K92 Provides Operational Update
Suite 488 – 1090 West Georgia Street
Vancouver, British Columbia
Canada V6E 3V7
Telephone: (604) 687-7130
Facsimile: (604) 608-9110
NEWS RELEASE
March 1, 2017 Vancouver, British Columbia
K92 Provides Operational Update
ore tonnes mined in January 50% above bud get, with contained Au ozs 20% above
budget
As at February 24 th, 2017, almost 8,000 tonnes of ore mined for the month, and on
target to achieve over 10,000 tonnes for the month, against a budget of 6,700 tonnes
As at 24 th February, 2017, almost 5,000 tonnes pro cessed and on target to achieve
7,000 tonnes for the month, against a budget for the month of 6,700 tonnes
Over 200 tonnes of concentrate produced to da te, with the first containers currently
being filled for shipment to the port of La e. First shipment of concentrates from the
port of Lae to smelter scheduled for early to mid-March
K92 Mining Inc. (“K92” or the “Company”) is pleased to report mining production has shown a
steady ramp up over the last 3 months with ore tonnes mined being over 50% above budget in
January, 2017, while contained gold ounces we re almost 20% above budget. The Company
mined over 8,000 ore tonnes by February 24 th, 2017, and the Company is on target to achieve
10,000 tonnes by month end, which is 40% above February budget. The increased ore production
is in part due to significant lower grade ore bein g identified outside of the planned ore envelope,
which was identified by our ongoing grade contro l program, highlighting the importance and
success of this program. All current February production has come from ore development
headings and the Company currently anticipate s the first stope mining to commence on schedule
by the end of March.
The commissioning of the drum scrubber at th e process plant has now been completed and
production is ramping up to meet the mine prod uction, with tonnes proce ssed in February 2017,
projected to be 5% above the February 2017 budget of mined 6,700 ore tonnes. The product from
the drum scrubber has met the required specifi cations and has allowed the crushing plant to
operate satisfactorily, with all of the fines portion, accounting for approximately 30% of the feed,
bypassing the crusher and reporting directly to the milling classification circuit.
The process plant has produced in excess of 200 tonnes of concentrate, with current grades
averaging approximately 150 g/t Au. This material is currently being loaded into containers for
transport to the port of Lae, with the first shipme nt scheduled to depart the port of Lae early to
mid-March, 2017.
As at February 24, 2017, there were approximately 12,000 tonnes of ore stockpiled on surface at
an average grade of just over 5 g/t, which in cluded some lower grade development ore mined
from outside the budgeted ore envelope. The Compa ny anticipates that this stockpile will allow
the plant to achieve over 80% of the design throughput in March, 2017. Based on performance to
date, the Company anticipates that both mi ne production and process plant throughput will
exceed budget in the March quarter.
The above production has been achieved despite unusually high rainfall during January and early
February, with January recording 700 mm of rain on site against a long-term average of 240 mm.
This rainfall has also caused some disruption to the power supply from PNG Power which has
had some adverse effect on operations, primarily the process plant.
The Company does have standby power installed fo r the mine, camp and offices and is in the
process of upgrading the installed standby power to also provide sufficient power to run the
entire processing plant. The dies el generators for this upgrade are currently on site and their
installation is due to be completed shortly.
Ian Stalker, K92 Chief Executive Officer and Director, states, “It is encouraging to report to all
stake-holders the current operational status of the Kainantu Mine. Progress has been made in all
aspects of our business, in excess of our own internal budget numbers. Our first concentrate is
being loaded into containers ready for onward shipping to the Smelter facility, and the grade
being recorded at +150 gpt Au., is coming from treatment of our lower grade development ore
This is hugely encouraging for the operation forecast when we start processing our mined stope
ore later in March.
The performance of the underground mine has been excellent, with ore production being ahead
of schedule. This is all the more remarkable against the background of re-starting an old mine in
weather conditions that are the wettest recorded for many years. I think this is testament to the
skills and dedication of the entire team that is K92, and I wish to record my thanks to them.”
On behalf of the company,
Ian Stalker
Chief Executive Officer and Director
CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION: This
news release includes certain “forward-looking statements” under applicable Canadian securities
legislation. Forward-looking statements are necessarily based upon a number of estimates and
assumptions that, while considered reasonable, are subject to known and unknown risks,
uncertainties, and other factors which may cause the actual results and future events to differ
materially from those expressed or implied by such forward-looking statements. All statements
that address future plans, activities, events or developments that the Company believes, expects
or anticipates will or may occur are forward-looking information, including statements regarding
potential ongoing production which may or may not occur and the generation of further
production assessment work at deposits, which may or may not occur. The Preliminary
Economic Assessment (“PEA”) issued by K92 is preliminary in nature and includes inferred
mineral resources that are considered too speculative geologically to have the economic
considerations applied to them that would enable them to be categorized as mineral reserves, and
there is no certainty that the PEA will be realized. Forward-looking statements and information
contained herein are based on certain factors and assumptions regarding, among other things, the
market price of the Company’s securities, metal prices, taxation, the estimation, timing and
amount of future exploration and development, capital and operating costs, the availability of
financing, the receipt of regulatory approvals, environmental risks, title disputes, failure of plant,
equipment or processes to operate as anticipated, accidents, labour disputes, claims and
limitations on insurance coverage and other risks of the mining industry, changes in national and
local government regulation of mining operations, and regulations and other matters. There can
be no assurance that such statements will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements. Accordingly, readers should
not place undue reliance on forward-looking statements. The Company disclaims any intention
or obligation to update or revise any forward-looking statements, whether as a result of new
information, future events or otherwise, except as required by law.