$0.93/lb Cu
$1.25/lb Cu
AISC
First 8 years
LOM
$2.13/lb Cu
$2.35/lb Cu
Mill Throughput
136,000tpd
Average Annual Production
First 8 years
LOM
183,017 t Cu
152,883 t Cu
Strip Ratio (waste:ore)
First 8 years
LOM
1.54
2.33
Initial LOM
26 years
* The NPV is based on long-term consensus copper and silver prices as calculated by a leading Canadian bank and molybdenum
long-term forecast price
from CRU.
The Project's Post Tax Cash Flow is shown in the following chart.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/916/155910_44e725f4942f2b7c_002full.jpg
Copper contributes 88% of the net revenue, followed by molybdenum with 10%, and the balance being
silver credits in copper concentrate.
NPV Sensitivities
The sensitivity analysis provides a range of outcomes for the Project when the key parameters are
varied from their base-case values. The NPV estimate is most sensitive to the copper price, followed by
the discount rate applied and the total operating costs.
The Post-tax NPV ranges from $822 million to $5.498 billion as the applied copper price is varied
between $2.75/lb Cu and $5.00/lb Cu.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/916/155910_44e725f4942f2b7c_003full.jpg
The Post-tax NPV ranges from $1.778 billion to $4.332 billion as the discount rate is adjusted between
11% and 5%. The Post-tax NPV remains positive in all isolated sensitivity scenarios presented.
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/916/155910_44e725f4942f2b7c_004full.jpg
The sensitivity of the post-tax NPV and IRR to changes of molybdenum price, initial CAPEX and OPEX
are illustrated in the three following figures:
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/916/155910_44e725f4942f2b7c_005full.jpg
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/916/155910_44e725f4942f2b7c_006full.jpg
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/916/155910_44e725f4942f2b7c_007full.jpg
CAPEX and OPEX
The initial capital, expensed over the first four years of the Project, amounts to $2.4 billion. The deferred
and sustaining capital over the remainder of LOM amounts to $1.5 billion. A breakdown of capital is
presented in the tables below.
Total Initial Capital Expenditures ($ '000)
2 440 955
Total Direct
1 640 403
Mine
436 050
Plant & Infrastructure
1 204 353
Indirect
454 104
Contingencies
346 449
Total LOM Capital Expenditures ($ '000)
3 934 646
Total Initial Capital Expenditures
2 440 955
LOM Deferred & Sustaining CAPEX (excluding closure costs)
1 493 691
Closure Costs ($ '000)
264 107
Operating costs
The associated operating costs are summarised in the table below.
Total Operating Costs ($/tonne)
11.11
Mining cost
5.02
Processing cost
3.90
Infrastructure
1.20
Indirect cost
0.30
Stockpile rehandling
0.70
Initial Vizcachitas Mineral Reserve Statement
The Initial Proven and Probable Mineral Reserves for the Vizcachitas Project are 10.889 billion lbs of
CuEq (9.623 billion lbs copper, 365 million lbs molybdenum and 43.6 million oz silver). These reserves
are contained within a 26-year mine life open pit and processed in a plant with a throughput of 136,000
tonnes per day. The Initial Mineral Reserve estimate for Vizcachitas, shown below, has an effective date
of
December 2, 2022.
Category
Tonnage
(Mt)
Grade
Contained Metal
Cu
Mo
Ag
CuEq
Cu
Mo
Ag
CuEq
(%)
(ppm)
(g/t)
(%)
(Mlb)
(Mlb)
(Moz)
(Mlb)
Proven
302
0.41%
135
1.2
0.45%
2,714
89.8
11.9
3,031
Probable
918
0.34%
136
1.1
0.39%
6,908
275.3
31.8
7,858
Proven &
Probable
1,220
0.36%
136
1.1
0.40%
9,623
365.0
43.6
10,889
Notes
1
.
Mineral Reserves were classified using CIM Definition Standards (2014).
2
.
Mineral Reserves have an effective date of December 2, 2022.
3
.
Mineral Reserves are included within the Mineral Resources.
4
.
The Qualified Person for the estimate is Mr. Severino Modena, BSc, Mining Engineer, MAusIMM, Member of the Chilean Mining Commission,
and a Tetra Tech Sudamérica employee.
5
.
The Mineral Reserve has a metallurgical cut-off based on processing plant design specifications of 0.18% Cu for direct mill feed.
6
.
Due to rounding, numbers may not add precisely to the totals.
7
.
The Mineral Reserves estimate uses a marginal phase analysis through a cut-off grade optimization software (COMET).
8
.
The Mineral Reserves are contained within operational phases defined with a COMET optimized mining schedule, which includes a stockpiling
strategy. Key inputs for that process are:
i. Metal prices of $3.5/lb copper and $12/lb molybdenum.
ii. Mining Cost of $1.59/t at a reference elevation of 1990 m.a.s.l., plus costs adjustments of $0.014/t per bench above reference and $0.032/t
per bench below reference.
iii. Processing cost of $5.7/t milled.
iv. General and Administration cost of $0.30/t milled.
v. Pit slopes angles varying from 44° to 52°.
9
.
Process recoveries are based on lithology for both copper and molybdenum, except for a sector with a fixed copper recovery value.
Mineral Resource
Measured and Indicated Resources are 1,541 million tonnes grading 0.436% CuEq (0.383% copper,
155 ppm molybdenum and 1.1 g/t silver) using a 0.25% copper cut-off. The Inferred Resource is 1,823
million tonnes grading 0.384% CuEq (0.342% Copper, 123ppm molybdenum, 0.9g/t silver) using a
0.25% copper cut-off. The Measured and Indicated Resources increased by 16% to 14.801 billion lbs
CuEq (13.021 billion lbs copper, 526 million lbs molybdenum and 54 million oz silver). The Inferred
Resource increased by 130% to 15.444 billion lbs CuEq (13.747 billion lbs copper, 495 million lbs
molybdenum and 15 million oz silver) with respect to the June 2019 PEA.
The resource estimate was calculated from 168 drill holes totaling 58,628 meters of drilling. This drilling
was used to generate an updated geological model, completed during 2022, that provided the basis to
separate the estimation domains used for the resource estimation.
The resource estimate presented below is the total Measured & Indicated and Inferred Resources and
has an effective date of February 7, 2023.
Resource
Classification
@
0.25% Cu cut-
off
Tonnage
(Mt)
Cu
(%)
Mo
(ppm)
Ag
(g/t)
CuEq
(%)
Cu
(Mlb)
Mo
(Mlb)
Ag
(Moz)
CuEq
(Mlb)
Measured
Resources
273
0.433
139
1.3
0.482
2,605
84
11
2,900
Indicated
Resources
1,268
0.373
158
1.0
0.426
10,416
442
43
11,901
Measured and
Indicated
Resources
1,541
0.383
155
1.1
0.436
13,021
526
54
14,801
Inferred
Resources
1,823
0.342
123
0.9
0.384
13,747
495
55
15,444
Notes
1
.
Mineral Resources were classified using CIM Definition Standards (2014).
2
.
The Mineral Resources effective date is February 7 2023
3
.
Mineral Resources are inclusive of Mineral Reserves.