Koryx Copper Announces Pre-Feasibility Results for the Haib Copper Project, Southern Namibia

Economic Studies

Koryx Copper S.A. 17, Boulevard Friedrich Wilhelm Raiffeisen Gasperich, L-2411 Luxembourg

135,000 MT ANNUAL CU PRODUCTION (1ST 10 YEARS) 17,000 OZ ANNUAL AU PRODUCTION (1ST 10 YEARS) 1.22 MILLION LB ANNUAL PAYABLE MO (1ST 10 YEARS) $1.72/LB C1 COST AND $2.07/LB AISC (1ST 10 YEARS) $14,985 MT CUEQ CAPITAL INTENSITY (1ST 10 YEARS) $2.5 BILLION AFTER-TAX NPV8% AND 25% POST-TAX IRR $2.06 BILLION BUILD CAPEX AND 24 YEAR MINE LIFE M&I&I RESOURCES OF 4.35 MILLION MT CONTAINED CU PROBABLE RESERVES OF 3 MILLION MT OF CONTAINED CU PFS Highlights

• Post-tax NPV8% of US$2.5bn (pre-tax US$4.2bn) and post-tax IRR of 25% (pre-tax 31%), at base-case price of US$5.00/lb Cu, US$3,500/oz Au, and US$22/lb Mo • 145ktpa of gross annual CuEq production (average first 10 years) and 117ktpa (life-of-mine, (“LOM”)), and 2.61 Mt total LOM copper in concentrate production • 130ktpa of average annual payable copper production (average first 10 years) and 105ktpa (LOM) • US$2.06bn upfront capital cost, incl. US$133m of project contingency and US$152m of capitalised pre-strip, with sustaining capital of US$639m over the LOM. • Average annual payable Au production of 15,000 oz (first 10 years) and 12,000 oz per annum (LOM) • Average annual payable Mo production of 1.22 million lb (first 10 years) and 1.13 million lb (LOM) • C1 cash cost of US$1.72/lb (net of byproducts, first 10 years) and US$2.19/lb (LOM) • All-in sustaining cost (AISC) of US$2.07/lb (first 10 years) and US$2.52/lb (LOM) • Capital intensity of $14,985/mt of annual payable CuEq production (Years 1 – 10) and $18,584/mt of annual payable CuEq production (LOM) • Conventional open pit with staged pushbacks and trolley-assisted haulage, mined by contractor, with a life-of-mine strip ratio of 0.98:1 • A conventional copper sulphide processing route using three-stage crushing (including HPGR), ball milling with coarse gangue rejection of 25% of ROM mill feed, followed by a common hybrid Jameson and Tank Cell flotation circuit configuration • LOM production schedule of 48Mtpa crushing throughput for approximately 1.1bn tonnes over 24 years, prioritising higher-grade feed (approximately 0.32% Cu) in the early years • LOM copper recovery of 87.3% (89.5% 1st 10 years) to a bulk concentrate grading 21.8% Cu, with molybdenum and gold recovered as by-products • Tailings Storage Facility selected from nine alternatives, with capacity of approx. 1.15 billion tonnes, located close to the processing plant to minimise pumping costs • 220kV overhead powerline connection to NamPower's Harib substation combined with approximately 417MWp of on-site solar PV and 361MWh of battery storage, supplying approximately 45% of life-of-mine energy • Water supply of 20Mm3 per annum from the Orange River incl. off-channel storage dam to manage seasonality. Permitting underway and signed NamWater MOU in place • All key permits (Mining License & Environmental Clearance Certificate) are targeted to be completed by mid 2027, paving the way for commencement of early works construction by end of 2027. • Definitive Feasibility Study to support project financing and a construction decision to begin in early 2027 and expected to take one year to complete

Live, online webinar conference call to discuss PFS results: Date: Wednesday, November 18th, 2026 Time: 10:00am EST, 17:00 Namibia time Webcast Registration Link: https://bit.ly/4zJJw3z

Koryx Site Visit & Investor Day to be held on site on 4/5 February 2027. Contact Management for Details.

Luxembourg, November 17, 2026: Koryx Copper S.A. (TSXV:KRY) (NSX:KYX) (OTCQX:KRYXF) (“Koryx” or the “Company”) is pleased to announce the results of the Pre-Feasibility Study (“PFS”) for the wholly-owned Haib Copper Project (“Haib” or the “Project”) in southern Namibia. Haib is a massive, disseminated porphyry copper (“Cu”) deposit with associated molybdenum (“Mo”) and gold (“Au”) and is planned as a large-scale open pit mining and conventional sulphide milling and flotation, producing separate Cu and Mo concentrates.

Heye Daun, Koryx President & CEO commented: “We are very pleased with the excellent results of this PFS, which have far exceeded our initial expectations. With a total mineral resource of 4.35mt of contained copper (plus significant by-product credits) and an average annual gross CuEq production rate of 145ktpa (first 10 years), this PFS undoubtedly benchmarks Haib as a truly world-class copper development project in a premium jurisdiction, Namibia. I am very proud of our dedicated and highly professional Koryx team, with assistance from various excellent Namibian and Southern African professional service providers, especially DRA Global Limited, Knight Piésold and Qubeka Mining Consultants, who together delivered the Haib Cu/Mo/Au project as a tier 1 copper development project of global stature. Major project improvements comprise (i) the completion of a bigger and significantly higher-grade mineral resource and maiden ore reserve (ii) process simplification via the abandonment of the heap leach facility and associated production, (iii) the use of coarse particle flotation and Jameson Cell technology in flotation and (iv) extensive flow sheet optimization which has materially improved the Haib project across all metrics compared with the Preliminary Economic Assessment (“PEA”) completed in September 2025. The next twelve (12) months will be focused on (i) the completion of the Definitive Feasibility Study (“DFS”), (ii) raising finance, (iii) finishing permitting in preparation for early works commencement late in 2027 and construction commencement in 1Q 2028.”

2 Property Description and Ownership

Haib is a porphyry copper exploration project located in the Karas Region of southern Namibia approximately six kilometres north of the border with South Africa and between 12km and 15km east of the tarred B1 highway that connects Namibia with South Africa. Koryx has a 100% interest in Deep South Mining Company (Pty) Ltd., a Namibian subsidiary which in turn has a 100% interest in Haib Minerals (Pty) Ltd. (“Haib Minerals”), which holds the exploration rights to the Project. Exclusive Prospecting Licence (“EPL”) 3140 allows for the exploration of base, rare and precious metals over an area of 36,589 hectares.

Results of PFS Financial Evaluation

Mining is expected to run for 15 years after a pre-strip period and feed the processing plant, which has been sized in the PFS base case for a capacity of 48 million tonnes per annum (“Mtpa”) of run of mine (“ROM”) material for 24 years including 9 years to process reclaimed low-grade stockpiles from Year 16 to Year 24.

A PFS financial model was developed from the updated studies with the following techno-economic results.

Table 1: PFS Financial Valuation Results US$11,023/t US$13,000/t Units Pre-Tax Post-Tax Pre-Tax Post-Tax NPV8% US$m 4,205 2,538 6,335 3,875 IRR % 30.6% 24.9% 39.9% 32.2% Payback Period Years 3.9 3.9 3.3 3.5 LOM Cashflow US$m 11,711 7,425 16,435 10,378 Upfront Capex 1 US$m 2,059 Sustaining Capex 2 US$m 639

Years 1 - 10 LOM Ave Annual Cu Production 135 109 C1 Cash Costs 3 US$/lb 1.72 2.19 AISC Costs 4 US$/lb 2.07 2.52 Capital Intensity payable CuEq US$/tpa 14,985 18,584

Table 2: Key Assumptions Item Units Years 1 - 10 Life-of-Mine Life of Mine Years 24 Copper Price (base case) US$/t 11,023 Copper Recovery (Milling & flotation) % 89.5% 87.3% Government Royalty (tax-deductible) % 3.0% Export Levy % 1.0%

Description Units PFS Base Case RoM Throughput Mtpa 48 Milling Circuit Type HPGR-Ball Mill Primary Grind Micron 150 48Mtpa CPF Duty CGR CGR Nominal Mass Reject % RoM 25 Flotation Throughput Mtpa 36 Flotation Circuit Type Jameson Cells / Tank Cells Tailings % Solids 60% w/w

3 Table 3: LOM Production Parameters Item Unit Years 1 - 10 Life-of-Mine Ore Tonnes Mined Mt 779 1,119 Waste Tonnes Mined Mt 853 1,093 Strip Ratio x 1.10 0.98 ROM Ore Mining Head Grade % Cu 0.32% 0.27% Flotation Processing Feed Grade % Cu 0.42% 0.35% Ore Mo Grade Mined % Mo 0.005% 0.006% Ore Au Grade Mined g/t Au 0.019 0.021 Contained Cu Metal kt 1,999 2,835 Concentrate grade % Cu 21.8% 21.8% Cu in concentrate kt 1,349 2,607 Annual Cu Production kt 135 109 Annual Mo Production Mlb 2.449 2.269 Annual Au Production koz 17 13 Annual Cu Production (Payable) ktpa 130 105 Annual Mo Production (Payable) Mlbpa 1.224 1.134 Annual Au Production (Payable) kozpa 15 12 Annual CuEq Production (Payable) ktpa 137 111

Capital and Operating Cost Estimates

The capital cost estimate for the project was compiled by DRA, with inputs from Koryx and supporting specialist consultants Knight Piésold and Qubeka.

The estimate for the main crushing, milling and flotation plant for higher grade (“HG”) mineralization was developed by DRA for a plant designed to process 48 Mtpa of ROM, with about 12 Mtpa of >150µm barren coarse particle flotation tailings being rejected ahead of conventional flotation of 36 Mtpa at a target grind of about 80% < 150µm.

Table 4: Capital Cost Estimates Capital Costs Units Years 1 - 10 Life-of-Mine Process Plant incl. Construction Camp and Ops US$m 1,319 Concentrate Load Out US$m 11 Bulk Power Reticulation US$m 61 MSA and Trolley assist US$m 85 Owner’s cost US$m 55 Tailings Storage Facility US$m 21 Surface Water Management US$m 0 Bulk Water Supply - Works US$m 80 Bulk Water Supply - Dam US$m 26 Construction Camp and Services US$m 8 Mine Housing US$m 27 Roads & Site Access US$m 2 Bulk Power Supply US$m 56 Site Infrastructure Indirect costs US$m 24 Subtotal Excluding Contingency US$m 1,774 Project Contingency US$m 133 Capitalised pre-strip US$m 152 Total Project Capital (incl. contingency) US$m 2,059 Sustaining Capital (LOM) 2 US$m 384 639

4 Knight Piésold developed the capital cost estimates for the Tailings Storage Facility (“TSF”), access roads, water and bulk power supply, stormwater management, housing and site accommodation. DRA and Qubeka prepared estimates for infrastructure directly associated respectively with the process plants and contract mining area.

Each consultant submitted estimates of engineering, project and construction management (“EPCM”) services costs associated with their scope of work. This was supplemented by a detailed estimate by Koryx of Owner’s costs during project implementation.

The cost estimate for pre-strip of waste rock before commencing production mining operations was an outcome of Qubeka’s detailed mining schedules.

Significant portions of the TSF construction and other infrastructure costs will only be incurred during the life of the operation, hence these were recorded as sustaining capital in the table below, estimated by DRA and Knight Piésold. The TSF operational cost is included in the sustaining capital cost.

Table 5: Unit Operating Costs Unit Costs per Tonne Mined/Processed Units Years 1 - 10 Life-of-Mine Mining Cost (per tonne mined) US$/t 2.02 2.15 Variable Processing Cost (per t processed) US$/t 5.38 5.38 Fixed Processing Cost (G&A) US$m 24.23 24.23

Unit Costs per tonne Payable Cu Produced Units Years 1 - 10 Life-of-Mine C1 Cash Costs 3, 7 US$/t 3,792 4,834 All-in Sustaining Costs 4, 7 US$/t 4,553 5,554

Unit Costs per lb Payable Cu Produced Units Years 1 - 10 Life-of-Mine C1 Cash Costs 3, 7 US$/lb 1.72 2.19 All-in Sustaining Costs 4,7 US$/lb 2.07 2.52

Notes for Tables 1 to 5: 1. Project Upfront Capital includes US$142m of EPCM costs 2. Sustaining capital covers deferred TSF capital plus 1.25% per year of Process Plant mechanical Equipment, Platework, Piping and ECI supply costs. Closure costs of US$183m are provisioned over the LOM and assumed to be offset by salvage value at closure. 3. C1 = Mining, processing plus on-site G&A and selling costs less by-product credits 4. AISC = C1 costs plus royalties & levies and sustaining capex (excluding closure costs & reclamation value) 5. No owner mining fleet capital is included; fleet costs are carried in the mining unit rate. 6. Estimated LOM gross revenue is attributable 95% to copper, 3% to gold and 2% to molybdenum. 7. Non-IFRS financial measure. See “Non-IFRS Financial Measures”.

5 Table 6: Project Operating Costs (US$/t processed) Concentrator Operating Cost % Fixed US$/t RoM US$m/annum Labour 100% 0.29 13.77 Power - Site Wide Fixed 100% 0.88 42.29 Power - Concentrator Variable 0% 1.80 86.45 Liners & Grinding Media 0% 1.13 54.03 Reagents 0% 0.55 26.51 Water 0% 0.00 0.00 Maintenance 30% 0.54 25.75 Laboratory Analysis 0% 0.04 1.77 Materials Handling 0% 0.16 7.45 Licensing & General 100% 0.004 0.20 Concentrator Operating Cost 5.38 258.22 Concentrator Direct Operating Cost - Fixed 25% 1.33 63.98 Concentrator Direct Operating Cost - Variable 75% 4.05 194.23 Infrastructure & TSF Operating Cost 11.29 Power - Site Wide Infrastructure (Excluding mining) 0% 0.19 9.29 Bulk Water - Maintenance Provision 30% 0.04 2.00 TSF OPEX 100% 0.00 Total Processing Infrastructure & TSF Operating Cost 5.61 269.51 Total Processing Infrastructure & TSF Op. Cost – Fixed 24% 1.35 64.58 Total Processing Infrastructure & TSF Op. Cost – Variable 76% 4.27 204.93

Table 7: LOM C1 Cash Cost and AISC Build-Up Component US$/lb payable Cu Mining 0.86 Processing 1.08 On-site G&A and General Site 0.10 Treatment, Refining, Freight and Marketing 0.43 By-Product Credits (Mo, Au) (0.28) C1 Cash Cost¹, 3 2.19 Royalty and Export Levy 0.21 Sustaining Capital 0.12 AISC2, 3 2.52

Note: 1. C1 = Mining, processing plus on-site G&A and selling costs less by-product credits 2. AISC = C1 costs plus royalties & levies and sustaining capex (excluding closure costs & reclamation value) 3. Non-IFRS financial ratio. See “Non-IFRS Financial Measures”.

Table 8: Annual Cashflow Schedule (next page)

6 PFS CASHFLOW MODEL Units Total/Avg. -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Mining Pre-strip Pre-strip Ore Tonnes Mined Mt 1,119 6.6 22.2 88.7 92.7 85.8 95.5 97.2 105.9 78.8 45.6 42.0 46.3 72.6 87.4 81.0 58.0 12.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Ore Grade Mined 1 % 0.27% 0.10% 0.26% 0.31% 0.31% 0.26% 0.24% 0.25% 0.28% 0.28% 0.29% 0.25% 0.25% 0.27% 0.25% 0.24% 0.27% 0.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Waste Tonnes Mined Mt 1,093 8.2 14.4 35.8 75.2 82.1 72.9 70.7 62.0 89.1 122.8 124.5 117.9 91.7 77.3 31.9 15.8 1.0 Total Tonnes Mined Mt 2,212 15 37 124 168 168 168 168 168 168 168 167 164 164 165 113 74 13 Strip Ratio x 0.98 1.23 0.65 0.40 0.81 0.96 0.76 0.73 0.58 1.13 2.69 2.96 2.54 1.26 0.88 0.39 0.27 0.09 - - - - - - - - - - Processing Yrs 1-10 LOM Processing Plant Feed Mt 1,119 36 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 48 27 Mining Head Grade % 0.27% 0.32% 0.27% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.33% 0.31% 0.28% 0.32% 0.31% 0.28% 0.28% 0.22% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.19% 0.23% 0.25% 0.00% Flotation Plant Feed Grade % 0.35% 0.42% 0.35% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.43% 0.40% 0.36% 0.41% 0.40% 0.37% 0.37% 0.28% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.24% 0.29% 0.30% 0.00% Cu Produced kt 2,607 135 109 107 142 142 142 142 142 142 141 132 117 136 131 121 121 89 76 76 76 76 76 76 76 87 40 Mo produced kt 25 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 0 Au produced koz 310 17 13 7 25 21 17 16 20 20 17 11 13 17 17 15 17 12 9 9 9 9 9 9 9 3 Revenue Copper Price US$/t 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 11,023 Total Sales 2 US$m 29,307 1,169 1,612 1,604 1,590 1,591 1,606 1,608 1,593 1,467 1,305 1,525 1,478 1,363 1,390 1,019 860 860 860 860 860 860 860 938 430 GRN Royalty/Export Levy US$m (1,172) (47) (64) (64) (64) (64) (64) (64) (64) (59) (52) (61) (59) (55) (56) (41) (34) (34) (34) (34) (34) (34) (34) (38) (17) Selling & Marketing Costs US$m (2,379) (26) (59) (73) (97) (145) (145) (145) (145) (135) (120) (139) (134) (124) (124) (92) (78) (78) (78) (78) (78) (78) (78) (88) (41) Operating Costs 3 Mining US$m (4,749) (246) (361) (351) (333) (331) (338) (343) (318) (334) (342) (326) (340) (265) (190) (78) (29) (29) (29) (29) (29) (29) (29) (29) (24) Processing US$m (6,017) (194) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (258) (143) Administration/ Fixed/ G&A US$m (582) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) (24) Total Cash Operating Cost US$m (11,348) (464) (643) (633) (616) (613) (621) (625) (600) (616) (624) (608) (622) (547) (472) (360) (311) (311) (311) (311) (311) (311) (311) (311) (191) Unit Costs Yrs 1-10 LOM Cash Operating Cost (C1) 7 US$/lb 1.72 2.19 1.38 1.41 1.53 1.62 1.74 1.66 1.68 1.79 2.07 2.35 2.01 2.00 2.10 1.98 2.71 3.20 3.20 3.20 3.20 3.20 3.20 3.20 3.06 3.77 4,7 All-in Sustaining Cost (AISC) US$/lb 2.07 2.52 1.85 1.78 1.92 2.00 2.06 1.97 2.00 2.11 2.39 2.65 2.31 2.41 2.43 2.30 3.02 3.54 3.54 3.52 3.46 3.48 3.46 3.46 3.30 4.05 Capital Expenditure Project Capex 5 US$m (2,059) (823) (1,235) Sustain Capex (incl. closure) 6 US$m (639) (68) (54) (60) (58) (38) (36) (38) (41) (38) (30) (34) (61) (36) (33) (27) (27) (28) (25) (14) (18) (15) (14) (14) (14) 183 Capex Intensity (Paybl. CuEq)7 US$/t (14,985) (18,584)

7 Tax Paid US$m (4,286) (272) (274) (277) (276) (279) (232) (180) (256) (226) (225) (264) (187) (153) (153) (154) (158) (157) (158) (158) (182) (62) Cash Flow 7 Net Free Cash before Tax US$m 11,711 (728) (1,177) 392 779 775 756 731 739 735 745 623 484 676 606 603 704 513 415 409 411 421 419 421 422 484 174 181 Net Free Cash after Tax7 US$m 7,425 (728) (1,177) 392 779 775 485 457 461 459 466 391 305 419 380 378 439 325 262 255 257 263 262 263 264 301 112 181 Discount Factor 8% 1.00 0.93 0.86 0.79 0.74 0.68 0.63 0.58 0.54 0.50 0.46 0.43 0.40 0.37 0.34 0.32 0.29 0.27 0.25 0.23 0.21 0.20 0.18 0.17 0.16 0.15 0.14 Disc. Cashflow8% before Tax US$m 4,205 (728) (1,090) 336 618 570 515 461 431 397 373 288 208 268 223 205 222 150 112 102 95 90 83 77 72 76 25 25 Disc Cash Flow8% after Tax US$m 2,538 (728) (1,090) 336 618 570 330 288 269 248 233 181 131 167 140 129 138 95 71 64 60 56 52 48 45 48 16 25 Payback Period (post-tax) 3.9 IRR (post-tax) 24.9% Notes: 1. Mining dilution and ore loss has been applied to the scheduled ore tonnes by the mining consultant 2. Gross revenue including by-product sales from Mo + Au and 96.5% payability for Cu in concentrate 3. Mining cash flow, comprised of (i) cash costs attributable to mined ore processed in this period (reflected in C1 costs and AISC), and (ii) cash reflected in inventory 4. AISC comprises C1 costs + sustaining capex + royalties + export levies but excludes ongoing capital for growth projects 5. Project Capex includes US$133m of contingency and US$152m of capitalised pre-strip costs. 6. Sustaining capital includes deferred capital for the TSF , plus 0.50% of other project capital costs + estimated closure costs - estimated salvage value 7. Non-IFRS financial measure. See “Non-IFRS Financial Measures” Key Economic Assumptions

The cash flow model is unlevered and on a 100% project basis, with flat prices and costs. It includes no streaming or offtake prepayment.

Table 9: Key Economic Assumptions Assumption Value Copper Price US$5.00/lb (US$11,023/t), flat for LOM Molybdenum Price US$22.00/lb Gold Price US$3,500/oz Silver No silver revenue (not payable) Payability Cu 96.5%; Mo 50%; Au 90% Treatment and Refining Charges Year 1: –US$75/mt (dry) and –US$0.075/lb; Year 2: –US$50/mt and –US$0.05/lb; Year 3: –US$25/mt and –US$0.025/lb; Year 4: nil; Year 5 onwards: US$50/mt and US$0.05/lb Trader's Margin 1% of revenue Concentrate Freight (road, port, US$140/t concentrate (Years 1 – 2), US$125/t concentrate sea and last mile) thereafter Government Royalty 3% of gross revenue (tax-deductible) Export Levy 1% of gross revenue Corporate Income Tax 37.5%; LOM effective rate of 32% of pre-tax profit Capital Allowances Capex redeemed against taxable income over 3 years; US$100m opening assessed loss. Sustaining Capex is immediately deductible and not depreciated Exchange Rate N$/ZAR18.00:US$1.00 Discount Rate 8% Construction Period 2 years (40% / 60% capex split), including pre-strip Processing 48Mtpa ROM, with 25% of mass rejected as coarse gangue ahead of flotation (DRA recovery model, October 2026) Oxide Stockpile (final two years) 60% copper recovery to concentrate

Geology and Mineralization

Haib is a Paleoproterozoic approximately 1,880 Ma, porphyry copper-molybdenum-gold deposit hosted by volcanic rocks of the Orange River Group and granites and granodiorites of the Vioolsdrif Intrusive Suite, within the Richtersveld Subprovince of the Namaqua-Natal Province. Mineralization occurs in all host units, mainly in igneous-hydrothermal breccias, with narrow higher-grade zones in quartz-rich veins and shear zones and extends over approximately 2km of strike. Widespread potassic alteration and deeper sodic-calcic alteration indicate a deeply emplaced, multi-stage porphyry Cu-Mo system.

Chalcopyrite and pyrite are the principal sulphides, with minor molybdenite and occasional bornite, digenite, chalcocite and covellite. The best mineralization occurs as chalcopyrite aggregates and clots in igneous and hydrothermal breccias, while molybdenum occurs mainly in quartz-molybdenite veins. There is no well- developed supergene zone; near-surface oxide copper rarely extends below 30m.

Mineral Resource Estimate

MSA Group (Pty) Ltd (“MSA”) has updated the previous Mineral Resource estimate for the Project, which had an effective date of 16 March 2026. Exploration continued through 2026 and new drilling has infilled the

8 Mineral Resource and improved the geological understanding. The updated Mineral Resource Statement, effective 28 October 2026, is based on an updated model and a revised optimised pit shell.

The estimate uses diamond drillhole data from 1963 to 2026 and one 126 m channel-sampled adit. After extensive validation, data from Rio Tinto Zinc (120 drillholes, 1972–1975), Great Fitzroy Mines (12 drillholes, 1995–1999) and Teck (32 drillholes, 2010) were accepted. Twenty-nine drillholes from the King Resources and Falconbridge campaigns (1963–1969) were excluded from grade estimation because MSA could not validate them.

The database includes Koryx holes drilled from 2021 to September 2026: 231 NQ diamond drillholes (“DD”) for 77,796 m and 19 reverse circulation (“RC”) drillholes for 7,942 m. Exploration data available on 07 October 2026 were used to update the model.

Pre-Teck and pre-Koryx holes were mostly vertical on a grid of about 150 m. Teck and Koryx drilled angled holes, sometimes from the same location, to better intersect the dipping mineralization. Spacing averages about 75 m in the higher-confidence (Indicated) area, but the grid is irregular owing to targeted infill drilling and challenging topography (Figure 1).

Figure 1: Plan view illustrating distribution of drilling by historical operators

A three-dimensional geological model of the copper mineralization was built from all drillhole sample data. Leapfrog Geo was used to create nested grade shells at copper thresholds of >0.25%, 0.20-0.25%, 0.15-0.20%, 0.10-0.15% and <0.10%, covering all mineralization currently defined.

The model incorporates interpreted structural trends and geological domains. Copper grade was estimated from the accepted historical and Koryx data by ordinary kriging of five metre composites in Leapfrog Edge. An 9 average in-situ dry bulk density of 2.78 t/m3 was assigned to all blocks. Classification considered data confidence, drillhole spacing and continuity.

Haib Mineral Resource Statement

The Mineral Resource was estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Best Practice Guidelines and is reported in accordance with the 2014 CIM Definition Standards, which have been incorporated by reference into National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

The Mineral Resource was reported from within an optimised pit shell. The Project envisages an open-pit mining operation with flotation of sulphide mineralization, including initial coarse particle flotation. Oxide material will be stockpiled and processed at end of life-of-mine by milling and flotation.

The optimised pit shell was informed by mineralization within the modelled 0.20% Cu grade shell. Lower-grade material inside the pit shell but outside that grade shell must be removed to extract the higher-grade Mineral Resource. Blocks within the pit shell grading above 0.15% Cu meet marginal cut-off criteria and, with the pit shell, demonstrate reasonable prospects for eventual economic extraction (“RPEEE”). The assessment to satisfy the criteria of RPEEE is a high-level estimate and is not an attempt to estimate Mineral Reserves.

A summary of the Mineral Resource estimate is presented in Table 10 below.

Table 10: Mineral Resource Estimate for Haib as of 28 October 2026 at a 0.15% Cu cut-off Cu Mo Au CuEq Cu Mo Cu Mo Au Tonnes Category Type Grade Grade Grade Grade Content Content Content Content Content (Mt) (%) (ppm) (g/t) (%) (Mlb) (Mlb) (kt) (kt) (koz) Total High Grade 577 0.36 72 0.02 0.39 4,563 92 2,070 42 427 (>0.25% Cu) Indicated Total Low Grade 793 0.19 49 0.02 0.21 3,312 86 1,502 39 465 (0.15-0.25% Cu) Total 1,371 0.26 59 0.02 0.28 7,875 178 3,572 81 892 Total High Grade 107 0.34 48 0.02 0.36 811 11 368 5 63 (>0.25% Cu) Inferred Total Low Grade 222 0.19 37 0.02 0.20 912 18 414 8 115 (0.15-0.25% Cu) Total 329 0.24 41 0.02 0.26 1,723 30 781 13 178

Notes: 1. All tabulated data have been rounded and as a result minor computational errors may occur. 2. Mineral Resources, which are not Mineral Reserves, have no demonstrated economic viability as may be obtained once a pre-feasibility or feasibility studies have been completed and all modifying factors have been taken into account. There is no guarantee that all or any part of the Mineral Resource will be converted into a Mineral Reserve. The estimate of Mineral Resources may be materially affected by geology, environment, permitting, legal title, taxation, socio-political, marketing, or other relevant issues. 3. Mt = Million tonnes, kt = thousand tonnes, Mlb = Million pounds. 4. The Mineral Resource Statement for Haib as of 28 October 2026 is reported within a conceptual pit shell using the following assumed parameters: Copper Price 10,469 USD/t. Molybdenum price 48,488 USD/t. Gold Price 4,000 USD/oz. Royalty and Export Levy: 4%, Copper payability: 96.0%, Molybdenum payability 76.4%, Gold payability 81.0%. Overall slope angle: 48° for Fresh, 45° for Oxide and Transitional. Flotation recovery: 88.2% Cu, 40.6% Mo, 54.0% Au. Average Mining Cost 2.27 USD/tonne Processing Cost 6.77 USD/tonne material processed by flotation, SG&A Overheads 0.38 USD/tonne material to primary crusher. 5. The copper equivalent calculation uses the following formula for price contribution of each metal in one tonne relative to copper. (Cu grade * Cu Price * Cu Recovery * Cu payability + Au grade * Au Price * Au Recovery * Au payability + Mo grade * Mo Price * Mo Recovery * Mo payability) / (Cu grade * Cu Price * Cu Recovery * Cu payability) * Cu grade, Cu Price = USD 10,469/t, Mo Price = USD 48,488/t, Au Price = USD 4000/oz, 10 Cu Recovery = 88.2% Mo Recovery = 40.6% Au Recovery = 54%, Cu Payability = 96.0%, Mo Payability = 76.4% Au Payability = 81%, Recoveries are assumed from preliminary metallurgical test work for bulk concentrate production with initial coarse particle flotation. Oxide material is planned to be stockpiled and processed at the end of life-of-mine through milling and flotation at an assumed 55% recovery.

Figure 2: Haib resource pit shell and block model – plan view

Figure 3: Haib resource pit shell and block model –oblique view to the north

11 Figure 4: Haib resource block model section, drillholes and pit shell NW Zone, view to the northwest

Pit Optimization and Mine Design

The PFS mining component is based on MSA’s updated Mineral Resource estimate, effective 28 October 2026. The PFS supports disclosure under NI 43-101, using the CIM Definition Standards, under the responsibility of appropriately experienced qualified persons (as defined in NI 43-101).

The PFS evaluates development options for the Project’s technical and economic viability and establishes the preferred open pit configuration and processing route. It includes financial analysis and an assessment of the modifying factors needed for the qualified persons to determine whether Mineral Resources can be converted to Mineral Reserves at the reporting date. A PFS carries a lower level of confidence than a Feasibility Study and is the minimum study level required to declare Mineral Reserves.

The operation comprises drilling, blasting, loading and hauling, with bulk mining supplemented by selective excavation of mineralised material to manage ore loss and dilution. An experienced contractor will undertake the full mining scope, with only mine technical services performed by the owner’s team. The contractor will be responsible for drilling, blasting, loading and hauling of ore and waste, stockpile rehandling, haul road and waste dump maintenance, and associated support, and will supply the equipment, materials, facilities, supervision and labour required.

Drilling and blasting will be on 15 m benches, with waste excavated over the full bench height and mineralised material mined selectively in two 7.5 m flitches to limit ore loss and dilution. Electric rope shovels with 56 m³ buckets will handle both bulk waste and selective ore, loading 360 t diesel-electric rigid haul trucks with trolley assist on designated routes. Support equipment will include production drills, graders, dozers, front-end loaders, rock breakers and utility excavators, with ore hauled to the primary crusher or run-of-mine (“ROM”) and low-grade stockpiles, and waste to waste rock dumps.

12 Pit designs use staged pushbacks to prioritise higher-grade plant feed early and defer waste stripping where practicable, subject to access, slope stability and production requirements. The production schedule integrates pit development, fleet capacity, stockpiles and plant feed over the life of the operation.

Sulphide material meeting the elevated processing cut-off grade of 0.15% Cu will be treated to produce copper concentrate, with molybdenum and gold recovered as byproducts. Transitional and oxide material meeting the 0.15% Cu cut-off grade will be stockpiled during mining and processed through the milling and flotation plant during the final years of the processing schedule. This material is expected to produce copper concentrate, with no molybdenum or gold recovery assumed.

Figure 5: Ultimate pit design and layout

Figure 6: Final & interim pushback designs

Whittle pit optimisation was undertaken using a base copper price of US$ 4.75/lb, equivalent to approximately US$ 10,469/t, and a discount rate of 8%. The optimisation incorporated a 3% gross royalty and a 1% export levy payable to the Namibian Government.

The optimised pit shell was informed by mineralization contained within the modelled 0.20% Cu grade shell. Lower-grade material exists outside the 0.20% Cu grade shell within the pit design that must be removed to extract the higher-grade Mineral Resource. Blocks that occur within the pit design with estimated grade above 0.15% Cu satisfy marginal cut-off grade criteria for Mineral Reserve reporting. 13 A series of nested economic pit shells was generated during the optimisation process using the applicable technical and economic assumptions. The selected optimisation shells were subsequently used as the basis for the development of practical ultimate pit designs.

The pit design converted the selected optimised pit shell into a practical open-pit design incorporating haul ramps, benches and berms, in compliance with geotechnical and mine design criteria. Practical adjustments for minimum mining widths, ramp access, bench configurations and geotechnical constraints mean the final design may deviate locally from the optimised shell.

Ramp layouts and pit exits were selected considering their effect on waste stripping, haul distances, productivity and operating costs, and the planned material flow to the primary crusher, run-of-mine facilities and waste rock storage. The resulting pit and pushback designs, shown in Figure 5 and Figure 6, set the practical mining limits used for production scheduling, equipment requirements and the Mineral Reserve estimate.

LOM Production Schedule

The Haib Copper Project LOM production schedule, as depicted in Figure 7, comprises of a pre-stripping period followed by approximately 24 years of processing. Mining progresses through five staged pushbacks, with about 51.5 Mt removed during pre-stripping.

Total Material Mined Total Material Mined 180.00 3.50 180.00 Strip Ratio Tonnes (Mt)

Tonnes (Mt)

160.00 160.00 3.00 140.00 140.00 2.50 120.00 120.00

100.00 2.00 100.00

80.00 1.50 80.00

60.00 60.00 1.00 40.00 40.00 0.50 20.00 20.00

0.00 0.00 0.00 Pre-strip Year 1 Pre-strip Year 2 Pre-strip Year 3 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25 Pre-strip Year 1 Pre-strip Year 2 Pre-strip Year 3 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25

Waste Milling Flotation Ore (> 0.150 %TCu) Oxide & Transitional Material Milling Flotation Ore ( 0.150 - 0.220 %TCu) Sulphide Material PB1 PB2 PB3 PB4 PB5 Milling Flotation Ore ( > 0.220 %TCu) Sulphide Material Strip Ratio

Milling Flotation Plant Feed Schedule Total Copper Tonnes Produced 60.00 0.004 160000 Cu & CuEq Grade (%Cu & %CuEq)

Tonnes Millions

0.0035 140000 50.00 0.003 120000 Tonnes (Mt)

40.00 0.0025 100000

30.00 0.002 80000 0.0015 20.00 60000 0.001 40000 10.00 0.0005 20000 0.00 0 Pre-strip Year 1 Pre-strip Year 2 Pre-strip Year 3 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10 Year 11 Year 12 Year 13 Year 14 Year 15 Year 16 Year 17 Year 18 Year 19 Year 20 Year 21 Year 22 Year 23 Year 24 Year 25

0 Pre-strip…

Pre-strip…

Year 2

Year 4

Year 6

Year 8

Year 10

Year 12

Year 14

Year 16

Year 18

Year 20

Year 22

Year 24

Year 26

Year 28

Year 30

Year 32

MF S/P Sulphide #1 MF S/P Sulphide #2 MF S/P Sulphide #3 MF S/P Sulphide #4 MF S/P Sulphide #5 MF S/P Oxide #6 Produced Metal - Cu - Sulphide Produced Metal - Cu - Oxide & Transitional Feed Grade - Cu Feed Grade - CuEq Feed Cut-off Grade - Cu

Figure 7: Key mining production schedule graphs

Total scheduled material movement is about 2,212 Mt (1,119 Mt of ore and 1,093 Mt of waste), at an overall strip ratio of 0.98:1. 14 Annual movement peaks at about 168 Mt before declining as the final pushbacks complete, with open pit mining ending in operating Year 15.

The concentrator is scheduled to process about 48 Mtpa after ramp-up. A variable cut-off grade strategy prioritises higher-grade sulphide material early, maintaining copper feed grades of about 0.33% initially. Lower-grade sulphide material is stockpiled and reclaimed to sustain plant throughput after open pit mining ends, with feed grades declining to about 0.19%. About 60.9 Mt of stockpiled transitional and oxide material is processed in the final two years.

Total scheduled copper production is approximately 2.61 Mt from sulphide and oxide/transitional material. Annual copper production reaches approximately 142 kt early and declines to about 76 ktpa during later sulphide stockpile treatment. Scheduled byproducts total about 24.7 kt of molybdenum and 310 koz of gold; no molybdenum or gold recovery is assumed for transitional and oxide feed.

The LOM production schedule uses a variable cut-off grade strategy based on Ken Lane’s economic principles. Rather than a single fixed cut-off, the scheduling cut-off grade varies through time to maximise project value. Material above the elevated scheduling cut-off is processed immediately, while lower-grade material above the marginal economic cut-off may be:

• Stockpiled for processing at a later stage; • Deferred to a subsequent scheduling period; or • Processed only when higher-grade material is unavailable.

Mineral Reserves

The Mineral Reserve estimate for the Haib Copper Project is reported in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) definitions and guidelines. It incorporates the PFS-level modifying factors: mining, metallurgical, economic, infrastructure, legal, environmental, social and governmental.

The estimate is based on open-pit optimisation, practical mine designs and a LOM production schedule. Only Indicated Mineral Resources were eligible for conversion to Mineral Reserves after applying modifying factors. Inferred Mineral Resources were given no economic value in pit optimisation, excluded from the estimate and treated as waste in the LOM schedule.

Nested economic pit shells were generated using the PFS technical and economic assumptions. Selected shells guided ultimate pit designs incorporating geotechnical criteria, haul roads, ramps, berms, minimum mining widths and other operational requirements. The Mineral Reserve comprises material within these designs that meets the economic and processing criteria. The LOM schedule and financial evaluation demonstrate the economic viability of extracting and processing this material under the PFS assumptions.

As of 6 November 2026, the Haib Copper Project has Probable Mineral Reserves of approximately 1,119 Mt at 0.27% Cu, 58 ppm Mo and 0.02 g/t Au (0.29% CuEq), containing approximately 2,995 kt of copper, 65 kt of molybdenum and 689 koz of gold. These comprise approximately 1,058 Mt of sulphide ore and 61 Mt of oxide and transitional ore, to which no molybdenum or gold contribution is attributed.

The estimate was prepared under the supervision of a qualified person experienced in open-pit mine planning, Mineral Reserve estimation and the Haib Copper Project. The Mineral Reserves, effective 6 November 2026, are summarised in Table 11.