K92 Mining Releases Strong 2020 Q4 & Annual Financial Results - Record Net Cash, Revenue & Throughput Following Commissioning of Stage 2 Plant Expansion

Mine Development & Operations Financials Metallurgy & Processing

Suite 488 – 1090 West Georgia Street

Vancouver, British Columbia

Canada V6E 3V7

Telephone: +1 (604) 687-7130

Facsimile: +1 (604) 608-9110

www.k92mining.com

NEWS RELEASE

K92 MINING RELEASES STRONG 2020 Q4 & ANNUAL FINANCIAL RESULTS -

RECORD NET CASH, REVENUE & THROUGHPUT FOLLOWING COMMISSIONING

OF STAGE 2 PLANT EXPANSION

Vancouver, British Columbia, March 29, 202 1 - K92 Mining Inc . (“ K92” or the “ Company”)

(TSX: KNT; OTCQX: KNTNF) is pleased to announce results from its financial statements for the

three and twelve months ended December 31, 2020.

Safety

• Strong safety record continues and one of the best safety records in the Australasia region since

start of operations.

• Proactive and focused management of COVID -19. K92 continues to operate and has strong

preventative and response plans.

Production

Fourth Quarter 2020

• Record quarterly tonnage of 68,932 tonnes treated, a 127% increase from Q4 2019.

• Record quarterly gold equivalent (“ AuEq”) production of 29,820 oz , or 28,809 oz gold,

493,584 lbs copper and 10,395 oz silver, representing a 26% AuEq increase from Q4 2019(1).

• Cash costs of US$639/oz gold and all-in sustaining costs (“AISC”) of US$768/oz gold ounce(2).

• Long hole stoping on both the K1 and K2 Veins has provided a notable positive impact on

operational flexibility.

Full Year 2020

• Record annual tonnage of 230,365 tonnes treated, an 81% increase from 2019.

• Record annual gold equivalent production of 98,872 oz or 95,109 oz gold, 1,853,078 lbs copper

and 36,067 oz silver, representing a year-over-year AuEq increase of 20%.

• Cash costs of US$651/oz gold and AISC of US$782/oz gold ounce.

Financials

Fourth Quarter 2020

2

• Sold 28,112 oz of gold, 512,203 lbs of copper and 10,594 oz of silver. Gold concentrate

inventories of 5,451 oz as of December 31, 2020, a quarterly decrease of 408 oz.

• Record quarterly revenue of US$48.0 million, increasing 44% from Q4 2019.

• Operating cash flow (before working capital adjustments) for the three months ended December

31, 2020 of US$18.9 million or US$0.09 per share and earnings before interest, taxes,

depreciation and amortization (“EBITDA”) of US$22.7 million or US$0.10 per share.

• Net income for the three months ended December 31, 2020 of US$10.9 million or US$0.05 per

share.

• Quarterly gross margin of 53%.

• Balance sheet significantly strengthened during Q4, with cash increasing by US$10.3 million

to US$51.5 million and debt decreasing by US$2.1 million to US$4.9 million as at December

31, 2020.

Full Year 2020

• Sold 93,273 oz of gold, 1,827,368 lbs of copper and 36,655 oz of silver.

• Record annual revenue of US$159.1 million, increasing 56% from 2019.

• Operating cash flow (before working capital adjustments) for the twelve months ended

December 31, 2020 of US$76.5 million or US$0.35 per share and EBITDA of US$79.6 million

or US$0.37 per share.

• Net income for the twelve months ended December 31, 20 20 of US$42.0 million or US$0.19

per share.

• Annual gross margin of 54%.

Growth

• Successful commissioning of the Stage 2 Plant Expansion to double throughput capacity to

400,000 tonnes per year and continued development of the twin incline following the lifting of

the State of Emergency in June 2020.

• Stage 3 Expansion Preliminary Economic Assessment announced on July 27, 2020, outlining a

potential Tier 1 asset, with ~318,000 ounces per annum AuEq run -rate production at a life of

mine average AISC cost of US$362 per gold ounce net of by-product credits.

o At $1,500/oz gold , $18/oz silver and $3.00/lb copper prices, the estimate after -tax

NPV5% is US$1.5 billion and is fully funded from mine cash flow . At US$1,900/oz

gold prices the estimated after-tax NPV5% is US$2.0 billion.

• Underground development on the Judd Vein #1, marking the first significant exploration

undertaken by K92 on the near-mine infrastructure, underexplored, +2.5km strike vein system.

A Phase 1 underground drill program commenced during the quarter after reporting the

preliminary results.

• Number of drill rigs increased to 10 at the end of the year, with plans to drill Kora, Kora South,

Karempe and Judd epithermal vein systems, plus the Blue Lake porphyry concurrently.

For complete details of the annual audited consolidated financial statements and associated

management’s discussion and analysis, please refer to the Company’s website or profile on SEDAR

(www.sedar.com). All amounts are in U.S. dollars unless otherwise indicated.

3

John Lewins, K92 Chief Executiv e Officer and Director, stated, “2020 represented another

transformational year for K92. In terms of operations, Kainantu delivered record throughput,

production and development, and finished the year particularly strong, with multiple quarterly records

achieved in the fourth quarter. In the third quarter, K92 achieved two major growth milestones: the

completion of the Stage 2 Plant Expansion commissioning, and; the Stage 3 Expansion PEA study. The

Stage 2 Plant Expansion, has already delivered a notable step-change in terms of the capabilities of

the operation, doubling throughput capacity from 200,000 tpa (~550 tpd) to 400,000 tpa (~1,100 tpd).

The Stage 3 Expansion PEA has outlined a Tier 1 Asset, expanding to 1 mtpa throughput with run-rate

production of ~318kozpa AuEq, LOM average AISC of $362/oz Au and capital costs funded from mine

cash flow at $1,500/oz.

On exploration, Kainantu doubled the number of drill rigs to 10, providing a signific ant boost to not

only the rate of drilling but our capacity to drill multiple targets concurrently. In the second half of the

year, this resulted in high grade mineralization recorded at both the underexplored Karempe and Judd

vein systems. The results from Judd are particularly encouraging with JDD0006 recording 7.25 m at

256.09 g/t Au, 113 g/t Ag and 0.42 % Cu (258.01 g/t AuEq, 5.30m true width) on the J1 vein (see

November 9, 2020 press release), representing one of the highest -grade intersections drilled by K92.

Importantly, underground development has supported the Judd drilling results, with the latest 65-metre

development extension on the Judd 1235 Level recording an average 3.8 metres vein thickness at 18.70

g/t AuEq (17.13 g/t Au, 0 .82% Cu and 37 g/t Ag) (see January 26, 2021 press release). Exploration

results have increased our conviction for a higher throughput rate for the Stage 3 Expansion Definitive

Feasibility Study and resulted in more drill rigs being added through 2021.

Lastly, I would like to highlight that this transformational year was achieved in one of the most

challenging environments globally due to the COVID -19 pandemic. The dedication and

resourcefulness of our workforce has been exemplary, and the support of government has also been a

major factor in our success.”

Mine Operating Activities

Three months ended Twelve months ended

December 31, 2020 December 31, 2020

Operating data

Head grade (Au g/t) 14.2 14.0

Gold recovery (%) 91.7% 91.8%

Gold ounces produced 28,809 95,109

Gold ounces equivalent produced (1) 29,820 98,872

Tonnes of copper produced 224 841

Silver ounces produced 10,395 36,067

Financial data (in thousands of dollars)

Gold ounces sold 28,112 93,273

Revenues from concentrate sales US$48,030 US$159,125

Mine operating expenses US$8,534 US$32,773

Other mine expenses US$11,906 US$28,253

Depreciation and depletion US$3,507 US$12,398

4

Statistics (in dollars)

Average realized selling price per ounce, net US$1,792 US$1,692

Cash cost per ounce US$639 US$651

All-in sustaining cost per ounce US$768 US$782

Notes:

(1) Gold equivalent for 2020 based on the following prices: gold $1,500 per ounce; silver $ 17.75

per ounce; and copper $2.70 per pound.

(2) The Company provides some non -international financial reporting standard measures as

supplementary information that management believes may be useful to investors to explain the

Company’s financial results. Please refer to non-IFRS financial performance measures in the

Company’s management’s discussion and analysis dated March 29, 2021, available on SEDAR

or the Company’s website, for reconciliation of these measures.

K92 has not based its production decisions on mineral reserve estimates or feasibility studies, and

historically such projects have increased uncertainty and risk of failure. Mineral resources that are not

mineral reserves do not have demonstrated economic viability.

Conference Call and Webcast to Present Results

K92 will host a conference call and webcast to present the fourth quarter and annual 2020 consolidated

financial results at 8:30 am (EDT) on Monday, March 29, 2021.

• Listeners may access the conference call by dialing toll -free to 1-800-319-4610 within North

America or +1-604-638-5340 from international locations.

• The conference call will also be broadcast live (webcast) and may be accessed via the following

link: http://services.choruscall.ca/links/k92mining20210329.html

Qualified Person

K92 Mine Geology Manager and Mine Exploration Manager, Mr. Andrew Kohler, PGeo, a qualified

person under the meaning of Canadian National Instrument 43 -101 – Standards of Disclosure for

Mineral Projects, has reviewed and is responsible for the technical content of this news release.

About K92

K92 Mining Inc. is engaged in the production of gold, copper and silver from the Kora deposit at the

Kainantu Gold Mine in the Eastern Highlands province of Papua New Guinea, as well as exploration

and development of mineral deposits in the immediate vicinity of the mine. The Company declared

commercial production from Kainantu in February 2018 and is in a strong financial position.

The Company commenced an expansion of the mine based on a n updated Preliminary Econom ic

Assessment on the property which was published in January 2019 and updated in July 2020 . K92 is

5

operated by a team of mining company professionals with extensive international mine -building and

operational experience.

On Behalf of the Company,

John Lewins, Chief Executive Officer and Director

For further information, please contact David Medilek, P.Eng., CFA at +1-604-687-7130.

CAUTIONARY STATEMENT REGARDING FORWARD -LOOKING INFORMATION: This news

release includes certain “forward -looking statements” under applicable Canadian securities

legislation. Forward -looking statements are necessarily based upon a number of estimates and

assumptions that, while considered reasonable, are subject to known and unknown risks, uncertainties,

and other factors which may cause the actual results and future events to differ materially from those

expressed or implied by such forward -looking statements. All statements that address future plans,

activities, events, or developments that the Company believes, expects or anticipates will or may occur

are forward-looking information, including statements regarding the realization of the preliminary

economic analysis for the Kainantu Project , expectations of future cash flows, the planned plant

expansion, production results, cost of sales, sales of production, potential expansion of resources and

the generation of further drilling results which may or may not occur. Forward-looking statements and

information contained herein are based on certain factors and assumptions regarding, among other

things, the market price of the Company’s securities, metal prices, exchange rates, taxation, the

estimation, timing and amount of future exploration and development, capital and operating costs, the

availability of financing, the receipt of regulatory approvals, assumptions contained in the PEA,

environmental risks, title disputes, failure of plant, equipment or processes to operate as anticipated,

accidents, labour disputes, claims and limitations on insurance coverage and other risks of the mining

industry, changes in national and local government regulation of mining operations in PNG, mitigation

of the Covid -19 pandemic, continuation of the lifted state of emergency, and regulations and other

matters. There can be no assurance that such statements will prove to be accurate, as actual results

and future events could differ materially from those anticipated in such statements. Accordingly,

readers should not place undue reliance on forward -looking statements. The Company disclaims any

intention or obligation to update or revise any forward-looking statements, whether as a result of new

information, future events or otherwise, except as required by law.