DEEP-SOUTH INTERSECTS 50 METRES OF 0.63% CuEq, INCLUDING 16

METRES OF 0.80% CuEq AND 4 METRES OF 2.57% CuEq FROM THE 2021

DRILLING PROGRAM UNDISCLOSED RESULTS

Significant copper and molybdenum intersections include:

• HM11 : 0.62% CuEq over 10 metres, including 4 metres @ 0.97% CuEq

• HM11 : 0.46% CuEq over 26.36 metres including 4m @ 0.76% CuEq

• HM12: 0.76% CuEq over 20 metres including 4m @ 2.57% CuEq

• HM14 : 0.35% CuEq over 30 metres from surface and 0.48% CuEq over 26

metres

• HM22 : 0.63% CuEq over 50 metres including 0.80% CuEq over 16.00 metres

• HM26 : 0.37% CuEq over 16 metres from 26 metres below surface

Vancouver, B.C., Canada – August 3, 202 3 – Deep-South Resources Inc. (" Deep-

South" or “ the Company") (TSX-V: DSM) announces the fourth batch of assay results

from its drilling program interrupted in June 2021 at its Haib Copper project in southern

Namibia. The program was interrupted when the Ministry of Mines and Energy of Namibia

had denied the renewal of the Haib Copper licence EPL 3140. Results from 13 drill holes

have been received in full after the renewal denial of the licence , with partial results

received for 1 drill hole . The first 6 drill holes were previously reported. Following the

completion of QA/QC the results for the remaining 7 holes are disclosed here.

Pierre Léveillé, President & CEO of Deep -South stated that: ""We are extremely

enthusiastic by the results from the drill program. Previous drilling programmes

point to the presence of higher copper grade zones, probably associated with near

vertical structures (shears and faults) within the broader mineralised areas of the

project. The use of vertical drilling in the past potentially missed those structures resulting

in an underestimation of the overall grade. Our drilling program is focussing to redress this

through the use of inclined holes to identify and delineate thes e structures and test the

association with higher Cu grade zones. These results seem to support this updated

interpretation, showing substantial intersections at Cu grades considered high for

Haib. Additionally the presence of molydenum has been confirmed with high Mo

grades obtained in association with structures and alterations”.

The 7 holes for which assay results are reported here cover some 1,360.92 metres and

cover all 4 of the target areas. All holes were positioned to better delineate the previously

identified higher grade portions of the Haib Copper Project and to test the extension of

grade between these targets . Assay results of significant intersections are tabulated

below:

Significant Intersections

Hole# Zone From To Width CuEq Cu Mo

(m) (m) (m)1 (%)2 (%) (%)

HM05 Main 30.00 32.00 2.00 0.47 0.33 0.041

Main 96.00 102.00 6.00 0.58 0.16 0.126

HM11

Main 118.00 122.00 4.00 0.47 0.47 0.001

Main 166.00 176.00 10.00 0.62 0.62 0.001

Including 168.00 172.00 4.00 0.97 0.97 0.001

Main 186.00 212.36 26.36 0.46 0.45 0.003

Including 190.00 194.00 4.00 0.76 0.75 0.004

Including 208.00 212.36 4.36 0.61 0.60 0.001

HM12 Main 76.00 96.00 20.00 0.76 0.74 0.005

Including 92.00 96.00 4.00 2.57 2.35 0.005

HM13 Main 4.00 8.00 4.00 0.53 0.53 0.001

HM14

Main 4.00 34.00 30.00 0.35 0.27 0.024

Main 78.00 104.00 26.00 0.48 0.45 0.008

Main 148.00 156.00 8.00 0.48 0.45 0.010

HM22

Main 96.00 110.00 14.00 0.66 0.61 0.015

Including 102.00 110.00 8.00 0.83 0.77 0.018

Main 190.00 196.00 6.00 0.60 0.51 0.026

Main 232.00 250.00 18.00 0.45 0.43 0.006

Main 272.00 322.00 50.00 0.63 0.57 0.020

Including 272.00 280.00 8.00 0.73 0.68 0.017

Including 286.00 302.00 16.00 0.80 0.72 0.024

Main 346.00 370.00 24.00 0.69 0.68 0.003

HM26

Main 26.00 42.00 16.00 0.37 0.35 0.006

Main 68.00 76.00 8.00 0.48 0.47 0.001

Main 84.00 96.00 12.00 0.45 0.45 0.002

1. HM12 – assay results have been received for only the first 96m of the 341.15m drilled.

2. Width refers to intersection width; true widths have not been determined.

3. CuEq (copper equivalent) has been used to express the combined value of copper and molybdenum and is

provided for illustrative purposes only. No allowances have been made of recovery losses that may occur should

mining eventually result. Calculations use metal prices of US$3.00/lb copper, US$10/lb molybdenum using the

formula: CuEq% = Cu% + (Mo% [$10/$3])

Borehole Locations (Figure 1)

HM05 was drilled northeastwards in the Pit 2 target area to determine the

southwestern limit of the 0.3% Cu contour.

HM11 was drilled towards the southwest in the Pit 3 target area to determine the

northern limit of the high-grade (>0.4% Cu) mineralization previously identified here.

HM12 was drilled northwards in Pit 3 to better delineate the southern limit of the high

grade mineralisation identified here by reducing the drillhole spacing.

HM13 was positioned in Pit 3 and drilled approximately northwards. The

mineralization in Pit 3 is believed to terminate against an east -west trending, near

vertical shear zone in the north and HM13 was planned to test this.

HM14 was placed between the Pit 4 and Pit 2 areas. Cu Mineralisation in Pit 4 is

believed to be associated with east -west oriented, near vertical structures and this

borehole was positioned to test this model and the potential extension of higher grades

between the two target areas.

HM22 was drilled vertically in Pit 1 to delineate the southern limit of the higher -grade

mineralization here. Additionally, the hole was drilled to over 400m from surface to

test the depth to which this mineralisation extends.

HM26 was drilled in the northwest of the Pit 4 target area to test the presence of near-

surface mineralisation as well as the northern limit of this mineralisation.

Figure 1: Planview showing the positions of the boreholes being reported here.

Discussion of Pertinent Results

HM05

The results of this hole showed Cu grades to be low grade (typically <0.25%) in this

part of the Pit 2 area . However, Mo grades are high , especially within the top 100m

from surface e.g., 18m @ 0.041% Mo, 16m @ 0.042% Mo and 6 m @ 0.126% Mo.

Low Cu grades associated with high Mo grades have been observed in boreholes to

the west and east of HM05 and are probably associated with an approximately east -

west trending unidentified structure.

HM11

Results from this hole showed good correlation with the existing model resulting in no

changes to the 0.3% and 0.4% Cu contours. Unfortunately, the hole had to be stopped

when operations were forced to cease while still within high grade mineralisation (last

sample 0.75% Cu).

HM12

Only the first 96m of this hole had been submitted for assaying before operations

ceased. Results show a significant southwards lateral (~50m) shift of the high-grade

mineralisation here, with the last two samples returning the highest (2.55%) and third

highest (2.15%) Cu grades seen at Haib.

HM13

Despite the first 8m of this hole returning a composite grade of >0.3% Cu, the Cu

grades drop to 0.2% for the next 40m before dropping further to <0.1% for the

remainder of the hole. The <0.1% Cu portion correlates with a wide zone of highly

sheared veining logged in the core and is probably the large east-west vertical shear

zone previously identified to the north of Pit 3. Mo grades are low over the first 40m

but within the shear zone, they are typically below detection limits.

HM14

Results for this hole showed the presence of an approximately 45m wide, near vertical,

>0.3% Cu zone which had been missed by the vertical historical drilling. This zone

correlates well with borehole HM27 drilled some 200m to the west of HM14, where 2

near-vertical, east-west oriented zones were identified. Overall, results show the Pit 4

mineralisation probably extends eastwards to Pit 2.

HM22

For the first 80m from surface , Cu grades in this hole are low averaging about 0.1%

while Mo remains at the detection limit. From 80m to 230m Cu grades are closer to

the 0.3% level with some intersections exceeding 0.5%. From 272m Cu grades

increase significantly averaging 0.63% CuEq (0.57% Cu) over 50m along with

elevated Mo grades. Another 24m zone is intersected from 346m averaging 0.69%

CuEq (0.68% Cu) but with Mo at the detection limits. As no mineralisation had been

identified here by previous drilling, the results of HM22 repr esent a significant

improvement in tonnage and grade in the southern portion of Pit 1.

HM26

Results for this hole point to a relatively wide (~ 100m) zone of east-west oriented, near

vertical structures with Cu grades >0.35%. The results correlate well with those of

boreholes HM14 and HM27 (previously reported) supporting the idea that mineralisation

within the Pit 4 area is contained within multiple east-west trending, near vertical structures

extending to the Pit 2 area.

Drilling Program Update

Twenty-two holes were completed in 2021 and by the time the licence renewal was

declined in June 2021, samples for 19 holes had been submitted to the laboratory. Results

for eight holes were disclosed in May and June 2021, 6 holes were recently disclosed

while the remaining 6 holes are disclosed here. The program was planned for 10,000

metres, of which 4,800 meters was completed in 2021. The remaining 5,200 metres will

be completed as part of the development program to be resume as soon as possible. At

1.8 billion years (Archean), the Haib Copper Deposit is one of the oldest deposits in the

world. Over time, it has seen several transformations including shearing and faulting

events that have further concentrated Cu and Mo.

The specific focus of this drilling campaign is to further delineate and grow the higher-

grade area(s) of the Haib deposit uncovered by Deep-South in 2019 and 2020

with the ultimate goal of establishing a measured resource over that higher-grade section

of the deposit.

Quality Control

All drill cores were logged, photographed, and cut in half with a diamond saw. Half of the

cores were bagged and sent to ALS Laboratories Ltd. in Johannesburg, South Africa for

analysis (SANAS Accredited Testing Laboratory, No. T0387), while the other half was

quartered with one quarter archived and stored on site for verification and reference

purposes while the other quarter will be used for metallurgical test work. 33 elements are

analyzed by Induced Coupled Plasma (ICP) utilizing a 4 -acid digestion and g old is

assayed using a 30g fire assay method . Duplicate samples, blanks, and certified

standards are included with every batch a nd are actively used to ensure proper quality

assurance and quality control.

About the Haib Copper Project

The Haib Copper Deposit is a large copper/molybdenum deposit situated 40 kilometers

from the southern boundary of Namibia. The license covers 370 square kilometers (37,000

hectares). Over the years the project has seen 70,000 meters of drilling, several

metallurgical test work programmes, geophysical surveys, geological mapping, mine

modeling and even a feasibility study in 1996. Deep-South holds all the historical data.

Please note that: Mineral Resources that are not mineral reserves do not have demonstrated

economic viability. Mineral resource estimates do not account for mineability, selectivity, mining

loss and dilution. These mineral resource estimates are based on Indicated Mineral Resources that

are considered too speculative geologically to have the economic considerations applied to them

that would enable them to be categorized as mineral reserves . However, there is no certainty that

these indicated mineral resources will be converted to measured categories through further drilling,

or into mineral reserves, once economic considerations are applied. There is no certainty that the

preliminary economic assessment will be realized.

Qualified Person

Mr. Dean Richards Pr.Sci.Nat. , MGSSA – BSc. (Hons.) Geology, is the Qualified Person

for the Haib P roject as defined by National Instrument 43 -101 and has approved the

technical disclosure contained in this news release.

About Deep-South Resources Inc.

Deep-South Resources is a mineral exploration and development company. Deep-South’s

growth strategy is to focus on the exploration and development of quality assets in

significant mineralized trends and in proximity to infrastructure in stable countries. The

Company holds the Haib Copper Project in Namibia and holds an interest in three

exploration licences in the Copperbelt in Zambia. In using and assessing environmentally

friendly technologies in the development of its copper projects, Deep-South embraces the

green revolution.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

This press release cont ains certain "forward -looking statements," as identified in Deep - South’s periodic

filings with Canadian Securities Regulators that involve a number of risks and uncertainties.

There can be no assurance that such statementsl prove to be accurate and actua l results and future

events could differ materially from those anticipated in such statements.

This News Release contains forward -looking statements, which relate to future events. In some cases, you

can identify forward-looking statements by terminology such as "will", "may", "should", "expects", "plans", or

"anticipates" or the negative of these terms or other comparable terminology. All statements included herein,

other than statements of historical fact, are forward looking statements, including but no t limited to the

Company’s plans regarding the Haib Copper project. These statements are only predictions and involve known

and unknown risks, uncertainties and other factors that may cause the Company’s actual results, level of

activity, performance or ac hievements to be materially different from any future results, levels of activity,

performance, or achievements expressed or implied by these forward-looking-statements. Such uncertainties

and risks may include, among others, actual results of the Company' s exploration activities being different

than those expected by management, delays in obtaining or failure to obtain required government or other

regulatory approvals or financing, inability to procure equipment and supplies in sufficient quantities and on a

timely basis, equipment breakdown and bad weather. While these forward -looking statements, and any

assumptions upon which they are based, are made in good faith and reflect the Company's current judgment

regarding the direction of its business, actual results will almost always vary, sometimes materially, from any

estimates, predictions, projections, assumptions or other future performance suggestions herein. Except as

required by applicable law, the Company does not intend to update any forward-looking statements to conform

these statements to actual results.

More information is available by contacting Pierre Léveillé, President & CEO at

+1-819-340-0140 or at: [email protected] or

Paradox Public Relations at +1-514-341-0408.